Chembur Deep Jyoti CHS LTD
by P M DEVELOPERS · Chembur, Mumbai 400071Also near Govandi, Kurla, Ghatkopar East
What’s in the report? →Possession date of Chembur Deep Jyoti CHS LTD (MahaRERA P51800047359): 30 November 2027, moved from 31 July 2026 (12 months later). It has 116 homes (1 BHK, 2 BHK and 3 BHK, 432–1043 sq ft carpet), 85% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800047359, and currently active. Its completion date has moved from July 2026 to November 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800047359, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Chembur Deep Jyoti CHS LTD?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Chembur Deep Jyoti CHS LTD has moved
31 July 2026
Completion date given when the project was registered
31 July 2027
Extended at the builder's request (MahaRERA application EA09072621707)
Reason the builder gave MahaRERA: “DUE TO SHORTAGE OF FUNDS WORK COULD NOT BE COMPLETED ON TIME BUT NOW WORK IS ABOUT TO GET COMPLETE, SO WE NEED EXTENSION TILL 31-07-2027”
30 November 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Chembur Deep Jyoti CHS LTD’s extension records on MahaRERA (P51800047359), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Chembur Deep Jyoti CHS LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800047359
- Status
- Registered and active
- Builder
- P M DEVELOPERS
- Location
- Chembur, Mumbai · 400071
- Project type
- Others
- Registered on
- 27 Oct 2022
- Completion date at registration
- July 2026
- Latest completion date
- November 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 116
- Sold or booked
- 85%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Chembur Deep Jyoti CHS LTD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| CHEMBUR DEEP JYOTI CHS LTD | 100% | 100% | 100% | 80% |
Commencement certificate (CC), as filed on MahaRERA
- CHEMBUR DEEP JYOTI CHS LTD: covers 15 floors
Latest CC order on MahaRERA: dated 24/04/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Chembur Deep Jyoti CHS LTD every 1–2 months.
Chembur Deep Jyoti CHS LTD: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 577 – 772 | 85 |
| 3 BHK | 876 – 1,043 | 30 |
| Shops | 114 – 710 | 6 |
| Office Space | 287 – 595 | 2 |
| 1 BHK | 432 | 1 |
- Buildings: CHEMBUR DEEP JYOTI CHS LTD (18 floors, 124 units)
- Car parking: 115 covered
- Land: 1,275 sq m (about 0.3 acres) · sanctioned built-up 8,938 sq m
- Land, as filed: CTS No. 826 (pt) / S NO. 67 TO 71
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
OM SAI Enterprises (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 2 past the promised date (typically 58 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Chembur Deep Jyoti CHS LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Chembur Deep Jyoti CHS LTD: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Chembur Deep Jyoti CHS LTD
What is the possession date of Chembur Deep Jyoti CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Chembur Deep Jyoti CHS LTD in Chembur, Mumbai is 30 November 2027 — 12 months later than 31 July 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Chembur Deep Jyoti CHS LTD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Chembur Deep Jyoti CHS LTD's builder has filed on MahaRERA, the official one, is 30 November 2027, already 12 months later than the 31 July 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Chembur Deep Jyoti CHS LTD extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Chembur Deep Jyoti CHS LTD's builder applied to MahaRERA to extend the completion date once: to 31 July 2027, giving the reason "DUE TO SHORTAGE OF FUNDS WORK COULD NOT BE COMPLETED ON TIME BUT NOW WORK IS ABOUT TO GET COMPLETE, SO WE NEED EXTENSION TILL 31-07-2027". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Chembur Deep Jyoti CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Chembur Deep Jyoti CHS LTD in Chembur, Mumbai is P51800047359.
Is Chembur Deep Jyoti CHS LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Chembur Deep Jyoti CHS LTD is registered as P51800047359 and its status is "Registered and active".
What is the current construction status of Chembur Deep Jyoti CHS LTD? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Chembur Deep Jyoti CHS LTD's status on MahaRERA is "Registered and active". As filed by the builder, slab work on CHEMBUR DEEP JYOTI CHS LTD is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Chembur Deep Jyoti CHS LTD have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Chembur Deep Jyoti CHS LTD safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Chembur Deep Jyoti CHS LTD is registered on MahaRERA as P51800047359, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Chembur Deep Jyoti CHS LTD?
Chembur Deep Jyoti CHS LTD is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Chembur Deep Jyoti CHS LTD are 432 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Chembur Deep Jyoti CHS LTD?
For a flat in Chembur Deep Jyoti CHS LTD (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Chembur Deep Jyoti CHS LTD received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Chembur Deep Jyoti CHS LTD is still under construction, with 30 November 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Chembur Deep Jyoti CHS LTD uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Chembur Deep Jyoti CHS LTD was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Chembur Deep Jyoti CHS LTD's possession date changes?
The latest dates are on Chembur Deep Jyoti CHS LTD's MahaRERA page (P51800047359). GharKundli's Kundli Watch sends a free WhatsApp update on Chembur Deep Jyoti CHS LTD every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Chembur Deep Jyoti CHS LTD have?
According to GharKundli's check of MahaRERA records (updated October 2026), Chembur Deep Jyoti CHS LTD has one building filed: CHEMBUR DEEP JYOTI CHS LTD with 18 floors and 124 units.
What are the flat sizes (carpet area) in Chembur Deep Jyoti CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Chembur Deep Jyoti CHS LTD: 2 BHK: 577 to 772 sq ft carpet (85 homes); 3 BHK: 876 to 1043 sq ft carpet (30 homes); 1 BHK: 432 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Chembur Deep Jyoti CHS LTD have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 115 covered car parking spaces for Chembur Deep Jyoti CHS LTD.
How big is the land of Chembur Deep Jyoti CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), Chembur Deep Jyoti CHS LTD stands on 1,275 sq m of land (about 0.3 acres), with 8,938 sq m of sanctioned built-up area.
What is the track record of Chembur Deep Jyoti CHS LTD's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), OM SAI Enterprises (a group of 4 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 2 past the promised date (typically 58 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Chembur Deep Jyoti CHS LTD?
Google Maps has reviews of Chembur Deep Jyoti CHS LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Chembur Deep Jyoti CHS LTD?
Chembur Deep Jyoti CHS LTD by P M DEVELOPERS is in Chembur, Mumbai, pincode 400071 (near Govandi, Kurla, Ghatkopar East), Maharashtra, and is registered on MahaRERA as P51800047359, per GharKundli's check of MahaRERA records. Its land is filed as CTS No. 826 (pt) / S NO. 67 TO 71. GharKundli lists all 318 MahaRERA projects in Chembur (400071).
How many flats are in Chembur Deep Jyoti CHS LTD, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Chembur Deep Jyoti CHS LTD has 116 homes in 1 tower registered on MahaRERA, and 85% of them are sold or booked.
When was Chembur Deep Jyoti CHS LTD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Chembur Deep Jyoti CHS LTD was registered on MahaRERA on 27 October 2022. GharKundli did not find a title report on the land on file there.
Does Chembur Deep Jyoti CHS LTD have any legal issues or court cases?
No court cases are listed for Chembur Deep Jyoti CHS LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Chembur Deep Jyoti CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is P M DEVELOPERS, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Chembur Deep Jyoti CHS LTD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Chembur (400071)
- Shree Saraswati CHS LTD Plot 8B
- Icons 71
- Viera Golf Greens
- Arham Mourya
- 71 Pardis
- Tulsi Chamber Phase II
- Queens Park
- Sampoorna
Other projects by P M DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.