Heritage Signature
by Heritage Homes · Chembur, Mumbai 400071Also near Kurla, Fci
What’s in the report? →Possession date of Heritage Signature (MahaRERA P51800049456): 31 July 2026, moved from 1 May 2025 (10 months later), and it has already passed. It has 11 homes (3 BHK, 845–1044 sq ft carpet), 27% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800049456. Status: Lapsed (registration period ended). Its completion date has moved from May 2025 to July 2026: 10 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800049456, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (July 2026) has passed.
What do you want to know about Heritage Signature?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Heritage Signature has moved
1 May 2025
Completion date given when the project was registered
31 March 2026
Extended at the builder's request (MahaRERA application EXT51800028249)
Reason the builder gave MahaRERA:
“The project faced delays due to slow MCGM approvals, supply chain disruptions, labour shortages, and unexpected technical issues. These challenges affected construction timelines despite efforts to maintain progress and uphold safety and qu…” Read the full reason
“The project faced delays due to slow MCGM approvals, supply chain disruptions, labour shortages, and unexpected technical issues. These challenges affected construction timelines despite efforts to maintain progress and uphold safety and quality standards.”31 July 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Heritage Signature’s extension records on MahaRERA (P51800049456), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Heritage Signature
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800049456
- Status
- Lapsed (registration period ended)
- Builder
- Heritage Homes
- Location
- Chembur, Mumbai · 400071
- Project type
- Residential / Group Housing
- Registered on
- 14 Feb 2023
- Completion date at registration
- May 2025
- Latest completion date
- July 2026
- Delay so far
- 10 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 11
- Sold or booked
- 27%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Heritage Signature, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Heritage Signature | 100% | 100% | 95% | 80% |
Commencement certificate (CC), as filed on MahaRERA
- Heritage Signature: covers 13 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Heritage Signature every 1–2 months.
Heritage Signature: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Other | 845 | 6 |
| 3 BHK | 1,044 | 5 |
- Buildings: Heritage Signature (15 floors, 11 units)
- Land: 700 sq m (about 0.2 acres)
- Land, as filed: 992,992/1-6
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Heritage Lifestyles & Developers (a group of 8 linked companies) has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 9 finished, 2 within the promised date and 7 needed more time (typically 20 months); 7 still being built, 2 past the promised date (typically 10 months late); 3 lapsed. 3 complaints on MahaRERA across 3 projects.
Read Google reviews of Heritage Signature →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Heritage Signature: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Heritage Signature
What is the possession date of Heritage Signature?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Heritage Signature in Chembur, Mumbai is 31 July 2026 — 10 months later than 1 May 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
The date has already moved 10 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Heritage Signature?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Heritage Signature's builder has filed on MahaRERA, the official one, is 31 July 2026, already 10 months later than the 1 May 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Heritage Signature extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Heritage Signature's builder applied to MahaRERA to extend the completion date once: to 31 March 2026, giving the reason "The project faced delays due to slow MCGM approvals, supply chain disruptions, labour shortages, and unexpected technical issues. These challenges affected construction timelines despite efforts to maintain progress and uphold safety and quality standards.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Heritage Signature?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Heritage Signature in Chembur, Mumbai is P51800049456.
Is Heritage Signature registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Heritage Signature is registered as P51800049456 and its status is "Lapsed (registration period ended)".
What is the current construction status of Heritage Signature? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Heritage Signature's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Heritage Signature is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does Heritage Signature have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Heritage Signature safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Heritage Signature is registered on MahaRERA as P51800049456, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 10 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Heritage Signature?
Heritage Signature isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Heritage Signature start at 845 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Heritage Signature?
For a flat in Heritage Signature (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Heritage Signature received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Heritage Signature isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 July 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Heritage Signature?
According to GharKundli's check of MahaRERA records (updated October 2026), Heritage Signature's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 July 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Is Heritage Signature a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Heritage Signature's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.
Has Heritage Signature uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Heritage Signature was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Heritage Signature's possession date changes?
The latest dates are on Heritage Signature's MahaRERA page (P51800049456). GharKundli's Kundli Watch sends a free WhatsApp update on Heritage Signature every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Heritage Signature have?
According to GharKundli's check of MahaRERA records (updated October 2026), Heritage Signature has one building filed: Heritage Signature with 15 floors and 11 units.
What are the flat sizes (carpet area) in Heritage Signature?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Heritage Signature: Other: 845 sq ft carpet (6 homes); 3 BHK: 1044 sq ft carpet (5 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Heritage Signature?
According to GharKundli's check of MahaRERA records (updated October 2026), Heritage Signature stands on 700 sq m of land (about 0.2 acres).
What is the track record of Heritage Signature's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Heritage Lifestyles & Developers (a group of 8 linked companies) has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 9 finished, 2 within the promised date and 7 needed more time (typically 20 months); 7 still being built, 2 past the promised date (typically 10 months late); 3 lapsed. 3 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Heritage Signature?
Google Maps has reviews of Heritage Signature written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Heritage Signature?
Heritage Signature by Heritage Homes is in Chembur, Mumbai, pincode 400071 (near Kurla, Fci), Maharashtra, and is registered on MahaRERA as P51800049456, per GharKundli's check of MahaRERA records. Its land is filed as 992,992/1-6. GharKundli lists all 318 MahaRERA projects in Chembur (400071).
How many flats are in Heritage Signature, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Heritage Signature has 11 homes in 1 tower registered on MahaRERA, and 27% of them are sold or booked.
When was Heritage Signature registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Heritage Signature was registered on MahaRERA on 14 February 2023. GharKundli did not find a title report on the land on file there.
Does Heritage Signature have any legal issues or court cases?
No court cases are listed for Heritage Signature on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Heritage Signature?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Heritage Homes.
Check it yourself on MahaRERA
- How to check the possession date of Heritage Signature
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Chembur (400071)
- 71 Pardis
- Tulsi Chamber Phase II
- Queens Park
- Sampoorna
- Shree Saraswati CHS LTD Plot 8B
- Icons 71
- Viera Golf Greens
- Arham Mourya
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.