Skip to content
GharKundli

Orient Regency Building No. 1

by ORIENT COMBINE · Chembur, Mumbai 400089Also near Tilak Nagar, Panvel, Ghatkopar East

What’s in the report? →

Possession date of Orient Regency Building No. 1 (MahaRERA P51800050097): 14 April 2027. It has 66 homes (1 BHK, 2 BHK and 3 BHK, 409–833 sq ft carpet), 94% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800050097, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800050097, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Orient Regency Building No. 1?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Orient Regency Building No. 1 has moved

  1. 14 December 2026

    Completion date given when the project was registered

  2. 14 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Orient Regency Building No. 1’s extension records on MahaRERA (P51800050097), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Orient Regency Building No. 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800050097
Status
Registered and active
Builder
ORIENT COMBINE
Location
Chembur, Mumbai · 400089
Project type
Residential / Group Housing
Registered on
15 Mar 2023
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
66
Sold or booked
94%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Orient Regency Building No. 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building No 1 on Plot No NDR-4100%100%85%60%

Commencement certificate (CC), as filed on MahaRERA

  • Building No 1 on Plot No NDR-4: covers Stilt + 17th upper floors

Latest CC order on MahaRERA: dated 13/11/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Orient Regency Building No. 1 every 1–2 months.

Orient Regency Building No. 1: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK611 – 71634
1 BHK409 – 45317
3 BHK83315

The builder’s record and reviews

Ocorp Realty (a group of 3 linked companies) has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Orient Regency Building No. 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Orient Regency Building No. 1: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Orient Regency Building No. 1

What is the possession date of Orient Regency Building No. 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Orient Regency Building No. 1 in Chembur, Mumbai is 14 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Orient Regency Building No. 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Orient Regency Building No. 1's builder has filed on MahaRERA, the official one, is 14 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Orient Regency Building No. 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Orient Regency Building No. 1 in Chembur, Mumbai is P51800050097.

Is Orient Regency Building No. 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Orient Regency Building No. 1 is registered as P51800050097 and its status is "Registered and active".

What is the current construction status of Orient Regency Building No. 1? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Orient Regency Building No. 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Building No 1 on Plot No NDR-4 is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.

Does Orient Regency Building No. 1 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Orient Regency Building No. 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Orient Regency Building No. 1 is registered on MahaRERA as P51800050097, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Orient Regency Building No. 1?

Orient Regency Building No. 1 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Orient Regency Building No. 1 are 409 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Orient Regency Building No. 1?

For a flat in Orient Regency Building No. 1 (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Orient Regency Building No. 1 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Orient Regency Building No. 1 is still under construction, with 14 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Orient Regency Building No. 1 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Orient Regency Building No. 1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Orient Regency Building No. 1's possession date changes?

The latest dates are on Orient Regency Building No. 1's MahaRERA page (P51800050097). GharKundli's Kundli Watch sends a free WhatsApp update on Orient Regency Building No. 1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Orient Regency Building No. 1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Orient Regency Building No. 1 has one building filed: Building No 1 on Plot No NDR-4 with 18 floors and 66 units.

What are the flat sizes (carpet area) in Orient Regency Building No. 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Orient Regency Building No. 1: 2 BHK: 611 to 716 sq ft carpet (34 homes); 1 BHK: 409 to 453 sq ft carpet (17 homes); 3 BHK: 833 sq ft carpet (15 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Orient Regency Building No. 1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 72 covered car parking spaces for Orient Regency Building No. 1.

How big is the land of Orient Regency Building No. 1?

According to GharKundli's check of MahaRERA records (updated October 2026), Orient Regency Building No. 1 stands on 2,313 sq m of land (about 0.6 acres), with 4,216 sq m of sanctioned built-up area.

What is the track record of Orient Regency Building No. 1's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ocorp Realty (a group of 3 linked companies) has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Orient Regency Building No. 1?

Google Maps has reviews of Orient Regency Building No. 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Orient Regency Building No. 1?

Orient Regency Building No. 1 by ORIENT COMBINE is in Chembur, Mumbai, pincode 400089 (near Tilak Nagar, Panvel, Ghatkopar East), Maharashtra, and is registered on MahaRERA as P51800050097, per GharKundli's check of MahaRERA records. Its land is filed as Plot No. NDR-4 / CTS No. 13 (pt) & 506 (pt). GharKundli lists all 75 MahaRERA projects in Chembur (400089).

How many flats are in Orient Regency Building No. 1, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Orient Regency Building No. 1 has 66 homes in 1 tower registered on MahaRERA, and 94% of them are sold or booked.

When was Orient Regency Building No. 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Orient Regency Building No. 1 was registered on MahaRERA on 15 March 2023. GharKundli did not find a title report on the land on file there.

Does Orient Regency Building No. 1 have any legal issues or court cases?

No court cases are listed for Orient Regency Building No. 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Orient Regency Building No. 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ORIENT COMBINE.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Chembur (400089)

All 75 projects in Chembur (400089) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.