Possession date of Charkop Rakesh Co. Op. HSG. Soceity LTD. (MahaRERA P51800051984): 30 April 2028. It has 82 homes (1 BHK, 2 BHK and 3 BHK, 404–1027 sq ft carpet), 33% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800051984, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800051984, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Charkop Rakesh Co. Op. HSG. Soceity LTD.?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Charkop Rakesh Co. Op. HSG. Soceity LTD. has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Charkop Rakesh Co. Op. HSG. Soceity LTD.’s extension records on MahaRERA (P51800051984), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Charkop Rakesh Co. Op. HSG. Soceity LTD.

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800051984
Status
Registered and active
Builder
CHARKOP RAKESH CO-OPERATIVE HOUSING SOCIETY LIMITED
Location
Charkop Kandivali West, Mumbai · 400067
Project type
Residential / Group Housing
Registered on
13 Jul 2023
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
82
Sold or booked
33%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Charkop Rakesh Co. Op. HSG. Soceity LTD., as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
CHARKOP RAKESH CO OP HSG SOCIETY LTD100%65%30%0%

Commencement certificate (CC), as filed on MahaRERA

  • CHARKOP RAKESH CO OP HSG SOCIETY LTD: covers 20 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Charkop Rakesh Co. Op. HSG. Soceity LTD. every 1–2 months.

Charkop Rakesh Co. Op. HSG. Soceity LTD.: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK404 – 42960
2 BHK629 – 81819
Shops177 – 5826
Other8351
3 BHK8071
4 BHK1,0271
  • Buildings: CHARKOP RAKESH CO OP HSG SOCIETY LTD (23 floors, 88 units)
  • Land: 917 sq m (about 0.2 acres) · sanctioned built-up 842 sq m
  • Boundaries filed include: 9 WIDE EXISTING LAYOUT ROAD
  • Land, as filed: PLOT NO 215, C.T.S NO 1C/1/198
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Charkop Rakesh Co. Op. HSG. Soceity LTD. →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Charkop Rakesh Co. Op. HSG. Soceity LTD.: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Charkop Rakesh Co. Op. HSG. Soceity LTD.

What is the possession date of Charkop Rakesh Co. Op. HSG. Soceity LTD.?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Charkop Rakesh Co. Op. HSG. Soceity LTD. in Charkop Kandivali West, Mumbai is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Charkop Rakesh Co. Op. HSG. Soceity LTD.?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Charkop Rakesh Co. Op. HSG. Soceity LTD.'s builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Charkop Rakesh Co. Op. HSG. Soceity LTD.?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Charkop Rakesh Co. Op. HSG. Soceity LTD. in Charkop Kandivali West, Mumbai is P51800051984.

Is Charkop Rakesh Co. Op. HSG. Soceity LTD. registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Rakesh Co. Op. HSG. Soceity LTD. is registered as P51800051984 and its status is "Registered and active".

What is the current construction status of Charkop Rakesh Co. Op. HSG. Soceity LTD.? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Rakesh Co. Op. HSG. Soceity LTD.'s status on MahaRERA is "Registered and active". As filed by the builder, slab work on CHARKOP RAKESH CO OP HSG SOCIETY LTD is 65% done and internal work 30%. GharKundli's full report compares construction progress with the deadline.

Does Charkop Rakesh Co. Op. HSG. Soceity LTD. have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Charkop Rakesh Co. Op. HSG. Soceity LTD. safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Rakesh Co. Op. HSG. Soceity LTD. is registered on MahaRERA as P51800051984, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Charkop Rakesh Co. Op. HSG. Soceity LTD.?

Charkop Rakesh Co. Op. HSG. Soceity LTD. is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Charkop Rakesh Co. Op. HSG. Soceity LTD. are 404 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Charkop Rakesh Co. Op. HSG. Soceity LTD.?

For a flat in Charkop Rakesh Co. Op. HSG. Soceity LTD. (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Charkop Rakesh Co. Op. HSG. Soceity LTD. received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Rakesh Co. Op. HSG. Soceity LTD. is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Charkop Rakesh Co. Op. HSG. Soceity LTD. a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Rakesh Co. Op. HSG. Soceity LTD. is a redevelopment: 36 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Charkop Rakesh Co. Op. HSG. Soceity LTD. uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Charkop Rakesh Co. Op. HSG. Soceity LTD. was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Charkop Rakesh Co. Op. HSG. Soceity LTD.'s possession date changes?

The latest dates are on Charkop Rakesh Co. Op. HSG. Soceity LTD.'s MahaRERA page (P51800051984). GharKundli's Kundli Watch sends a free WhatsApp update on Charkop Rakesh Co. Op. HSG. Soceity LTD. every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Charkop Rakesh Co. Op. HSG. Soceity LTD. have?

According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Rakesh Co. Op. HSG. Soceity LTD. has one building filed: CHARKOP RAKESH CO OP HSG SOCIETY LTD with 23 floors and 88 units.

What are the flat sizes (carpet area) in Charkop Rakesh Co. Op. HSG. Soceity LTD.?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Charkop Rakesh Co. Op. HSG. Soceity LTD.: 1 BHK: 404 to 429 sq ft carpet (60 homes); 2 BHK: 629 to 818 sq ft carpet (19 homes); Other: 835 sq ft carpet (1 homes); 3 BHK: 807 sq ft carpet (1 homes); 4 BHK: 1027 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Charkop Rakesh Co. Op. HSG. Soceity LTD.?

According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Rakesh Co. Op. HSG. Soceity LTD. stands on 917 sq m of land (about 0.2 acres), with 842 sq m of sanctioned built-up area.

What are the reviews of Charkop Rakesh Co. Op. HSG. Soceity LTD.?

Google Maps has reviews of Charkop Rakesh Co. Op. HSG. Soceity LTD. written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Charkop Rakesh Co. Op. HSG. Soceity LTD.?

Charkop Rakesh Co. Op. HSG. Soceity LTD. by CHARKOP RAKESH CO-OPERATIVE HOUSING SOCIETY LIMITED is in Charkop Kandivali West, Mumbai, pincode 400067 (near Borivali West, Chikoowadi), Maharashtra, and is registered on MahaRERA as P51800051984, per GharKundli's check of MahaRERA records. Its boundaries filed there include 9 WIDE EXISTING LAYOUT ROAD. Its land is filed as PLOT NO 215, C.T.S NO 1C/1/198. GharKundli lists all 318 MahaRERA projects in Kandivali West (400067).

How many flats are in Charkop Rakesh Co. Op. HSG. Soceity LTD., and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Rakesh Co. Op. HSG. Soceity LTD. has 82 homes in 1 tower registered on MahaRERA, and 33% of them are sold or booked.

When was Charkop Rakesh Co. Op. HSG. Soceity LTD. registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Charkop Rakesh Co. Op. HSG. Soceity LTD. was registered on MahaRERA on 13 July 2023. GharKundli did not find a title report on the land on file there.

Does Charkop Rakesh Co. Op. HSG. Soceity LTD. have any legal issues or court cases?

No court cases are listed for Charkop Rakesh Co. Op. HSG. Soceity LTD. on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Charkop Rakesh Co. Op. HSG. Soceity LTD.?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is CHARKOP RAKESH CO-OPERATIVE HOUSING SOCIETY LIMITED.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Kandivali West (400067)

All 318 projects in Kandivali West (400067) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.