by RAJ SKYLINE & KCD BUILDERS PRIVATE LIMITED · Kandivali West, MumbaiAlso near Charkop
Possession date of Neminavkar Dudhreshi: 30 June 2027, moved from 5 June 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800053058, and currently active. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Neminavkar Dudhreshi?
How the possession date of Neminavkar Dudhreshi has moved
5 June 2026
Completion date given when the project was registered
30 June 2027
Extended at the builder's request (MahaRERA application EA01062621192)
Reason the builder gave MahaRERA:
“SUBJECT: SUBMISSION OF TECHNICAL REASONS FOR DELAY IN COMPLETION OF THE PROJECT-NEMINAVKAR DUDHRESHI, MAHA RERA REG. NO. P51800053058. Respected Sir, We, RAJSKYLINE & KCD BUILDERS PVT LTD, are the promoters of the real estate project known…” Read the full reason
“SUBJECT: SUBMISSION OF TECHNICAL REASONS FOR DELAY IN COMPLETION OF THE PROJECT-NEMINAVKAR DUDHRESHI, MAHA RERA REG. NO. P51800053058. Respected Sir, We, RAJSKYLINE & KCD BUILDERS PVT LTD, are the promoters of the real estate project known as "NEMINAVKAR DUDHRESHI" bearing Maha RERA Registration No. P51800053058 The progress of the project has been delayed due to the prolonged process involved in clubbing the PTC scheme with our proposed scheme. The approvals, coordination, and procedural formalities required for integration of both schemes consumed additional time, which consequently affec…”
Source: Neminavkar Dudhreshi’s extension records on MahaRERA (P51800053058), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Neminavkar Dudhreshi
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800053058
- Status
- Registered and active
- Builder
- RAJ SKYLINE & KCD BUILDERS PRIVATE LIMITED
- Location
- Kandivali West, Mumbai · 400067
- Project type
- Others
- Registered on
- 12 Oct 2023
- Completion date at registration
- June 2026
- Latest completion date
- June 2027
- Delay so far
- 12 months
- Homes
- 61
- Sold or booked
- 77%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Neminavkar Dudhreshi, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Neminavkar Dudhreshi | 100% | 83.33% | 45% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Neminavkar Dudhreshi: covers 19 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Neminavkar Dudhreshi every month.
Neminavkar Dudhreshi: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 308 – 454 | 36 |
| 2 BHK | 300 – 4,855 | 25 |
| Amenity | 218 – 524 | 10 |
| Shops | 281 – 561 | 8 |
| Office Space | 269 – 699 | 7 |
- Buildings: Neminavkar Dudhreshi (22 floors, 86 units)
- Car parking: 67 covered
- Land: 1,115 sq m (about 0.3 acres) · sanctioned built-up 3,757 sq m
- Boundaries filed include: Panchasheel Garden building, mahavir nagar road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Neminavkar Construction (a group of 2 linked companies) has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 1 months late). 2 complaints on MahaRERA across 1 project.
Read Google reviews of Neminavkar Dudhreshi →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Neminavkar Dudhreshi: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Neminavkar Dudhreshi
What is the possession date of Neminavkar Dudhreshi?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Neminavkar Dudhreshi in Kandivali West, Mumbai is 30 June 2027 — 12 months later than 5 June 2026, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Neminavkar Dudhreshi?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Neminavkar Dudhreshi's builder has filed on MahaRERA, the official one, is 30 June 2027, already 12 months later than the 5 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Neminavkar Dudhreshi extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Neminavkar Dudhreshi's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "SUBJECT: SUBMISSION OF TECHNICAL REASONS FOR DELAY IN COMPLETION OF THE PROJECT-NEMINAVKAR DUDHRESHI, MAHA RERA REG. NO. P51800053058. Respected Sir, We, RAJSKYLINE & KCD BUILDERS PVT LTD, are the promoters of the real estate project known as "NEMINAVKAR DUDHRESHI" bearing Maha RERA Registration No. P51800053058 The progress of the project has been delayed due to the prolonged process involved in clubbing the PTC scheme with our proposed scheme. The approvals, coordination, and procedural formalities required for integration of both schemes consumed additional time, which consequently affec…".
What is the RERA number of Neminavkar Dudhreshi?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Neminavkar Dudhreshi in Kandivali West, Mumbai is P51800053058.
Is Neminavkar Dudhreshi registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Neminavkar Dudhreshi is registered as P51800053058 and its status is "Registered and active".
What is the construction status of Neminavkar Dudhreshi?
According to GharKundli's check of MahaRERA records (updated October 2026), Neminavkar Dudhreshi's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Neminavkar Dudhreshi is 83.33% done and internal work 45%. GharKundli's full report compares construction progress with the deadline.
Does Neminavkar Dudhreshi have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Neminavkar Dudhreshi safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Neminavkar Dudhreshi is registered on MahaRERA as P51800053058, its completion date has moved 12 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Neminavkar Dudhreshi's possession date changes?
The latest dates are on Neminavkar Dudhreshi's MahaRERA page (P51800053058). GharKundli's Kundli Watch sends a free WhatsApp update on Neminavkar Dudhreshi every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Neminavkar Dudhreshi have?
According to GharKundli's check of MahaRERA records (updated October 2026), Neminavkar Dudhreshi has one building filed: Neminavkar Dudhreshi with 22 floors and 86 units.
What are the flat sizes (carpet area) in Neminavkar Dudhreshi?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Neminavkar Dudhreshi: 1 BHK: 308 to 454 sq ft carpet (36 homes); 2 BHK: 300 to 4855 sq ft carpet (25 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Neminavkar Dudhreshi have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 67 covered car parking spaces for Neminavkar Dudhreshi.
How big is the land of Neminavkar Dudhreshi?
According to GharKundli's check of MahaRERA records (updated October 2026), Neminavkar Dudhreshi stands on 1,115 sq m of land (about 0.3 acres), with 3,757 sq m of sanctioned built-up area.
What is the track record of Neminavkar Dudhreshi's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Neminavkar Construction (a group of 2 linked companies) has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 1 months late). 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Neminavkar Dudhreshi?
Google Maps has reviews of Neminavkar Dudhreshi written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Neminavkar Dudhreshi?
Neminavkar Dudhreshi by RAJ SKYLINE & KCD BUILDERS PRIVATE LIMITED is in Kandivali West, Mumbai (pincode 400067), near Charkop, Maharashtra, and is registered on MahaRERA as P51800053058, per GharKundli's check of MahaRERA records. Its boundaries filed there include Panchasheel Garden building, mahavir nagar road.
How many homes are in Neminavkar Dudhreshi?
According to GharKundli's check of MahaRERA records (updated October 2026), Neminavkar Dudhreshi has 61 homes in 1 tower registered on MahaRERA, and 77% of them are sold or booked.
When was Neminavkar Dudhreshi registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Neminavkar Dudhreshi was registered on MahaRERA on 12 October 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Neminavkar Dudhreshi?
No court cases are listed for Neminavkar Dudhreshi on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Neminavkar Dudhreshi?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAJ SKYLINE & KCD BUILDERS PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of Neminavkar Dudhreshi
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400067
- PRIME SQUARE
- LA SERENA Tower 5, Tower 6 and Tower 7
- CHARKOP SHREE GANESH CHS LTD
- MPR SHRI PARAS DARSHAN
- SAFFRONWOODS CHSL
- SIGMA AMBER
- Avenue Wing B phase 2
- JAYAKAR HOUSE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.