Suji Platinum
by Shraddha Platinum Builders and Developers · Hariyali- Vikhroli East, MumbaiAlso near Tagore Nagar, kanamwar Nagar, vikroli
Possession date of Suji Platinum: 31 December 2027, moved from 31 January 2026 (23 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800053230, and currently active. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Suji Platinum?
How the possession date of Suji Platinum has moved
31 January 2026
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA23022619974)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. At the time of initial registration, our project was registered for a short duration of 27 months (from 23rd October 2023 to 31st January 2026),…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. At the time of initial registration, our project was registered for a short duration of 27 months (from 23rd October 2023 to 31st January 2026), based on an optimistic completion timeline. The project work commenced in October 2023. However, due to certain genuine and technical reasons, the project progress has been delayed. The key factors contributing to the delay are summarized below: 1. Small Plot Size & Phased Construction: Due to the limited plot area, simultaneous construction across the s…”
Source: Suji Platinum’s extension records on MahaRERA (P51800053230), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Suji Platinum
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800053230
- Status
- Registered and active
- Builder
- Shraddha Platinum Builders and Developers
- Location
- Hariyali- Vikhroli East, Mumbai · 400083
- Project type
- Others
- Registered on
- 23 Oct 2023
- Completion date at registration
- January 2026
- Latest completion date
- December 2027
- Delay so far
- 23 months
- Homes
- 166
- Sold or booked
- 76%
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Suji Platinum, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Suji Platinum | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Suji Platinum: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Suji Platinum every month.
Suji Platinum: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 363 | 124 |
| 2 BHK | 483 – 676 | 42 |
- Buildings: Suji Platinum (2 floors, 166 units)
- Land: 1,172 sq m (about 0.3 acres)
- Boundaries filed include: Aatmaram Surve Marg
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Suji Platinum Builders & Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 9 months late). 3 complaints on MahaRERA across 2 projects.
Read Google reviews of Suji Platinum →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Suji Platinum: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Suji Platinum
What is the possession date of Suji Platinum?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Suji Platinum in Hariyali- Vikhroli East, Mumbai is 31 December 2027 — 23 months later than 31 January 2026, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Suji Platinum?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Suji Platinum's builder has filed on MahaRERA, the official one, is 31 December 2027, already 23 months later than the 31 January 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Suji Platinum extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Suji Platinum's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. At the time of initial registration, our project was registered for a short duration of 27 months (from 23rd October 2023 to 31st January 2026), based on an optimistic completion timeline. The project work commenced in October 2023. However, due to certain genuine and technical reasons, the project progress has been delayed. The key factors contributing to the delay are summarized below: 1. Small Plot Size & Phased Construction: Due to the limited plot area, simultaneous construction across the s…".
What is the RERA number of Suji Platinum?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Suji Platinum in Hariyali- Vikhroli East, Mumbai is P51800053230.
Is Suji Platinum registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Suji Platinum is registered as P51800053230 and its status is "Registered and active".
What is the construction status of Suji Platinum?
According to GharKundli's check of MahaRERA records (updated October 2026), Suji Platinum's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Suji Platinum is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Suji Platinum have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Suji Platinum safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Suji Platinum is registered on MahaRERA as P51800053230, its completion date has moved 23 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Suji Platinum's possession date changes?
The latest dates are on Suji Platinum's MahaRERA page (P51800053230). GharKundli's Kundli Watch sends a free WhatsApp update on Suji Platinum every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Suji Platinum have?
According to GharKundli's check of MahaRERA records (updated October 2026), Suji Platinum has one building filed: Suji Platinum with 2 floors and 166 units.
What are the flat sizes (carpet area) in Suji Platinum?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Suji Platinum: 1 BHK: 363 sq ft carpet (124 homes); 2 BHK: 483 to 676 sq ft carpet (42 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Suji Platinum?
According to GharKundli's check of MahaRERA records (updated October 2026), Suji Platinum stands on 1,172 sq m of land (about 0.3 acres).
What is the track record of Suji Platinum's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Suji Platinum Builders & Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 9 months late). 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Suji Platinum?
Google Maps has reviews of Suji Platinum written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Suji Platinum?
Suji Platinum by Shraddha Platinum Builders and Developers is in Hariyali- Vikhroli East, Mumbai (pincode 400083), near Tagore Nagar, kanamwar Nagar, vikroli, Maharashtra, and is registered on MahaRERA as P51800053230, per GharKundli's check of MahaRERA records. Its boundaries filed there include Aatmaram Surve Marg.
How many homes are in Suji Platinum?
According to GharKundli's check of MahaRERA records (updated October 2026), Suji Platinum has 166 homes in 1 tower registered on MahaRERA, and 76% of them are sold or booked.
When was Suji Platinum registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Suji Platinum was registered on MahaRERA on 23 October 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Suji Platinum?
No court cases are listed for Suji Platinum on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Suji Platinum?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shraddha Platinum Builders and Developers.
Check it yourself on MahaRERA
- How to check the possession date of Suji Platinum
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Kurla
- SUDHANSHU HEIGHTS
- Saptashringi
- Jai Arihant
- Kalyan Kutir Co-operative Housing Society Limited
- Heritage Lakeside
- Kanakdhara
- Privilon
- Valentina CHS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.