Veena Smart Homes
by V.D. Infratech Private Limited (Veena) · Kandivali, MumbaiAlso near Kharodi
Possession date of Veena Smart Homes: 31 December 2026, moved from 31 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800032966, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Veena Smart Homes?
How the possession date of Veena Smart Homes has moved
31 December 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA29122519108)
Reason the builder gave MahaRERA:
“The Project has reached an advanced stage of completion, and all major construction and development activities have been substantially completed in compliance with the sanctioned plans and applicable laws. The present application for extens…” Read the full reason
“The Project has reached an advanced stage of completion, and all major construction and development activities have been substantially completed in compliance with the sanctioned plans and applicable laws. The present application for extension of completion date is sought solely for the limited purpose of obtaining the Occupation Certificate (“OC”) from the competent authority and to ensure continued compliance with the provisions of the RERA Act. The application for issuance of the OC in respect of the said Project was duly submitted on 16th December 2025 and the same is currently under co…”
Source: Veena Smart Homes’s extension records on MahaRERA (P51800032966), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Veena Smart Homes
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Veena Smart HomesP51800031045 · possession 30 Jun 2025
- Veena Smart HomesP51800029400 · possession 30 Jun 2025
- MahaRERA registration
- P51800032966
- Status
- Registered and active
- Builder
- V.D. Infratech Private Limited
- Location
- Kandivali, Mumbai · 400067
- Project type
- Others
- Registered on
- 2 Feb 2022
- Completion date at registration
- December 2025
- Latest completion date
- December 2026
- Delay so far
- 12 months
- Homes
- 148
- Sold or booked
- 89%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Veena Smart Homes, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Veena Smart Homes Wing C | 100% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- Veena Smart Homes Wing C: covers 39 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Veena Smart Homes every month.
Veena Smart Homes: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 377 – 625 | 148 |
| Shops | 82 – 229 | 12 |
| Amenity | 586 – 2,390 | 8 |
| Office Space | 482 – 613 | 4 |
- Buildings: Veena Smart Homes Wing C (41 floors, 172 units)
- Land: 5,728 sq m (about 1.4 acres) · sanctioned built-up 9,389 sq m · recreational space 397 sq m
- Boundaries filed include: Babrekar Road
The builder’s record and reviews
Veena Developers (a group of 6 linked companies) has 15 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 6 finished, 4 within the promised date and 2 needed more time (typically 9 months); 7 still being built, 2 past the promised date (typically 14 months late). 14 complaints on MahaRERA across 6 projects.
Read Google reviews of Veena Smart Homes →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Veena Smart Homes: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Veena Smart Homes
What is the possession date of Veena Smart Homes?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Veena Smart Homes in Kandivali, Mumbai is 31 December 2026 — 12 months later than 31 December 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Veena Smart Homes?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Veena Smart Homes's builder has filed on MahaRERA, the official one, is 31 December 2026, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Veena Smart Homes extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Veena Smart Homes's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The Project has reached an advanced stage of completion, and all major construction and development activities have been substantially completed in compliance with the sanctioned plans and applicable laws. The present application for extension of completion date is sought solely for the limited purpose of obtaining the Occupation Certificate (“OC”) from the competent authority and to ensure continued compliance with the provisions of the RERA Act. The application for issuance of the OC in respect of the said Project was duly submitted on 16th December 2025 and the same is currently under co…".
What is the RERA number of Veena Smart Homes?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Veena Smart Homes in Kandivali, Mumbai is P51800032966.
Is Veena Smart Homes registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Veena Smart Homes is registered as P51800032966 and its status is "Registered and active".
What is the construction status of Veena Smart Homes?
According to GharKundli's check of MahaRERA records (updated October 2026), Veena Smart Homes's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Veena Smart Homes Wing C is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Veena Smart Homes have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Veena Smart Homes safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Veena Smart Homes is registered on MahaRERA as P51800032966, its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Veena Smart Homes have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Veena Smart Homes (P51800031045, possession 30 Jun 2025); Veena Smart Homes (P51800029400, possession 30 Jun 2025). Check that your agreement names the registration of your own wing.
How can I get updates if Veena Smart Homes's possession date changes?
The latest dates are on Veena Smart Homes's MahaRERA page (P51800032966). GharKundli's Kundli Watch sends a free WhatsApp update on Veena Smart Homes every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Veena Smart Homes have?
According to GharKundli's check of MahaRERA records (updated October 2026), Veena Smart Homes has one building filed: Veena Smart Homes Wing C with 41 floors and 172 units.
What are the flat sizes (carpet area) in Veena Smart Homes?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Veena Smart Homes: 2 BHK: 377 to 625 sq ft carpet (148 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Veena Smart Homes?
According to GharKundli's check of MahaRERA records (updated October 2026), Veena Smart Homes stands on 5,728 sq m of land (about 1.4 acres), with 9,389 sq m of sanctioned built-up area and 397 sq m of recreational open space.
What is the track record of Veena Smart Homes's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Veena Developers (a group of 6 linked companies) has 15 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 6 finished, 4 within the promised date and 2 needed more time (typically 9 months); 7 still being built, 2 past the promised date (typically 14 months late). 14 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Veena Smart Homes?
Google Maps has reviews of Veena Smart Homes written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Veena Smart Homes?
Veena Smart Homes by V.D. Infratech Private Limited (Veena) is in Kandivali, Mumbai (pincode 400067), near Kharodi, Maharashtra, and is registered on MahaRERA as P51800032966, per GharKundli's check of MahaRERA records. Its boundaries filed there include Babrekar Road.
How many homes are in Veena Smart Homes?
According to GharKundli's check of MahaRERA records (updated October 2026), Veena Smart Homes has 148 homes in 1 tower registered on MahaRERA, and 89% of them are sold or booked.
When was Veena Smart Homes registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Veena Smart Homes was registered on MahaRERA on 2 February 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Veena Smart Homes?
No court cases are listed for Veena Smart Homes on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Veena Smart Homes?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is V.D. Infratech Private Limited, the company Veena files this project under, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Veena Smart Homes
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in pincode 400067
- PRIME SQUARE
- LA SERENA Tower 5, Tower 6 and Tower 7
- CHARKOP SHREE GANESH CHS LTD
- MPR SHRI PARAS DARSHAN
- SAFFRONWOODS CHSL
- SIGMA AMBER
- Avenue Wing B phase 2
- JAYAKAR HOUSE
Other projects by V.D. Infratech Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.