Serinity Palace Liberty

by SERINITY EXQUISITE LLP · Malad West, Mumbai 400064Also near Malad East, Motilal NagarRegistered on MahaRERA as “PALACE LIBERTY”

What’s in the report? →

Possession date of Serinity Palace Liberty (MahaRERA P51800052160): 11 May 2027, moved from 11 May 2026 (12 months later). It has 59 homes (1 BHK, 2 BHK and 3 BHK, 322–675 sq ft carpet), 28% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800052160, and currently active.

Source: MahaRERA website — records for P51800052160, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Serinity Palace Liberty?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Serinity Palace Liberty has moved

  1. 11 May 2026

    Completion date given when the project was registered

  2. 11 May 2027

    Extended at the builder's request (MahaRERA application EA18062621425)

    Reason the builder gave MahaRERA:
    “Subject: Submission of Technical Reasons for Delay in Completion of the Project Palace Liberty, Maha RERA Reg. No. P51800052160 Respected Sir, We, SERINITY EXQUISITE LLP, are the promoters of the real estate project known as "Palace Liberty…” Read the full reason“Subject: Submission of Technical Reasons for Delay in Completion of the Project Palace Liberty, Maha RERA Reg. No. P51800052160 Respected Sir, We, SERINITY EXQUISITE LLP, are the promoters of the real estate project known as "Palace Liberty" bearing Maha RERA Registration No, P51800052160 The project completion has been delayed due to war and the resulting disruption of supply chains, transportation, availability of construction materials, and work force. These circumstances were beyond the control of the promoter and have significantly impacted the progress of construction, Accordingly, an…”

Source: Serinity Palace Liberty’s extension records on MahaRERA (P51800052160), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Serinity Palace Liberty

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the May 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800052160
Status
Registered and active
Builder
SERINITY EXQUISITE LLP
Location
Malad West, Mumbai · 400064
Project type
Others
Registered on
27 Jul 2023
Completion date at registration
May 2026
Latest completion date
May 2027
Delay so far
12 months
Homes
59
Sold or booked
28%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Serinity Palace Liberty, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PALACE LIBERTY100%100%98%30%

Commencement certificate (CC), as filed on MahaRERA

  • PALACE LIBERTY: covers PLINTH LEVEL

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Serinity Palace Liberty every 1–2 months.

Serinity Palace Liberty: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK480 – 55927
1 BHK322 – 43615
Other44815
Shops166 – 5647
3 BHK619 – 6752
  • Buildings: PALACE LIBERTY (6 floors, 66 units)
  • Land: 582 sq m (about 0.1 acres) · sanctioned built-up 1,168 sq m
  • Land, as filed: 17, 17/1 AND 21, 21/1, 21/2, 21/3, 21/4
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Serinity Palace Liberty →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Serinity Palace Liberty: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Serinity Palace Liberty

What is the possession date of Serinity Palace Liberty?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Serinity Palace Liberty in Malad West, Mumbai is 11 May 2027 — 12 months later than 11 May 2026, the date given at registration.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Serinity Palace Liberty?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Serinity Palace Liberty's builder has filed on MahaRERA, the official one, is 11 May 2027, already 12 months later than the 11 May 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Serinity Palace Liberty extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Serinity Palace Liberty's builder applied to MahaRERA to extend the completion date once: to 11 May 2027, giving the reason "Subject: Submission of Technical Reasons for Delay in Completion of the Project Palace Liberty, Maha RERA Reg. No. P51800052160 Respected Sir, We, SERINITY EXQUISITE LLP, are the promoters of the real estate project known as "Palace Liberty" bearing Maha RERA Registration No, P51800052160 The project completion has been delayed due to war and the resulting disruption of supply chains, transportation, availability of construction materials, and work force. These circumstances were beyond the control of the promoter and have significantly impacted the progress of construction, Accordingly, an…".

What is the RERA number of Serinity Palace Liberty?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Serinity Palace Liberty in Malad West, Mumbai is P51800052160.

Is Serinity Palace Liberty registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Serinity Palace Liberty is registered as P51800052160 and its status is "Registered and active".

What is the current construction status of Serinity Palace Liberty? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Serinity Palace Liberty's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PALACE LIBERTY is 100% done and internal work 98%. GharKundli's full report compares construction progress with the deadline.

Does Serinity Palace Liberty have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Serinity Palace Liberty safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Serinity Palace Liberty is registered on MahaRERA as P51800052160, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Serinity Palace Liberty?

Serinity Palace Liberty is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Serinity Palace Liberty are 322 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Serinity Palace Liberty?

For a flat in Serinity Palace Liberty (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Serinity Palace Liberty received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Serinity Palace Liberty is still under construction, with 11 May 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Serinity Palace Liberty a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Serinity Palace Liberty is a redevelopment: 20 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Serinity Palace Liberty uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Serinity Palace Liberty was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Serinity Palace Liberty's possession date changes?

The latest dates are on Serinity Palace Liberty's MahaRERA page (P51800052160). GharKundli's Kundli Watch sends a free WhatsApp update on Serinity Palace Liberty every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Serinity Palace Liberty have?

According to GharKundli's check of MahaRERA records (updated October 2026), Serinity Palace Liberty has one building filed: PALACE LIBERTY with 6 floors and 66 units.

What are the flat sizes (carpet area) in Serinity Palace Liberty?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Serinity Palace Liberty: 2 BHK: 480 to 559 sq ft carpet (27 homes); 1 BHK: 322 to 436 sq ft carpet (15 homes); Other: 448 sq ft carpet (15 homes); 3 BHK: 619 to 675 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Serinity Palace Liberty?

According to GharKundli's check of MahaRERA records (updated October 2026), Serinity Palace Liberty stands on 582 sq m of land (about 0.1 acres), with 1,168 sq m of sanctioned built-up area.

What are the reviews of Serinity Palace Liberty?

Google Maps has reviews of Serinity Palace Liberty written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Serinity Palace Liberty?

Serinity Palace Liberty by SERINITY EXQUISITE LLP is in Malad West, Mumbai, pincode 400064 (near Malad East, Motilal Nagar), Maharashtra, and is registered on MahaRERA as P51800052160, per GharKundli's check of MahaRERA records. Its land is filed as 17, 17/1 AND 21, 21/1, 21/2, 21/3, 21/4. GharKundli lists all 301 MahaRERA projects in Malad West (400064).

How many flats are in Serinity Palace Liberty, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Serinity Palace Liberty has 59 homes in 1 tower registered on MahaRERA, and 28% of them are sold or booked.

When was Serinity Palace Liberty registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Serinity Palace Liberty was registered on MahaRERA on 27 July 2023. GharKundli did not find a title report on the land on file there.

Does Serinity Palace Liberty have any legal issues or court cases?

No court cases are listed for Serinity Palace Liberty on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Serinity Palace Liberty?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SERINITY EXQUISITE LLP.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Malad West (400064)

All 301 projects in Malad West (400064) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.