Kandivali Neelayalam Co op Housing Society Ltd

by Sapriya Developers (Supreme) · Kandivali West, Mumbai 400067Also near Borivali

What’s in the report? →

Possession date of Kandivali Neelayalam Co op Housing Society Ltd (MahaRERA P51800034690): 31 December 2025, moved from 31 March 2024 (21 months later), and it has already passed. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800034690. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800034690, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about Kandivali Neelayalam Co op Housing Society Ltd?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Kandivali Neelayalam Co op Housing Society Ltd has moved

  1. 31 March 2024

    Completion date given when the project was registered

  2. 30 March 2025

    Extended at the builder's request (MahaRERA application EXT51800019340)

    Reason the builder gave MahaRERA:
    “Earlier the parking system was comprising of 2 PIT+ Puzzle parking. Due to local soil condition not favourable for 2 level pit parking, the aprking system was revised and now the parking is proposed as puzzle parking without pit within the…” Read the full reason“Earlier the parking system was comprising of 2 PIT+ Puzzle parking. Due to local soil condition not favourable for 2 level pit parking, the aprking system was revised and now the parking is proposed as puzzle parking without pit within the building line and cantilevered parking. Subsequently revised concessions and approvals granted by BMC. Revised foudnation drawings are prepared for proposing pile foundation. Therefore in leiu of said changes we seek extension”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800028008)

    Reason the builder gave MahaRERA: “Reason for delay as per covering letter.”

Source: Kandivali Neelayalam Co op Housing Society Ltd’s extension records on MahaRERA (P51800034690), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Kandivali Neelayalam Co op Housing Society Ltd

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800034690
Status
Lapsed (registration period ended)
Builder
Sapriya Developers
Location
Kandivali West, Mumbai · 400067
Project type
Others
Registered on
20 Apr 2022
Completion date at registration
March 2024
Latest completion date
December 2025
Delay so far
21 months
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Kandivali Neelayalam Co op Housing Society Ltd, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Kandivali Neelayalam Co op Housing Society Ltd100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kandivali Neelayalam Co op Housing Society Ltd every 1–2 months.

Kandivali Neelayalam Co op Housing Society Ltd: buildings, flats and land, as filed on MahaRERA

  • Buildings: Kandivali Neelayalam Co op Housing Society Ltd (10 floors)
  • Land: 470 sq m (about 0.1 acres) · sanctioned built-up 1,297 sq m
  • Land, as filed: Plot no 76,CTS No 942 of Village Kandivali
  • Map: Get directions

The builder’s record and reviews

Sapriya Developers (a group of 5 linked companies) has 8 projects on MahaRERA since 2019, this one included. Of the 8 GharKundli has checked: 7 finished, 5 within the promised date and 2 needed more time (typically 13 months); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Kandivali Neelayalam Co op Housing Society Ltd →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Kandivali Neelayalam Co op Housing Society Ltd: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Kandivali Neelayalam Co op Housing Society Ltd

What is the possession date of Kandivali Neelayalam Co op Housing Society Ltd?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kandivali Neelayalam Co op Housing Society Ltd in Kandivali West, Mumbai is 31 December 2025 — 21 months later than 31 March 2024, the date given at registration. That date has already passed.

The date has already moved 21 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Kandivali Neelayalam Co op Housing Society Ltd?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Kandivali Neelayalam Co op Housing Society Ltd's builder has filed on MahaRERA, the official one, is 31 December 2025, already 21 months later than the 31 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Kandivali Neelayalam Co op Housing Society Ltd extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Neelayalam Co op Housing Society Ltd's builder applied to MahaRERA to extend the completion date 2 times: to 30 March 2025, giving the reason "Earlier the parking system was comprising of 2 PIT+ Puzzle parking. Due to local soil condition not favourable for 2 level pit parking, the aprking system was revised and now the parking is proposed as puzzle parking without pit within the building line and cantilevered parking. Subsequently revised concessions and approvals granted by BMC. Revised foudnation drawings are prepared for proposing pile foundation. Therefore in leiu of said changes we seek extension"; to 31 December 2025, giving the reason "Reason for delay as per covering letter.".

