by SEAROCK CONSTRUCTIONS LLP · Khar West, Mumbai 400052Also near Bandra West, Bandra East, santacruz west

What’s in the report? →

Possession date of Searock Residences (MahaRERA P51800052899): 28 February 2027. It has 23 homes (2 BHK and 3 BHK, 994–4085 sq ft carpet), 20% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800052899, and currently active. Its completion date is now February 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800052899, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Searock Residences?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Searock Residences has moved

  1. 30 October 2026

    Completion date given when the project was registered

  2. 28 February 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Searock Residences’s extension records on MahaRERA (P51800052899), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Searock Residences

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the February 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800052899
Status
Registered and active
Builder
SEAROCK CONSTRUCTIONS LLP
Location
Khar West, Mumbai · 400052
Project type
Residential / Group Housing
Registered on
5 Oct 2023
Completion date at registration
October 2026
Latest completion date
February 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
23
Sold or booked
20%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Searock Residences, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SEAROCK RESIDENCES100%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • SEAROCK RESIDENCES: covers PLINTH LEVEL

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Searock Residences every 1–2 months.

Searock Residences: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK1,017 – 4,08522
2 BHK9941
Other1,8751
  • Buildings: SEAROCK RESIDENCES (21 floors, 24 units)
  • Car parking: 6 covered
  • Land: 871 sq m (about 0.2 acres) · sanctioned built-up 3,522 sq m
  • Boundaries filed include: Pali Hill Road, Union Park road no 1
  • Land, as filed: CTS NO. C/1629A 1/3A AND C/1629A 1/3B
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Searock Residences →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Searock Residences: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Searock Residences

What is the possession date of Searock Residences?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Searock Residences in Khar West, Mumbai is 28 February 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Searock Residences?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Searock Residences's builder has filed on MahaRERA, the official one, is 28 February 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Searock Residences?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Searock Residences in Khar West, Mumbai is P51800052899.

Is Searock Residences registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Searock Residences is registered as P51800052899 and its status is "Registered and active".

What is the current construction status of Searock Residences? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Searock Residences's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SEAROCK RESIDENCES is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Searock Residences have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Searock Residences safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Searock Residences is registered on MahaRERA as P51800052899, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Searock Residences?

Searock Residences is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Searock Residences start at 994 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Searock Residences?

For a flat in Searock Residences (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Searock Residences received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Searock Residences is still under construction, with 28 February 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Searock Residences a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Searock Residences is a redevelopment: 9 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Searock Residences uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Searock Residences was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Searock Residences's possession date changes?

The latest dates are on Searock Residences's MahaRERA page (P51800052899). GharKundli's Kundli Watch sends a free WhatsApp update on Searock Residences every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Searock Residences have?

According to GharKundli's check of MahaRERA records (updated October 2026), Searock Residences has one building filed: SEAROCK RESIDENCES with 21 floors and 24 units.

What are the flat sizes (carpet area) in Searock Residences?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Searock Residences: 3 BHK: 1017 to 4085 sq ft carpet (22 homes); 2 BHK: 994 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Searock Residences have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 6 covered car parking spaces for Searock Residences.

How big is the land of Searock Residences?

According to GharKundli's check of MahaRERA records (updated October 2026), Searock Residences stands on 871 sq m of land (about 0.2 acres), with 3,522 sq m of sanctioned built-up area.

What are the reviews of Searock Residences?

Google Maps has reviews of Searock Residences written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Searock Residences?

Searock Residences by SEAROCK CONSTRUCTIONS LLP is in Khar West, Mumbai, pincode 400052 (near Bandra West, Bandra East, santacruz west), Maharashtra, and is registered on MahaRERA as P51800052899, per GharKundli's check of MahaRERA records. Its boundaries filed there include Pali Hill Road, Union Park road no 1. Its land is filed as CTS NO. C/1629A 1/3A AND C/1629A 1/3B. GharKundli lists all 129 MahaRERA projects in Khar West (400052).

How many flats are in Searock Residences, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Searock Residences has 23 homes in 1 tower registered on MahaRERA, and 20% of them are sold or booked.

When was Searock Residences registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Searock Residences was registered on MahaRERA on 5 October 2023. GharKundli did not find a title report on the land on file there.

Does Searock Residences have any legal issues or court cases?

No court cases are listed for Searock Residences on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Searock Residences?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SEAROCK CONSTRUCTIONS LLP.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Khar West (400052)

All 129 projects in Khar West (400052) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.