Samarpeet Thapar Le Parc
by SAMARPEET PROPERTIES PVT LTD · Chembur, Mumbai 400071Also near Bhandup West, Ghatkopar East, KurlaRegistered on MahaRERA as “THAPAR LE PARC”
What’s in the report? →Possession date of Samarpeet Thapar Le Parc (MahaRERA P51800052495): 15 November 2026, moved from 30 June 2026 (5 months later), and it has already passed. It has 22 homes (3 BHK and 4 BHK, 1083–1886 sq ft carpet), 65% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800052495, and currently active.
Source: MahaRERA website — records for P51800052495, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (November 2026) has passed.
What do you want to know about Samarpeet Thapar Le Parc?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Samarpeet Thapar Le Parc has moved
30 June 2026
Completion date given when the project was registered
15 November 2026
Extended at the builder's request (MahaRERA application EA22072621830)
Reason the builder gave MahaRERA:
“The project has been completed in all respects, and the Occupancy Certificate (OC) has been received on 30/03/2026. We had applied for Project Completion But same was Sent Back due to data Mismatch on MahaRERA Portal. As project Completion…” Read the full reason
“The project has been completed in all respects, and the Occupancy Certificate (OC) has been received on 30/03/2026. We had applied for Project Completion But same was Sent Back due to data Mismatch on MahaRERA Portal. As project Completion date is 30/06/2026 ,it is practical not possible to Apply for correction and get the same approved Also. Hence we are advised by SRO to Withdraw the project completion application, Apply for Extension and then correction and final project completion application which will take 4-6 months in all.”
Source: Samarpeet Thapar Le Parc’s extension records on MahaRERA (P51800052495), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Samarpeet Thapar Le Parc
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800052495
- Status
- Registered and active
- Builder
- SAMARPEET PROPERTIES PVT LTD
- Location
- Chembur, Mumbai · 400071
- Project type
- Others
- Registered on
- 8 Sep 2023
- Completion date at registration
- June 2026
- Latest completion date
- November 2026
- Delay so far
- 5 months
- Homes
- 22
- Sold or booked
- 65%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Samarpeet Thapar Le Parc, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| THAPAR LE PARC | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- THAPAR LE PARC: covers Full CC
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Samarpeet Thapar Le Parc every 1–2 months.
Samarpeet Thapar Le Parc: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 1,083 – 1,169 | 21 |
| Other | 602 – 1,593 | 3 |
| Shops | 138 – 160 | 2 |
| Office Space | 269 – 555 | 2 |
| 4 BHK | 1,886 | 1 |
- Buildings: THAPAR LE PARC (14 floors, 29 units)
- Car parking: 66 covered
- Land: 1,006 sq m (about 0.2 acres) · sanctioned built-up 2,986 sq m
- Boundaries filed include: GAOTHAN ROAD
- Land, as filed: 1269, 1269/ 1 to 20
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Vedhas Realtors (a group of 2 linked companies) has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date. No complaints on MahaRERA.
Read Google reviews of Samarpeet Thapar Le Parc →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Samarpeet Thapar Le Parc: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Samarpeet Thapar Le Parc
What is the possession date of Samarpeet Thapar Le Parc?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Samarpeet Thapar Le Parc in Chembur, Mumbai is 15 November 2026 — 5 months later than 30 June 2026, the date given at registration. That date has already passed.
The date has already moved 5 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Samarpeet Thapar Le Parc?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Samarpeet Thapar Le Parc's builder has filed on MahaRERA, the official one, is 15 November 2026, already 5 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Samarpeet Thapar Le Parc extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Samarpeet Thapar Le Parc's builder applied to MahaRERA to extend the completion date once: to 15 November 2026, giving the reason "The project has been completed in all respects, and the Occupancy Certificate (OC) has been received on 30/03/2026. We had applied for Project Completion But same was Sent Back due to data Mismatch on MahaRERA Portal. As project Completion date is 30/06/2026 ,it is practical not possible to Apply for correction and get the same approved Also. Hence we are advised by SRO to Withdraw the project completion application, Apply for Extension and then correction and final project completion application which will take 4-6 months in all.".
