Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.

by SMERA HOMES LLP (Heritage) · Chembur, Mumbai 400071Also near Ghatkopar East, Kurla, Subhash Nagar

What’s in the report? →

Possession: Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. (MahaRERA P51800045578) is marked completed on MahaRERA. It has 7 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800045578. Status: Completed.

Source: MahaRERA website — records for P51800045578, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. has moved

  1. 30 September 2024

    Completion date given when the project was registered

  2. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800024689)

    Reason the builder gave MahaRERA: “we have applied for an occupancy certificate and we are waiting for the same”

Source: Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.’s extension records on MahaRERA (P51800045578), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800045578
Status
Completed
Builder
SMERA HOMES LLP
Location
Chembur, Mumbai · 400071
Project type
Residential / Group Housing
Registered on
24 May 2022
Completion date at registration
September 2024
Latest completion date
June 2025
Delay so far
9 months
Homes
7
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd., as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Balmukund Heritage100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. every 1–2 months.

Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.: buildings, flats and land, as filed on MahaRERA

  • Buildings: Balmukund Heritage (15 floors)
  • Land: 535 sq m (about 0.1 acres) · sanctioned built-up 1,444 sq m
  • Boundaries filed include: Avighna Chsl 14th Road
  • Land, as filed: Plot No. 472 and C.T.S. No. 1339, 1339/1 to 4
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Heritage Lifestyles & Developers (a group of 8 linked companies) has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 9 finished, 2 within the promised date and 7 needed more time (typically 20 months); 7 still being built, 2 past the promised date (typically 10 months late); 3 lapsed. 3 complaints on MahaRERA across 3 projects.

Read Google reviews of Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.

What is the possession date of Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. in Chembur, Mumbai is 30 June 2025 — 9 months later than 30 September 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.'s builder has filed on MahaRERA, the official one, is 30 June 2025, already 9 months later than the 30 September 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.'s builder applied to MahaRERA to extend the completion date once: to 30 June 2025, giving the reason "we have applied for an occupancy certificate and we are waiting for the same".

What is the RERA number of Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. in Chembur, Mumbai is P51800045578.

Is Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. is registered as P51800045578 and its status is "Completed".

What is the current construction status of Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.'s status on MahaRERA is "Completed". As filed by the builder, slab work on Balmukund Heritage is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. is registered on MahaRERA as P51800045578, its MahaRERA status is "Completed", its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.?

For a flat in Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. completed?

According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. is marked completed on MahaRERA, and the completion date filed there is 30 June 2025. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.'s possession date changes?

The latest dates are on Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.'s MahaRERA page (P51800045578). GharKundli's Kundli Watch sends a free WhatsApp update on Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. have?

According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. has one building filed: Balmukund Heritage with 15 floors.

How big is the land of Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. stands on 535 sq m of land (about 0.1 acres), with 1,444 sq m of sanctioned built-up area.

What is the track record of Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.'s builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Heritage Lifestyles & Developers (a group of 8 linked companies) has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 9 finished, 2 within the promised date and 7 needed more time (typically 20 months); 7 still being built, 2 past the promised date (typically 10 months late); 3 lapsed. 3 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.?

Google Maps has reviews of Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.?

Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. by SMERA HOMES LLP (Heritage) is in Chembur, Mumbai, pincode 400071 (near Ghatkopar East, Kurla, Subhash Nagar), Maharashtra, and is registered on MahaRERA as P51800045578, per GharKundli's check of MahaRERA records. Its boundaries filed there include Avighna Chsl 14th Road. Its land is filed as Plot No. 472 and C.T.S. No. 1339, 1339/1 to 4. GharKundli lists all 318 MahaRERA projects in Chembur (400071).

How many flats are in Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. has 7 homes in 1 tower registered on MahaRERA.

When was Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. was registered on MahaRERA on 24 May 2022. GharKundli did not find a title report on the land on file there.

Does Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. have any legal issues or court cases?

No court cases are listed for Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd. on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SMERA HOMES LLP, the company Heritage files this project under, which has 2 other projects registered on MahaRERA.