Laxmina Krishna Niwas
by Laxmina Argentum Realties (India) Private Limited · Chembur East, Mumbai 400071Also near Bhandup West, Chembur West, Ghatkopar East
What’s in the report? →Possession date of Laxmina Krishna Niwas (MahaRERA P51800052240): 31 October 2026, moved from 31 March 2026 (7 months later), and it has already passed. It has 41 homes (1 BHK and 2 BHK, 430–647 sq ft carpet), 94% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800052240, and currently active.
Source: MahaRERA website — records for P51800052240, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about Laxmina Krishna Niwas?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Laxmina Krishna Niwas has moved
31 March 2026
Completion date given when the project was registered
31 October 2026
Extended at the builder's request (MahaRERA application EA30032620455)
Reason the builder gave MahaRERA:
“The application has been submitted for Occupancy Certificate in respect of the project has already been made; however, certain compliance requirements were raised by the Planning Authority, due to which some documents are required to be re-…” Read the full reason
“The application has been submitted for Occupancy Certificate in respect of the project has already been made; however, certain compliance requirements were raised by the Planning Authority, due to which some documents are required to be re-submitted. We are in the process of complying with the said requirements and, upon submission of the requisite compliances, the Planning Authority is expected to issue the Occupancy Certificate within the prescribed statutory timelines. We presently expect to receive the Occupancy Certificate on or before 31/10/2026. We kindly request an extension until 3…”
Source: Laxmina Krishna Niwas’s extension records on MahaRERA (P51800052240), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Laxmina Krishna Niwas
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800052240
- Status
- Registered and active
- Builder
- Laxmina Argentum Realties (India) Private Limited
- Location
- Chembur East, Mumbai · 400071
- Project type
- Residential / Group Housing
- Registered on
- 2 Aug 2023
- Completion date at registration
- March 2026
- Latest completion date
- October 2026
- Delay so far
- 7 months
- Homes
- 41
- Sold or booked
- 94%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Laxmina Krishna Niwas, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Laxmina Krishna Niwas | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Laxmina Krishna Niwas: covers 12 (G + 11)
Latest CC order on MahaRERA: dated 05/11/2024.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Laxmina Krishna Niwas every 1–2 months.
Laxmina Krishna Niwas: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 430 – 431 | 26 |
| 2 BHK | 639 – 647 | 15 |
- Buildings: Laxmina Krishna Niwas (12 floors, 41 units)
- Car parking: 45 covered
- Land: 865 sq m (about 0.2 acres) · sanctioned built-up 2,203 sq m
- Land, as filed: 1085, 1085/1 to 8
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Laxmina Krishna Niwas →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Laxmina Krishna Niwas: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Laxmina Krishna Niwas
What is the possession date of Laxmina Krishna Niwas?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Laxmina Krishna Niwas in Chembur East, Mumbai is 31 October 2026 — 7 months later than 31 March 2026, the date given at registration. That date has already passed.
The date has already moved 7 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Laxmina Krishna Niwas?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Laxmina Krishna Niwas's builder has filed on MahaRERA, the official one, is 31 October 2026, already 7 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Laxmina Krishna Niwas extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Laxmina Krishna Niwas's builder applied to MahaRERA to extend the completion date once: to 31 October 2026, giving the reason "The application has been submitted for Occupancy Certificate in respect of the project has already been made; however, certain compliance requirements were raised by the Planning Authority, due to which some documents are required to be re-submitted. We are in the process of complying with the said requirements and, upon submission of the requisite compliances, the Planning Authority is expected to issue the Occupancy Certificate within the prescribed statutory timelines. We presently expect to receive the Occupancy Certificate on or before 31/10/2026. We kindly request an extension until 3…".
What is the RERA number of Laxmina Krishna Niwas?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Laxmina Krishna Niwas in Chembur East, Mumbai is P51800052240.
Is Laxmina Krishna Niwas registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Laxmina Krishna Niwas is registered as P51800052240 and its status is "Registered and active".
What is the current construction status of Laxmina Krishna Niwas? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Laxmina Krishna Niwas's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Laxmina Krishna Niwas is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Laxmina Krishna Niwas have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Laxmina Krishna Niwas safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Laxmina Krishna Niwas is registered on MahaRERA as P51800052240, its completion date has moved 7 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Laxmina Krishna Niwas?
Laxmina Krishna Niwas is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Laxmina Krishna Niwas are 430 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Laxmina Krishna Niwas?
For a flat in Laxmina Krishna Niwas (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Laxmina Krishna Niwas received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Laxmina Krishna Niwas is still under construction, with 31 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Laxmina Krishna Niwas a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Laxmina Krishna Niwas is a redevelopment: 24 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Laxmina Krishna Niwas uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Laxmina Krishna Niwas was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Laxmina Krishna Niwas's possession date changes?
The latest dates are on Laxmina Krishna Niwas's MahaRERA page (P51800052240). GharKundli's Kundli Watch sends a free WhatsApp update on Laxmina Krishna Niwas every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Laxmina Krishna Niwas have?
According to GharKundli's check of MahaRERA records (updated October 2026), Laxmina Krishna Niwas has one building filed: Laxmina Krishna Niwas with 12 floors and 41 units.
What are the flat sizes (carpet area) in Laxmina Krishna Niwas?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Laxmina Krishna Niwas: 1 BHK: 430 to 431 sq ft carpet (26 homes); 2 BHK: 639 to 647 sq ft carpet (15 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Laxmina Krishna Niwas have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 45 covered car parking spaces for Laxmina Krishna Niwas.
How big is the land of Laxmina Krishna Niwas?
According to GharKundli's check of MahaRERA records (updated October 2026), Laxmina Krishna Niwas stands on 865 sq m of land (about 0.2 acres), with 2,203 sq m of sanctioned built-up area.
What are the reviews of Laxmina Krishna Niwas?
Google Maps has reviews of Laxmina Krishna Niwas written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Laxmina Krishna Niwas?
Laxmina Krishna Niwas by Laxmina Argentum Realties (India) Private Limited is in Chembur East, Mumbai, pincode 400071 (near Bhandup West, Chembur West, Ghatkopar East), Maharashtra, and is registered on MahaRERA as P51800052240, per GharKundli's check of MahaRERA records. Its land is filed as 1085, 1085/1 to 8. GharKundli lists all 318 MahaRERA projects in Chembur (400071).
How many flats are in Laxmina Krishna Niwas, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Laxmina Krishna Niwas has 41 homes in 1 tower registered on MahaRERA, and 94% of them are sold or booked.
When was Laxmina Krishna Niwas registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Laxmina Krishna Niwas was registered on MahaRERA on 2 August 2023. GharKundli did not find a title report on the land on file there.
Does Laxmina Krishna Niwas have any legal issues or court cases?
No court cases are listed for Laxmina Krishna Niwas on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Laxmina Krishna Niwas?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Laxmina Argentum Realties (India) Private Limited.
Check it yourself on MahaRERA
- How to check the possession date of Laxmina Krishna Niwas
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Chembur (400071)
- 71 Pardis
- Tulsi Chamber Phase II
- Queens Park
- Sampoorna
- Shree Saraswati CHS LTD Plot 8B
- Icons 71
- Viera Golf Greens
- Arham Mourya
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.