by Vira Infratech and Developers Private Limited · Vile Parle East, Mumbai 400057Also near Vile Parle West, Vileparle East, Borivali West

What’s in the report? →

Possession date of Vira Park View (MahaRERA P51800049141): 10 December 2026, moved from 31 December 2024 (24 months later). It has 19 homes (2 BHK, 3 BHK and 4 BHK, 270–1736 sq ft carpet), 91% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800049141, and currently active.

Source: MahaRERA website — records for P51800049141, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Vira Park View?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Vira Park View has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 30 July 2025

    Extended at the builder's request (MahaRERA application EXT51800027501)

    Reason the builder gave MahaRERA:
    “1. We would like to inform that almost all of the work has been done in the project. The main challenges we were facing delay in completion was due to shortage of skilled labors, because of that we could not complete the project as per spec…” Read the full reason“1. We would like to inform that almost all of the work has been done in the project. The main challenges we were facing delay in completion was due to shortage of skilled labors, because of that we could not complete the project as per specified date 2. We are in completion stage as we are addressing stricter contractor oversight, communication with the project team and seeing the labors sources actively to ensure the completion of the projects. We appreciate your understanding ind support to resolve the challenges we face and to ensure the project completion before 30/07/2025.”
  3. 10 December 2026

    Extended at the builder's request (MahaRERA application EA10092622504)

    Reason the builder gave MahaRERA: “OC Recived”

Source: Vira Park View’s extension records on MahaRERA (P51800049141), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Vira Park View

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800049141
Status
Registered and active
Builder
Vira Infratech and Developers Private Limited
Location
Vile Parle East, Mumbai · 400057
Project type
Others
Registered on
1 Feb 2023
Completion date at registration
December 2024
Latest completion date
December 2026
Delay so far
24 months
Homes
19
Sold or booked
91%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Vira Park View, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VIRA PARK VIEW100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • VIRA PARK VIEW: covers Ground to 9th Upper Floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vira Park View every 1–2 months.

Vira Park View: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK654 – 8648
3 BHK809 – 1,7366
Shops100 – 2096
Other797 – 9223
Office Space1,033 – 1,1762
4 BHK1,6321
Multi Purpose Room2701

The builder’s record and reviews

Vira Realty (a group of 5 linked companies) has 6 projects on MahaRERA since 2020, this one included. Of the 6 GharKundli has checked: 1 finished, all within the promised date; 5 still being built, 1 past the promised date (typically 22 months late). No complaints on MahaRERA.

Read Google reviews of Vira Park View →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vira Park View: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Vira Park View

What is the possession date of Vira Park View?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vira Park View in Vile Parle East, Mumbai is 10 December 2026 — 24 months later than 31 December 2024, the date given at registration.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Vira Park View?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vira Park View's builder has filed on MahaRERA, the official one, is 10 December 2026, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Vira Park View extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Vira Park View's builder applied to MahaRERA to extend the completion date 2 times: to 30 July 2025, giving the reason "1. We would like to inform that almost all of the work has been done in the project. The main challenges we were facing delay in completion was due to shortage of skilled labors, because of that we could not complete the project as per specified date 2. We are in completion stage as we are addressing stricter contractor oversight, communication with the project team and seeing the labors sources actively to ensure the completion of the projects. We appreciate your understanding ind support to resolve the challenges we face and to ensure the project completion before 30/07/2025."; to 10 December 2026, giving the reason "OC Recived".

What is the RERA number of Vira Park View?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vira Park View in Vile Parle East, Mumbai is P51800049141.

Is Vira Park View registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vira Park View is registered as P51800049141 and its status is "Registered and active".

What is the current construction status of Vira Park View? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Vira Park View's status on MahaRERA is "Registered and active". As filed by the builder, slab work on VIRA PARK VIEW is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Vira Park View have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Vira Park View safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Vira Park View is registered on MahaRERA as P51800049141, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Vira Park View?

Vira Park View is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Vira Park View are 270 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Vira Park View?

For a flat in Vira Park View (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Vira Park View received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vira Park View is still under construction, with 10 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Vira Park View a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Vira Park View is a redevelopment: 16 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Vira Park View uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vira Park View was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Vira Park View's possession date changes?

The latest dates are on Vira Park View's MahaRERA page (P51800049141). GharKundli's Kundli Watch sends a free WhatsApp update on Vira Park View every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vira Park View have?

According to GharKundli's check of MahaRERA records (updated October 2026), Vira Park View has one building filed: VIRA PARK VIEW with 10 floors and 27 units.

What are the flat sizes (carpet area) in Vira Park View?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Vira Park View: 2 BHK: 654 to 864 sq ft carpet (8 homes); 3 BHK: 809 to 1736 sq ft carpet (6 homes); Other: 797 to 922 sq ft carpet (3 homes); 4 BHK: 1632 sq ft carpet (1 homes); Multi Purpose Room: 270 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Vira Park View?

According to GharKundli's check of MahaRERA records (updated October 2026), Vira Park View stands on 519 sq m of land (about 0.1 acres), with 1,921 sq m of sanctioned built-up area.

What is the track record of Vira Park View's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vira Realty (a group of 5 linked companies) has 6 projects on MahaRERA since 2020, this one included. Of the 6 GharKundli has checked: 1 finished, all within the promised date; 5 still being built, 1 past the promised date (typically 22 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Vira Park View?

Google Maps has reviews of Vira Park View written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Vira Park View?

Vira Park View by Vira Infratech and Developers Private Limited is in Vile Parle East, Mumbai, pincode 400057 (near Vile Parle West, Vileparle East, Borivali West), Maharashtra, and is registered on MahaRERA as P51800049141, per GharKundli's check of MahaRERA records. Its boundaries filed there include PARK ROAD, MALVIYA ROAD. Its land is filed as CTS 1268/A. GharKundli lists all 251 MahaRERA projects in Vile Parle East (400057).

How many flats are in Vira Park View, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Vira Park View has 19 homes in 1 tower registered on MahaRERA, and 91% of them are sold or booked.

When was Vira Park View registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vira Park View was registered on MahaRERA on 1 February 2023. GharKundli did not find a title report on the land on file there.

Does Vira Park View have any legal issues or court cases?

No court cases are listed for Vira Park View on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Vira Park View?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Vira Infratech and Developers Private Limited.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Vile Parle East (400057)

All 251 projects in Vile Parle East (400057) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.