Possession date of Kandivali Hanuman Co-op Housing Society Ltd. (MahaRERA P51800050192): 18 March 2027. It has 59 homes (1 BHK, 423–427 sq ft carpet), 47% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800050192, and currently active. Its completion date is now March 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800050192, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Kandivali Hanuman Co-op Housing Society Ltd.?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Kandivali Hanuman Co-op Housing Society Ltd. has moved

  1. 18 November 2026

    Completion date given when the project was registered

  2. 18 March 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Kandivali Hanuman Co-op Housing Society Ltd.’s extension records on MahaRERA (P51800050192), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Kandivali Hanuman Co-op Housing Society Ltd.

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800050192
Status
Registered and active
Builder
Kandivali Hanuman Co-op Housing Society Ltd.
Location
Patel Nagar Kandivali West, Mumbai · 400067
Project type
Residential / Group Housing
Registered on
21 Mar 2023
Completion date at registration
November 2026
Latest completion date
March 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
59
Sold or booked
47%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Kandivali Hanuman Co-op Housing Society Ltd., as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Kandivali Hanuman Co-op Housing Society Ltd100%100%95%50%

Commencement certificate (CC), as filed on MahaRERA

  • Kandivali Hanuman Co-op Housing Society Ltd: covers 15 floors

Latest CC order on MahaRERA: dated 02/05/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kandivali Hanuman Co-op Housing Society Ltd. every 1–2 months.

Kandivali Hanuman Co-op Housing Society Ltd.: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK423 – 42759
  • Buildings: Kandivali Hanuman Co-op Housing Society Ltd (16 floors, 59 units)
  • Land: 1,031 sq m (about 0.3 acres) · sanctioned built-up 2,574 sq m · recreational space 207 sq m
  • Land, as filed: 1095 A/1(pt)
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Kandivali Hanuman Co-op Housing Society Ltd. →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Kandivali Hanuman Co-op Housing Society Ltd.: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Kandivali Hanuman Co-op Housing Society Ltd.

What is the possession date of Kandivali Hanuman Co-op Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kandivali Hanuman Co-op Housing Society Ltd. in Patel Nagar Kandivali West, Mumbai is 18 March 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Kandivali Hanuman Co-op Housing Society Ltd.?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Kandivali Hanuman Co-op Housing Society Ltd.'s builder has filed on MahaRERA, the official one, is 18 March 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Kandivali Hanuman Co-op Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kandivali Hanuman Co-op Housing Society Ltd. in Patel Nagar Kandivali West, Mumbai is P51800050192.

Is Kandivali Hanuman Co-op Housing Society Ltd. registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Hanuman Co-op Housing Society Ltd. is registered as P51800050192 and its status is "Registered and active".

What is the current construction status of Kandivali Hanuman Co-op Housing Society Ltd.? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Hanuman Co-op Housing Society Ltd.'s status on MahaRERA is "Registered and active". As filed by the builder, slab work on Kandivali Hanuman Co-op Housing Society Ltd is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does Kandivali Hanuman Co-op Housing Society Ltd. have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Kandivali Hanuman Co-op Housing Society Ltd. safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Hanuman Co-op Housing Society Ltd. is registered on MahaRERA as P51800050192, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Kandivali Hanuman Co-op Housing Society Ltd.?

Kandivali Hanuman Co-op Housing Society Ltd. is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Kandivali Hanuman Co-op Housing Society Ltd. are 423 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Kandivali Hanuman Co-op Housing Society Ltd.?

For a flat in Kandivali Hanuman Co-op Housing Society Ltd. (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Kandivali Hanuman Co-op Housing Society Ltd. received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Hanuman Co-op Housing Society Ltd. is still under construction, with 18 March 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Kandivali Hanuman Co-op Housing Society Ltd. a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Hanuman Co-op Housing Society Ltd.'s planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.

Has Kandivali Hanuman Co-op Housing Society Ltd. uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Kandivali Hanuman Co-op Housing Society Ltd. was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Kandivali Hanuman Co-op Housing Society Ltd.'s possession date changes?

The latest dates are on Kandivali Hanuman Co-op Housing Society Ltd.'s MahaRERA page (P51800050192). GharKundli's Kundli Watch sends a free WhatsApp update on Kandivali Hanuman Co-op Housing Society Ltd. every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Kandivali Hanuman Co-op Housing Society Ltd. have?

According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Hanuman Co-op Housing Society Ltd. has one building filed: Kandivali Hanuman Co-op Housing Society Ltd with 16 floors and 59 units.

What are the flat sizes (carpet area) in Kandivali Hanuman Co-op Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Kandivali Hanuman Co-op Housing Society Ltd.: 1 BHK: 423 to 427 sq ft carpet (59 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Kandivali Hanuman Co-op Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Hanuman Co-op Housing Society Ltd. stands on 1,031 sq m of land (about 0.3 acres), with 2,574 sq m of sanctioned built-up area and 207 sq m of recreational open space.

What are the reviews of Kandivali Hanuman Co-op Housing Society Ltd.?

Google Maps has reviews of Kandivali Hanuman Co-op Housing Society Ltd. written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Kandivali Hanuman Co-op Housing Society Ltd.?

Kandivali Hanuman Co-op Housing Society Ltd. by Kandivali Hanuman Co-op Housing Society Ltd. is in Patel Nagar Kandivali West, Mumbai, pincode 400067 (near Borivali), Maharashtra, and is registered on MahaRERA as P51800050192, per GharKundli's check of MahaRERA records. Its land is filed as 1095 A/1(pt). GharKundli lists all 318 MahaRERA projects in Kandivali West (400067).

How many flats are in Kandivali Hanuman Co-op Housing Society Ltd., and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Hanuman Co-op Housing Society Ltd. has 59 homes in 1 tower registered on MahaRERA, and 47% of them are sold or booked.

When was Kandivali Hanuman Co-op Housing Society Ltd. registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kandivali Hanuman Co-op Housing Society Ltd. was registered on MahaRERA on 21 March 2023. GharKundli did not find a title report on the land on file there.

Does Kandivali Hanuman Co-op Housing Society Ltd. have any legal issues or court cases?

No court cases are listed for Kandivali Hanuman Co-op Housing Society Ltd. on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Kandivali Hanuman Co-op Housing Society Ltd.?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Kandivali Hanuman Co-op Housing Society Ltd..

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Kandivali West (400067)

All 318 projects in Kandivali West (400067) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.