Aishwarya Optima
by Aishwarya Associates LLP · Mulund West, Mumbai 400080Also near Bhandup West, Off Dmart, Wagle I.E
What’s in the report? →Possession date of Aishwarya Optima (MahaRERA P51800050999): 29 August 2027, moved from 30 April 2026 (12 months later). It has 72 homes (1 BHK, 1 Room Kitchen and 2 BHK, 343–1029 sq ft carpet), 18% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800050999, and currently active. Its completion date has moved from April 2026 to August 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800050999, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Aishwarya Optima?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Aishwarya Optima has moved
30 April 2026
Completion date given when the project was registered
29 April 2027
Extended at the builder's request (MahaRERA application EXT51800024713)
Reason the builder gave MahaRERA: “No Inventory Sold - Due to change in Team we are taking Extension for additional 12 Months”
29 August 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Aishwarya Optima’s extension records on MahaRERA (P51800050999), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Aishwarya Optima
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the August 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800050999
- Status
- Registered and active
- Builder
- Aishwarya Associates LLP
- Location
- Mulund West, Mumbai · 400080
- Project type
- Residential / Group Housing
- Registered on
- 19 May 2023
- Completion date at registration
- April 2026
- Latest completion date
- August 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 72
- Sold or booked
- 18%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Aishwarya Optima, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Aishwarya Optima | 100% | 100% | 88% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Aishwarya Optima: covers 19 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aishwarya Optima every 1–2 months.
Aishwarya Optima: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 474 – 910 | 59 |
| 1 BHK | 348 – 505 | 10 |
| 3 BHK | 1,011 – 1,029 | 2 |
| 1 Room Kitchen | 343 | 1 |
- Buildings: Aishwarya Optima (18 floors, 72 units)
- Land: 1,254 sq m (about 0.3 acres) · sanctioned built-up 3,772 sq m
- Boundaries filed include: Murar Road
- Land, as filed: 1132/A Pt
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Shree Samruddhi Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 2 months late); 1 lapsed. 8 complaints on MahaRERA across 1 project.
Read Google reviews of Aishwarya Optima →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Aishwarya Optima: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Aishwarya Optima
What is the possession date of Aishwarya Optima?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Aishwarya Optima in Mulund West, Mumbai is 29 August 2027 — 12 months later than 30 April 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Aishwarya Optima?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Aishwarya Optima's builder has filed on MahaRERA, the official one, is 29 August 2027, already 12 months later than the 30 April 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Aishwarya Optima extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Aishwarya Optima's builder applied to MahaRERA to extend the completion date once: to 29 April 2027, giving the reason "No Inventory Sold - Due to change in Team we are taking Extension for additional 12 Months". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Aishwarya Optima?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Aishwarya Optima in Mulund West, Mumbai is P51800050999.
Is Aishwarya Optima registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Aishwarya Optima is registered as P51800050999 and its status is "Registered and active".
What is the current construction status of Aishwarya Optima? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Aishwarya Optima's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Aishwarya Optima is 100% done and internal work 88%. GharKundli's full report compares construction progress with the deadline.
Does Aishwarya Optima have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Aishwarya Optima safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Aishwarya Optima is registered on MahaRERA as P51800050999, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Aishwarya Optima?
Aishwarya Optima is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Aishwarya Optima are 343 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Aishwarya Optima?
For a flat in Aishwarya Optima (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Aishwarya Optima received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Aishwarya Optima is still under construction, with 29 August 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Aishwarya Optima uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Aishwarya Optima was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Aishwarya Optima's possession date changes?
The latest dates are on Aishwarya Optima's MahaRERA page (P51800050999). GharKundli's Kundli Watch sends a free WhatsApp update on Aishwarya Optima every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Aishwarya Optima have?
According to GharKundli's check of MahaRERA records (updated October 2026), Aishwarya Optima has one building filed: Aishwarya Optima with 18 floors and 72 units.
What are the flat sizes (carpet area) in Aishwarya Optima?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Aishwarya Optima: 2 BHK: 474 to 910 sq ft carpet (59 homes); 1 BHK: 348 to 505 sq ft carpet (10 homes); 3 BHK: 1011 to 1029 sq ft carpet (2 homes); 1 Room Kitchen: 343 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Aishwarya Optima?
According to GharKundli's check of MahaRERA records (updated October 2026), Aishwarya Optima stands on 1,254 sq m of land (about 0.3 acres), with 3,772 sq m of sanctioned built-up area.
What is the track record of Aishwarya Optima's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Samruddhi Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 2 months late); 1 lapsed. 8 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Aishwarya Optima?
Google Maps has reviews of Aishwarya Optima written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Aishwarya Optima?
Aishwarya Optima by Aishwarya Associates LLP is in Mulund West, Mumbai, pincode 400080 (near Bhandup West, Off Dmart, Wagle I.E), Maharashtra, and is registered on MahaRERA as P51800050999, per GharKundli's check of MahaRERA records. Its boundaries filed there include Murar Road. Its land is filed as 1132/A Pt. GharKundli lists all 303 MahaRERA projects in Mulund West (400080).
How many flats are in Aishwarya Optima, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Aishwarya Optima has 72 homes in 1 tower registered on MahaRERA, and 18% of them are sold or booked.
When was Aishwarya Optima registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Aishwarya Optima was registered on MahaRERA on 19 May 2023. GharKundli did not find a title report on the land on file there.
Does Aishwarya Optima have any legal issues or court cases?
No court cases are listed for Aishwarya Optima on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Aishwarya Optima?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Aishwarya Associates LLP.
Check it yourself on MahaRERA
- How to check the possession date of Aishwarya Optima
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Mulund West (400080)
- Malhar Guide
- Arihant Royale
- The Sanctuary - Tower 5
- Keshavpada
- Dhanraj Tower
- Old Hemant Villa Co. Op. Housing Soc. LTD.
- Madhuvan Nivanta
- Shraddha Paradise Enclave
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.