What is the RERA number of Samarpeet Thapar Le Parc?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Samarpeet Thapar Le Parc in Chembur, Mumbai is P51800052495.
Is Samarpeet Thapar Le Parc registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Samarpeet Thapar Le Parc is registered as P51800052495 and its status is "Registered and active".
What is the current construction status of Samarpeet Thapar Le Parc? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Samarpeet Thapar Le Parc's status on MahaRERA is "Registered and active". As filed by the builder, slab work on THAPAR LE PARC is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Samarpeet Thapar Le Parc have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Samarpeet Thapar Le Parc safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Samarpeet Thapar Le Parc is registered on MahaRERA as P51800052495, its completion date has moved 5 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Samarpeet Thapar Le Parc?
Samarpeet Thapar Le Parc is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Samarpeet Thapar Le Parc start at 1083 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Samarpeet Thapar Le Parc?
For a flat in Samarpeet Thapar Le Parc (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Samarpeet Thapar Le Parc received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Samarpeet Thapar Le Parc is still under construction, with 15 November 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Samarpeet Thapar Le Parc a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Samarpeet Thapar Le Parc is a redevelopment: 7 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Samarpeet Thapar Le Parc uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Samarpeet Thapar Le Parc was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Samarpeet Thapar Le Parc's possession date changes?
The latest dates are on Samarpeet Thapar Le Parc's MahaRERA page (P51800052495). GharKundli's Kundli Watch sends a free WhatsApp update on Samarpeet Thapar Le Parc every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Samarpeet Thapar Le Parc have?
According to GharKundli's check of MahaRERA records (updated October 2026), Samarpeet Thapar Le Parc has one building filed: THAPAR LE PARC with 14 floors and 29 units.
What are the flat sizes (carpet area) in Samarpeet Thapar Le Parc?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Samarpeet Thapar Le Parc: 3 BHK: 1083 to 1169 sq ft carpet (21 homes); 4 BHK: 1886 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Samarpeet Thapar Le Parc have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 66 covered car parking spaces for Samarpeet Thapar Le Parc.
How big is the land of Samarpeet Thapar Le Parc?
According to GharKundli's check of MahaRERA records (updated October 2026), Samarpeet Thapar Le Parc stands on 1,006 sq m of land (about 0.2 acres), with 2,986 sq m of sanctioned built-up area.
What is the track record of Samarpeet Thapar Le Parc's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Vedhas Realtors (a group of 2 linked companies) has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Samarpeet Thapar Le Parc?
Google Maps has reviews of Samarpeet Thapar Le Parc written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Samarpeet Thapar Le Parc?
Samarpeet Thapar Le Parc by SAMARPEET PROPERTIES PVT LTD is in Chembur, Mumbai, pincode 400071 (near Bhandup West, Ghatkopar East, Kurla), Maharashtra, and is registered on MahaRERA as P51800052495, per GharKundli's check of MahaRERA records. Its boundaries filed there include GAOTHAN ROAD. Its land is filed as 1269, 1269/ 1 to 20. GharKundli lists all 318 MahaRERA projects in Chembur (400071).
How many flats are in Samarpeet Thapar Le Parc, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Samarpeet Thapar Le Parc has 22 homes in 1 tower registered on MahaRERA, and 65% of them are sold or booked.
When was Samarpeet Thapar Le Parc registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Samarpeet Thapar Le Parc was registered on MahaRERA on 8 September 2023. GharKundli did not find a title report on the land on file there.
Does Samarpeet Thapar Le Parc have any legal issues or court cases?
No court cases are listed for Samarpeet Thapar Le Parc on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Samarpeet Thapar Le Parc?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAMARPEET PROPERTIES PVT LTD.
Check it yourself on MahaRERA
- How to check the possession date of Samarpeet Thapar Le Parc
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Chembur (400071)
- 71 Pardis
- Tulsi Chamber Phase II
- Queens Park
- Sampoorna
- Shree Saraswati CHS LTD Plot 8B
- Icons 71
- Viera Golf Greens
- Arham Mourya
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.