JAYMALA SADAN CHSL
by SWAANAND BUILDERS AND CONTRACTORS · Malad West, MumbaiAlso near Borivali, Vile Parle East, Worli
Possession date of JAYMALA SADAN CHSL: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800050074, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about JAYMALA SADAN CHSL?
How the possession date of JAYMALA SADAN CHSL has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: JAYMALA SADAN CHSL’s extension records on MahaRERA (P51800050074), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on JAYMALA SADAN CHSL
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800050074
- Status
- Registered and active
- Builder
- SWAANAND BUILDERS AND CONTRACTORS
- Location
- Malad West, Mumbai · 400064
- Project type
- Others
- Registered on
- 13 Mar 2023
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 33
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of JAYMALA SADAN CHSL, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| JAYMALA SADAN CHSL | 100% | 11% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on JAYMALA SADAN CHSL every month.
JAYMALA SADAN CHSL: buildings, flats and land, as filed on MahaRERA
- Buildings: JAYMALA SADAN CHSL (13 floors)
- Land: 1,388 sq m (about 0.3 acres) · sanctioned built-up 3,060 sq m
- Boundaries filed include: GARDEN
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of JAYMALA SADAN CHSL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
JAYMALA SADAN CHSL: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about JAYMALA SADAN CHSL
What is the possession date of JAYMALA SADAN CHSL?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for JAYMALA SADAN CHSL in Malad West, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for JAYMALA SADAN CHSL?
Builders and listing sites often quote an earlier "target" date for handover. The completion date JAYMALA SADAN CHSL's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of JAYMALA SADAN CHSL?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of JAYMALA SADAN CHSL in Malad West, Mumbai is P51800050074.
Is JAYMALA SADAN CHSL registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), JAYMALA SADAN CHSL is registered as P51800050074 and its status is "Registered and active".
What is the construction status of JAYMALA SADAN CHSL?
According to GharKundli's check of MahaRERA records (updated November 2026), JAYMALA SADAN CHSL's status on MahaRERA is "Registered and active". As filed by the builder, slab work on JAYMALA SADAN CHSL is 11% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does JAYMALA SADAN CHSL have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is JAYMALA SADAN CHSL safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), JAYMALA SADAN CHSL is registered on MahaRERA as P51800050074, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if JAYMALA SADAN CHSL's possession date changes?
The latest dates are on JAYMALA SADAN CHSL's MahaRERA page (P51800050074). GharKundli's Kundli Watch sends a free WhatsApp update on JAYMALA SADAN CHSL every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does JAYMALA SADAN CHSL have?
According to GharKundli's check of MahaRERA records (updated November 2026), JAYMALA SADAN CHSL has one building filed: JAYMALA SADAN CHSL with 13 floors.
How big is the land of JAYMALA SADAN CHSL?
According to GharKundli's check of MahaRERA records (updated November 2026), JAYMALA SADAN CHSL stands on 1,388 sq m of land (about 0.3 acres), with 3,060 sq m of sanctioned built-up area.
Where can I read reviews of JAYMALA SADAN CHSL?
Google Maps has reviews of JAYMALA SADAN CHSL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is JAYMALA SADAN CHSL?
JAYMALA SADAN CHSL by SWAANAND BUILDERS AND CONTRACTORS is in Malad West, Mumbai (pincode 400064), near Borivali, Vile Parle East, Worli, Maharashtra, and is registered on MahaRERA as P51800050074, per GharKundli's check of MahaRERA records. Its boundaries filed there include GARDEN.
How many homes are in JAYMALA SADAN CHSL?
According to GharKundli's check of MahaRERA records (updated November 2026), JAYMALA SADAN CHSL has 33 homes in 1 tower registered on MahaRERA.
When was JAYMALA SADAN CHSL registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), JAYMALA SADAN CHSL was registered on MahaRERA on 13 March 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on JAYMALA SADAN CHSL?
No court cases are listed for JAYMALA SADAN CHSL on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of JAYMALA SADAN CHSL?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SWAANAND BUILDERS AND CONTRACTORS.
Check it yourself on MahaRERA
- How to check the possession date of JAYMALA SADAN CHSL
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400064
- AABIEL AVENUE
- Lotus Sky Garden
- Bhagat Grandeur
- AVIRAHI ELEGANCE
- Rite Amor
- RASHMI ICON
- MARU MANSION
- Florence Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.