What is the RERA number of Kandivali Neelayalam Co op Housing Society Ltd?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kandivali Neelayalam Co op Housing Society Ltd in Kandivali West, Mumbai is P51800034690.

Is Kandivali Neelayalam Co op Housing Society Ltd registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Neelayalam Co op Housing Society Ltd is registered as P51800034690 and its status is "Lapsed (registration period ended)".

What is the current construction status of Kandivali Neelayalam Co op Housing Society Ltd? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Neelayalam Co op Housing Society Ltd's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Kandivali Neelayalam Co op Housing Society Ltd is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Kandivali Neelayalam Co op Housing Society Ltd have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Kandivali Neelayalam Co op Housing Society Ltd safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Neelayalam Co op Housing Society Ltd is registered on MahaRERA as P51800034690, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 21 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Kandivali Neelayalam Co op Housing Society Ltd?

Kandivali Neelayalam Co op Housing Society Ltd isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Kandivali Neelayalam Co op Housing Society Ltd?

For a flat in Kandivali Neelayalam Co op Housing Society Ltd (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Kandivali Neelayalam Co op Housing Society Ltd received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Neelayalam Co op Housing Society Ltd isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Kandivali Neelayalam Co op Housing Society Ltd?

According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Neelayalam Co op Housing Society Ltd's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Kandivali Neelayalam Co op Housing Society Ltd uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Kandivali Neelayalam Co op Housing Society Ltd was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Kandivali Neelayalam Co op Housing Society Ltd's possession date changes?

The latest dates are on Kandivali Neelayalam Co op Housing Society Ltd's MahaRERA page (P51800034690). GharKundli's Kundli Watch sends a free WhatsApp update on Kandivali Neelayalam Co op Housing Society Ltd every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Kandivali Neelayalam Co op Housing Society Ltd have?

According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Neelayalam Co op Housing Society Ltd has one building filed: Kandivali Neelayalam Co op Housing Society Ltd with 10 floors.

How big is the land of Kandivali Neelayalam Co op Housing Society Ltd?

According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Neelayalam Co op Housing Society Ltd stands on 470 sq m of land (about 0.1 acres), with 1,297 sq m of sanctioned built-up area.

What is the track record of Kandivali Neelayalam Co op Housing Society Ltd's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sapriya Developers (a group of 5 linked companies) has 8 projects on MahaRERA since 2019, this one included. Of the 8 GharKundli has checked: 7 finished, 5 within the promised date and 2 needed more time (typically 13 months); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Kandivali Neelayalam Co op Housing Society Ltd?

Google Maps has reviews of Kandivali Neelayalam Co op Housing Society Ltd written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Kandivali Neelayalam Co op Housing Society Ltd?

Kandivali Neelayalam Co op Housing Society Ltd by Sapriya Developers (Supreme) is in Kandivali West, Mumbai, pincode 400067 (near Borivali), Maharashtra, and is registered on MahaRERA as P51800034690, per GharKundli's check of MahaRERA records. Its land is filed as Plot no 76,CTS No 942 of Village Kandivali. GharKundli lists all 318 MahaRERA projects in Kandivali West (400067).

When was Kandivali Neelayalam Co op Housing Society Ltd registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Neelayalam Co op Housing Society Ltd was registered on MahaRERA on 20 April 2022. GharKundli did not find a title report on the land on file there.

Does Kandivali Neelayalam Co op Housing Society Ltd have any legal issues or court cases?

No court cases are listed for Kandivali Neelayalam Co op Housing Society Ltd on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Kandivali Neelayalam Co op Housing Society Ltd?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sapriya Developers, the company Supreme files this project under, which has 3 other projects registered on MahaRERA.

Other projects in Kandivali West (400067)

All 318 projects in Kandivali West (400067) →

Other projects by Sapriya Developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.