Acenza Tower C
by Lodha Developers Limited · Andheri, Mumbai
Registered on MahaRERA under P51800052417, and currently active. Its completion date has moved from December 2027 to April 2028, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on Acenza Tower C
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800052417
- Status
- Registered and active
- Builder
- Lodha Developers Limited
- Location
- Andheri, Mumbai · 400069
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2023
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- Delay so far
- 4 months
- Homes
- 67
- Sold or booked
- 55%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 8
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 180
Kundli Watch
Acenza Tower C: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Acenza Tower C
Is Acenza Tower C registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Acenza Tower C is registered as P51800052417 and its status is "Registered and active".
Where is Acenza Tower C?
Acenza Tower C by Lodha Developers Limited is in Andheri, Mumbai (pincode 400069), Maharashtra, and is registered on MahaRERA as P51800052417, per GharKundli's check of MahaRERA records.
When is possession of Acenza Tower C due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Acenza Tower C in Andheri, Mumbai is 30 April 2028 — 4 months later than 31 December 2027, the date given at registration.
Does Acenza Tower C have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Acenza Tower C?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Lodha Developers Limited, which has 180 other projects registered on MahaRERA.
Other projects in pincode 400069
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.