Estella

by V CITY BUILDERS & DEVELOPERS LLP (Yashodanand) · Kandivali West, Mumbai 400067Also near Borivali

What’s in the report? →

Possession date of Estella (MahaRERA P51800052152): 30 June 2028, moved from 30 June 2025 (36 months later). It has 74 homes (1 Room Kitchen, 1 BHK and 2 BHK, 182–975 sq ft carpet), 82% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800052152, and currently active.

Source: MahaRERA website — records for P51800052152, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Estella?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Estella has moved

  1. 30 June 2025

    Completion date given when the project was registered

  2. 30 June 2026

    Extended at the builder's request (MahaRERA application EA08082502343)

    Reason the builder gave MahaRERA: “Due to delay from contractor in completing work the project was not able to complete in time. We would like to request you to further grant us extension for 1 year/12 month. We request you kindly grant us the certificate of the earliest.”
  3. 30 June 2028

    Extended at the builder's request (MahaRERA application EA18072621794)

    Reason the builder gave MahaRERA:
    “We, V City Builders and Developers LLP, are the promoters of the real estate project known as "Estella" bearing Maha RERA Registration No. P51800005112. We Would like to request you that the Project Estella which is located at CTS no, 87/B,…” Read the full reason“We, V City Builders and Developers LLP, are the promoters of the real estate project known as "Estella" bearing Maha RERA Registration No. P51800005112. We Would like to request you that the Project Estella which is located at CTS no, 87/B, 87/8/1 to 21 of Village Malad (North) In R/South ward, At junction of Mathuradas read and Bhogilal Fadia Road, Kandivali - West, Mumbai - 400 067 having its Registration No P518000051152 was mentioned to be completed on 30 June 2025. The project has faced unavoidable delays due to administrative and statutory processing timelines. Specifically, under the…”

Source: Estella’s extension records on MahaRERA (P51800052152), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Estella

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800052152
Status
Registered and active
Builder
V CITY BUILDERS & DEVELOPERS LLP
Location
Kandivali West, Mumbai · 400067
Project type
Others
Registered on
24 Jul 2023
Completion date at registration
June 2025
Latest completion date
June 2028
Delay so far
36 months
Homes
74
Sold or booked
82%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Estella, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ESTELLA100%90%70%50%

Commencement certificate (CC), as filed on MahaRERA

  • ESTELLA: covers plinth level

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Estella every 1–2 months.

Estella: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK577 – 78553
Shops23 – 41130
Office Space151 – 5,50023
3 BHK826 – 97516
1 Room Kitchen182 – 2283
1 BHK412 – 5652
  • Buildings: ESTELLA (15 floors, 127 units)
  • Land: 1,371 sq m (about 0.3 acres) · sanctioned built-up 3,833 sq m
  • Boundaries filed include: Mathuradas Road, B Padia Road
  • Land, as filed: 87/B , 87/B/1 TO 21
  • Map: Get directions

The builder’s record and reviews

Yashodanand Infra (a group of 5 linked companies) has 7 projects on MahaRERA since 2022, this one included. Of the 7 GharKundli has checked: 7 still being built, 3 past the promised date (typically 20 months late). No complaints on MahaRERA.

Read Google reviews of Estella →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Estella: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Estella

What is the possession date of Estella?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Estella in Kandivali West, Mumbai is 30 June 2028 — 36 months later than 30 June 2025, the date given at registration.

The date has already moved 36 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Estella?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Estella's builder has filed on MahaRERA, the official one, is 30 June 2028, already 36 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Estella extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Estella's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2026, giving the reason "Due to delay from contractor in completing work the project was not able to complete in time. We would like to request you to further grant us extension for 1 year/12 month. We request you kindly grant us the certificate of the earliest."; to 30 June 2028, giving the reason "We, V City Builders and Developers LLP, are the promoters of the real estate project known as "Estella" bearing Maha RERA Registration No. P51800005112. We Would like to request you that the Project Estella which is located at CTS no, 87/B, 87/8/1 to 21 of Village Malad (North) In R/South ward, At junction of Mathuradas read and Bhogilal Fadia Road, Kandivali - West, Mumbai - 400 067 having its Registration No P518000051152 was mentioned to be completed on 30 June 2025. The project has faced unavoidable delays due to administrative and statutory processing timelines. Specifically, under the…".

What is the RERA number of Estella?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Estella in Kandivali West, Mumbai is P51800052152.

Is Estella registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Estella is registered as P51800052152 and its status is "Registered and active".

What is the current construction status of Estella? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Estella's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ESTELLA is 90% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.

Does Estella have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Estella safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Estella is registered on MahaRERA as P51800052152, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Estella?

Estella is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Estella are 182 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Estella?

For a flat in Estella (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Estella received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Estella is still under construction, with 30 June 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Estella a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Estella is a redevelopment: 51 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Estella uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Estella was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Estella's possession date changes?

The latest dates are on Estella's MahaRERA page (P51800052152). GharKundli's Kundli Watch sends a free WhatsApp update on Estella every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Estella have?

According to GharKundli's check of MahaRERA records (updated October 2026), Estella has one building filed: ESTELLA with 15 floors and 127 units.

What are the flat sizes (carpet area) in Estella?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Estella: 2 BHK: 577 to 785 sq ft carpet (53 homes); 3 BHK: 826 to 975 sq ft carpet (16 homes); 1 Room Kitchen: 182 to 228 sq ft carpet (3 homes); 1 BHK: 412 to 565 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Estella?

According to GharKundli's check of MahaRERA records (updated October 2026), Estella stands on 1,371 sq m of land (about 0.3 acres), with 3,833 sq m of sanctioned built-up area.

What is the track record of Estella's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Yashodanand Infra (a group of 5 linked companies) has 7 projects on MahaRERA since 2022, this one included. Of the 7 GharKundli has checked: 7 still being built, 3 past the promised date (typically 20 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Estella?

Google Maps has reviews of Estella written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Estella?

Estella by V CITY BUILDERS & DEVELOPERS LLP (Yashodanand) is in Kandivali West, Mumbai, pincode 400067 (near Borivali), Maharashtra, and is registered on MahaRERA as P51800052152, per GharKundli's check of MahaRERA records. Its boundaries filed there include Mathuradas Road, B Padia Road. Its land is filed as 87/B , 87/B/1 TO 21. GharKundli lists all 318 MahaRERA projects in Kandivali West (400067).

How many flats are in Estella, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Estella has 74 homes in 1 tower registered on MahaRERA, and 82% of them are sold or booked.

When was Estella registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Estella was registered on MahaRERA on 24 July 2023. GharKundli did not find a title report on the land on file there.

Does Estella have any legal issues or court cases?

No court cases are listed for Estella on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Estella?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is V CITY BUILDERS & DEVELOPERS LLP, the company Yashodanand files this project under.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Kandivali West (400067)

All 318 projects in Kandivali West (400067) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.