by ADVENT DEVELOPERS PRIVATE LIMITED · Malad West, Mumbai 400064Also near Borivali West, Vile Parle East, Goregaon West
What’s in the report? →Possession date of Advent Deepak (MahaRERA P51800054861): 30 April 2028, moved from 31 December 2025 (24 months later). It has 74 homes (1 BHK, 2 BHK and 3 BHK, 436–740 sq ft carpet), 2% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800054861, and currently active. Its completion date has moved from December 2025 to April 2028: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800054861, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Advent Deepak?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Advent Deepak has moved
31 December 2025
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA26082502443)
Reason the builder gave MahaRERA:
“We, Advent Developers Private Limited, Promoters of the above-mentioned project, hereby submit this explanatory note in support of our request for an extension of the project completion date. 1. Grounds and Reasons for Delay The project has…” Read the full reason
“We, Advent Developers Private Limited, Promoters of the above-mentioned project, hereby submit this explanatory note in support of our request for an extension of the project completion date. 1. Grounds and Reasons for Delay The project has faced delays due to a combination of factors beyond our reasonable control: • Construction Challenges: The pace of RCC (Reinforced Cement Concrete) works slowed down due to logistical and manpower constraints during the initial phase. • Market Conditions: Considering prevailing real estate market trends and cautious buyer sentiment, we decided not to lau…”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Advent Deepak’s extension records on MahaRERA (P51800054861), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Advent Deepak
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800054861
- Status
- Registered and active
- Builder
- ADVENT DEVELOPERS PRIVATE LIMITED
- Location
- Malad West, Mumbai · 400064
- Project type
- Residential / Group Housing
- Registered on
- 15 Feb 2024
- Completion date at registration
- December 2025
- Latest completion date
- April 2028
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 74
- Sold or booked
- 2%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Advent Deepak, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| DEEPAK APARTMENT CHS LTD | 100% | 65% | 25% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- DEEPAK APARTMENT CHS LTD: covers 20 floors
Latest CC order on MahaRERA: dated 12/06/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Advent Deepak every 1–2 months.
Advent Deepak: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 436 | 38 |
| 3 BHK | 740 | 27 |
| 2 BHK | 549 | 9 |
- Buildings: DEEPAK APARTMENT CHS LTD (20 floors, 74 units)
- Car parking: 83 covered
- Land: 1,093 sq m (about 0.3 acres) · sanctioned built-up 4,221 sq m · recreational space 167 sq m
- Land, as filed: 83/10
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Advent Developers (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, 1 past the promised date (typically 6 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of Advent Deepak →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Advent Deepak: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Advent Deepak
What is the possession date of Advent Deepak?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Advent Deepak in Malad West, Mumbai is 30 April 2028 — 24 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Advent Deepak?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Advent Deepak's builder has filed on MahaRERA, the official one, is 30 April 2028, already 24 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Advent Deepak extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Advent Deepak's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "We, Advent Developers Private Limited, Promoters of the above-mentioned project, hereby submit this explanatory note in support of our request for an extension of the project completion date. 1. Grounds and Reasons for Delay The project has faced delays due to a combination of factors beyond our reasonable control: • Construction Challenges: The pace of RCC (Reinforced Cement Concrete) works slowed down due to logistical and manpower constraints during the initial phase. • Market Conditions: Considering prevailing real estate market trends and cautious buyer sentiment, we decided not to lau…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Advent Deepak?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Advent Deepak in Malad West, Mumbai is P51800054861.
Is Advent Deepak registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Advent Deepak is registered as P51800054861 and its status is "Registered and active".
What is the current construction status of Advent Deepak? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Advent Deepak's status on MahaRERA is "Registered and active". As filed by the builder, slab work on DEEPAK APARTMENT CHS LTD is 65% done and internal work 25%. GharKundli's full report compares construction progress with the deadline.
Does Advent Deepak have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Advent Deepak safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Advent Deepak is registered on MahaRERA as P51800054861, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Advent Deepak?
Advent Deepak is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Advent Deepak are 436 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Advent Deepak?
For a flat in Advent Deepak (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Advent Deepak received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Advent Deepak is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Advent Deepak a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Advent Deepak is a redevelopment: 26 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Advent Deepak uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Advent Deepak was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Advent Deepak's possession date changes?
The latest dates are on Advent Deepak's MahaRERA page (P51800054861). GharKundli's Kundli Watch sends a free WhatsApp update on Advent Deepak every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Advent Deepak have?
According to GharKundli's check of MahaRERA records (updated October 2026), Advent Deepak has one building filed: DEEPAK APARTMENT CHS LTD with 20 floors and 74 units.
What are the flat sizes (carpet area) in Advent Deepak?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Advent Deepak: 1 BHK: 436 sq ft carpet (38 homes); 3 BHK: 740 sq ft carpet (27 homes); 2 BHK: 549 sq ft carpet (9 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Advent Deepak have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 83 covered car parking spaces for Advent Deepak.
How big is the land of Advent Deepak?
According to GharKundli's check of MahaRERA records (updated October 2026), Advent Deepak stands on 1,093 sq m of land (about 0.3 acres), with 4,221 sq m of sanctioned built-up area and 167 sq m of recreational open space.
What is the track record of Advent Deepak's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Advent Developers (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, 1 past the promised date (typically 6 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Advent Deepak?
Google Maps has reviews of Advent Deepak written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Advent Deepak?
Advent Deepak by ADVENT DEVELOPERS PRIVATE LIMITED is in Malad West, Mumbai, pincode 400064 (near Borivali West, Vile Parle East, Goregaon West), Maharashtra, and is registered on MahaRERA as P51800054861, per GharKundli's check of MahaRERA records. Its land is filed as 83/10. GharKundli lists all 301 MahaRERA projects in Malad West (400064).
How many flats are in Advent Deepak, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Advent Deepak has 74 homes in 1 tower registered on MahaRERA, and 2% of them are sold or booked.
When was Advent Deepak registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Advent Deepak was registered on MahaRERA on 15 February 2024. GharKundli did not find a title report on the land on file there.
Does Advent Deepak have any legal issues or court cases?
No court cases are listed for Advent Deepak on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Advent Deepak?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ADVENT DEVELOPERS PRIVATE LIMITED, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Advent Deepak
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Malad West (400064)
- Florence Residency
- Aabiel Avenue
- Rashmi Icon
- Maru Mansion
- Rite Amor
- Avirahi Elegance
- Bhagat Grandeur
- Lotus Sky Garden
Other projects by ADVENT DEVELOPERS PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.