Anant Siddhi
by Shri Anantnathji Maharaj Jain Temple and Its Sadharan Funds · Bahndup, Mumbai 400078
What’s in the report? →Possession date of Anant Siddhi (MahaRERA P51800052583): 31 July 2028. It has 139 homes (1 BHK, 2 BHK and 3 BHK, 439–1009 sq ft carpet), 78% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800052583, and currently active. Its completion date is now July 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51800052583, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Anant Siddhi?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Anant Siddhi has moved
31 March 2028
Completion date given when the project was registered
31 July 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Anant Siddhi’s extension records on MahaRERA (P51800052583), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Anant Siddhi
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800052583
- Status
- Registered and active
- Builder
- Shri Anantnathji Maharaj Jain Temple and Its Sadharan Funds
- Location
- Bahndup, Mumbai · 400078
- Project type
- Residential / Group Housing
- Registered on
- 11 Sep 2023
- Completion date at registration
- March 2028
- Latest completion date
- July 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 139
- Sold or booked
- 78%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Anant Siddhi, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Anant Siddhi | 100% | 100% | 85% | 15% |
Commencement certificate (CC), as filed on MahaRERA
- Anant Siddhi: covers 34 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Anant Siddhi every 1–2 months.
Anant Siddhi: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 439 – 440 | 58 |
| 2 BHK | 644 – 710 | 56 |
| 3 BHK | 792 | 24 |
| Shops | 362 – 1,064 | 21 |
| 4 BHK | 1,009 | 1 |
- Buildings: Anant Siddhi (41 floors, 160 units)
- Car parking: 240 covered
- Land: 3,307 sq m (about 0.8 acres) · sanctioned built-up 12,319 sq m · recreational space 661 sq m
- Boundaries filed include: LBS Road
- Land, as filed: 470,470/1
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Anant Siddhi →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Anant Siddhi: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Anant Siddhi
What is the possession date of Anant Siddhi?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Anant Siddhi in Bahndup, Mumbai is 31 July 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Anant Siddhi?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Anant Siddhi's builder has filed on MahaRERA, the official one, is 31 July 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Anant Siddhi?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Anant Siddhi in Bahndup, Mumbai is P51800052583.
Is Anant Siddhi registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Anant Siddhi is registered as P51800052583 and its status is "Registered and active".
What is the current construction status of Anant Siddhi? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Anant Siddhi's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Anant Siddhi is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.
Does Anant Siddhi have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Anant Siddhi safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Anant Siddhi is registered on MahaRERA as P51800052583, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Anant Siddhi?
Anant Siddhi is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Anant Siddhi are 439 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Anant Siddhi?
For a flat in Anant Siddhi (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Anant Siddhi received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Anant Siddhi is still under construction, with 31 July 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Anant Siddhi a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Anant Siddhi is a redevelopment: 56 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Anant Siddhi uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Anant Siddhi was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Anant Siddhi's possession date changes?
The latest dates are on Anant Siddhi's MahaRERA page (P51800052583). GharKundli's Kundli Watch sends a free WhatsApp update on Anant Siddhi every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Anant Siddhi have?
According to GharKundli's check of MahaRERA records (updated October 2026), Anant Siddhi has one building filed: Anant Siddhi with 41 floors and 160 units.
What are the flat sizes (carpet area) in Anant Siddhi?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Anant Siddhi: 1 BHK: 439 to 440 sq ft carpet (58 homes); 2 BHK: 644 to 710 sq ft carpet (56 homes); 3 BHK: 792 sq ft carpet (24 homes); 4 BHK: 1009 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Anant Siddhi have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 240 covered car parking spaces for Anant Siddhi.
How big is the land of Anant Siddhi?
According to GharKundli's check of MahaRERA records (updated October 2026), Anant Siddhi stands on 3,307 sq m of land (about 0.8 acres), with 12,319 sq m of sanctioned built-up area and 661 sq m of recreational open space.
What are the reviews of Anant Siddhi?
Google Maps has reviews of Anant Siddhi written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Anant Siddhi?
Anant Siddhi by Shri Anantnathji Maharaj Jain Temple and Its Sadharan Funds is in Bahndup, Mumbai, pincode 400078, Maharashtra, and is registered on MahaRERA as P51800052583, per GharKundli's check of MahaRERA records. Its boundaries filed there include LBS Road. Its land is filed as 470,470/1. GharKundli lists all 176 MahaRERA projects in Bhandup West (400078).
How many flats are in Anant Siddhi, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Anant Siddhi has 139 homes in 1 tower registered on MahaRERA, and 78% of them are sold or booked.
When was Anant Siddhi registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Anant Siddhi was registered on MahaRERA on 11 September 2023. GharKundli did not find a title report on the land on file there.
Does Anant Siddhi have any legal issues or court cases?
No court cases are listed for Anant Siddhi on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Anant Siddhi?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shri Anantnathji Maharaj Jain Temple and Its Sadharan Funds.
Check it yourself on MahaRERA
- How to check the possession date of Anant Siddhi
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Kurla
- Sudhanshu Heights
- Saptashringi
- Jai Arihant
- Kanakdhara
- Kalyan Kutir Co-operative Housing Society Limited
- Privilon
- Heritage Lakeside
- Malhar Guide
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.