GAGANGIRI LEGACY
by SHRI GAGANGIRI CONSTRUCTION CO · Dahisar West, MumbaiAlso near Borivali West, I C Colony, Dahisar East
Possession date of GAGANGIRI LEGACY: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800052082, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about GAGANGIRI LEGACY?
How the possession date of GAGANGIRI LEGACY has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: GAGANGIRI LEGACY’s extension records on MahaRERA (P51800052082), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GAGANGIRI LEGACY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 1 court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800052082
- Status
- Registered and active
- Builder
- SHRI GAGANGIRI CONSTRUCTION CO
- Location
- Dahisar West, Mumbai · 400068
- Project type
- Residential / Group Housing
- Registered on
- 24 Jul 2023
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of GAGANGIRI LEGACY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GAGANGIRI LEGACY | 100% | 58% | 30% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- GAGANGIRI LEGACY: covers 0 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GAGANGIRI LEGACY every month.
GAGANGIRI LEGACY: buildings, flats and land, as filed on MahaRERA
- Land: 841 sq m (about 0.2 acres) · sanctioned built-up 1,232 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Gagangiri Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project.
Read Google reviews of GAGANGIRI LEGACY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GAGANGIRI LEGACY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about GAGANGIRI LEGACY
What is the possession date of GAGANGIRI LEGACY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GAGANGIRI LEGACY in Dahisar West, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for GAGANGIRI LEGACY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GAGANGIRI LEGACY's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of GAGANGIRI LEGACY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GAGANGIRI LEGACY in Dahisar West, Mumbai is P51800052082.
Is GAGANGIRI LEGACY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GAGANGIRI LEGACY is registered as P51800052082 and its status is "Registered and active".
What is the construction status of GAGANGIRI LEGACY?
According to GharKundli's check of MahaRERA records (updated October 2026), GAGANGIRI LEGACY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GAGANGIRI LEGACY is 58% done and internal work 30%. GharKundli's full report compares construction progress with the deadline.
Does GAGANGIRI LEGACY have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is GAGANGIRI LEGACY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), GAGANGIRI LEGACY is registered on MahaRERA as P51800052082, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if GAGANGIRI LEGACY's possession date changes?
The latest dates are on GAGANGIRI LEGACY's MahaRERA page (P51800052082). GharKundli's Kundli Watch sends a free WhatsApp update on GAGANGIRI LEGACY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How big is the land of GAGANGIRI LEGACY?
According to GharKundli's check of MahaRERA records (updated October 2026), GAGANGIRI LEGACY stands on 841 sq m of land (about 0.2 acres), with 1,232 sq m of sanctioned built-up area.
What is the track record of GAGANGIRI LEGACY's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Gagangiri Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of GAGANGIRI LEGACY?
Google Maps has reviews of GAGANGIRI LEGACY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is GAGANGIRI LEGACY?
GAGANGIRI LEGACY by SHRI GAGANGIRI CONSTRUCTION CO is in Dahisar West, Mumbai (pincode 400068), near Borivali West, I C Colony, Dahisar East, Maharashtra, and is registered on MahaRERA as P51800052082, per GharKundli's check of MahaRERA records.
When was GAGANGIRI LEGACY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GAGANGIRI LEGACY was registered on MahaRERA on 24 July 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on GAGANGIRI LEGACY?
1 court case is listed for GAGANGIRI LEGACY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of GAGANGIRI LEGACY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHRI GAGANGIRI CONSTRUCTION CO.
Check it yourself on MahaRERA
- How to check the possession date of GAGANGIRI LEGACY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400068
- RAJHANS
- Royal Accord
- SHREE GANESH CHSL
- Ozone Residency
- BRINDAVAN CHSL
- RAJ CAPITAL
- EMPIRE HEIGHTS
- Nirali Lifespace
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.