OM SIDDHI SRA CHS LTD
by M/S. OM SIDDHI VENTURE · Dadar West, MumbaiAlso near Shivaji Park, Matunga, Mahim
Possession date of OM SIDDHI SRA CHS LTD: 31 December 2025, moved from 30 December 2020 (60 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900010775. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about OM SIDDHI SRA CHS LTD?
How the possession date of OM SIDDHI SRA CHS LTD has moved
30 December 2020
Completion date given when the project was registered
30 December 2021
Extended at the builder's request (MahaRERA application EXT51900011001)
Reason the builder gave MahaRERA:
“The Secretary, Date: 20/10/2021 Maharashtra Real Estate Regulatory Authority 3rd Floor, A-Wing, Slum Rehabilitation Authority, Administrative Building, Anant Kanekar Marg, Bandra (E), Mumbai 400051 SUBJECT: Extension of Date of Completion o…” Read the full reason
“The Secretary, Date: 20/10/2021 Maharashtra Real Estate Regulatory Authority 3rd Floor, A-Wing, Slum Rehabilitation Authority, Administrative Building, Anant Kanekar Marg, Bandra (E), Mumbai 400051 SUBJECT: Extension of Date of Completion of the project ‘OM SIDDHI SRA CHS LTD’ RERA Registration Number: P51900010775 Dear Sir, With reference to the captioned subject, we would like to inform your goodself that our project ‘OM SIDDHI SRA CHS LTD’ is registered on the MahaRERA webportal vide Registration Number: P51900010775. The registration certificate was issued for the period ending 31 Decem…”31 December 2025
Extended at the builder's request (MahaRERA application EXT51900016501)
Reason the builder gave MahaRERA:
“Date: 24/04/2023. To, The Secretary, Maharashtra Real Estate Regulatory Authority, Housefin Bhavan, Plot No.C-21, E-Block, Bandra-Kurla Complex, Bandra (E), Mumbai - 400 051 Sub: Extension of Date of Completion of the project ‘OM SIDDHI (SR…” Read the full reason
“Date: 24/04/2023. To, The Secretary, Maharashtra Real Estate Regulatory Authority, Housefin Bhavan, Plot No.C-21, E-Block, Bandra-Kurla Complex, Bandra (E), Mumbai - 400 051 Sub: Extension of Date of Completion of the project ‘OM SIDDHI (SRA) CHS LTD.’ RERA Registration Number: P51900010775. Sir, With reference to the captioned subject, we would like to inform your goodself that, our/the promoter’s project ‘OM SIDDHI (SRA) CHS LTD’ is registered on the MahaRERA Web Portal vide Registration Number: P51900010775. The Registration Certificate was issued for the period ending 30th June, 2022 (A…”
Source: OM SIDDHI SRA CHS LTD’s extension records on MahaRERA (P51900010775), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on OM SIDDHI SRA CHS LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900010775
- Status
- Lapsed (registration period ended)
- Builder
- M/S. OM SIDDHI VENTURE
- Location
- Dadar West, Mumbai · 400028
- Project type
- Others
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2020
- Latest completion date
- December 2025
- Delay so far
- 60 months
- Homes
- 49
- Sold or booked
- 89%
- Towers
- 2
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of OM SIDDHI SRA CHS LTD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| OM SIDDHI SRA CHS LTD | 100% | 100% | 98% | 95% |
| GRAND PALLAZO | 100% | 100% | 95% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- OM SIDDHI SRA CHS LTD: covers 23 floors
- GRAND PALLAZO: covers 25 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on OM SIDDHI SRA CHS LTD every month.
OM SIDDHI SRA CHS LTD: buildings, flats and land, as filed on MahaRERA
- Buildings: OM SIDDHI SRA CHS LTD (23 floors, 14 units) · GRAND PALLAZO (25 floors, 40 units)
- Land: 2,151 sq m (about 0.5 acres) · sanctioned built-up 6,451 sq m · recreational space 212 sq m
- Boundaries filed include: SHANKAR GHANEKAR MARG, GOKHALE ROAD SOUTH
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of OM SIDDHI SRA CHS LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
OM SIDDHI SRA CHS LTD: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about OM SIDDHI SRA CHS LTD
What is the possession date of OM SIDDHI SRA CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for OM SIDDHI SRA CHS LTD in Dadar West, Mumbai is 31 December 2025 — 60 months later than 30 December 2020, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for OM SIDDHI SRA CHS LTD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date OM SIDDHI SRA CHS LTD's builder has filed on MahaRERA, the official one, is 31 December 2025, already 60 months later than the 30 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of OM SIDDHI SRA CHS LTD extended?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SIDDHI SRA CHS LTD's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2021, giving the reason "The Secretary, Date: 20/10/2021 Maharashtra Real Estate Regulatory Authority 3rd Floor, A-Wing, Slum Rehabilitation Authority, Administrative Building, Anant Kanekar Marg, Bandra (E), Mumbai 400051 SUBJECT: Extension of Date of Completion of the project ‘OM SIDDHI SRA CHS LTD’ RERA Registration Number: P51900010775 Dear Sir, With reference to the captioned subject, we would like to inform your goodself that our project ‘OM SIDDHI SRA CHS LTD’ is registered on the MahaRERA webportal vide Registration Number: P51900010775. The registration certificate was issued for the period ending 31 Decem…"; to 31 December 2025, giving the reason "Date: 24/04/2023. To, The Secretary, Maharashtra Real Estate Regulatory Authority, Housefin Bhavan, Plot No.C-21, E-Block, Bandra-Kurla Complex, Bandra (E), Mumbai - 400 051 Sub: Extension of Date of Completion of the project ‘OM SIDDHI (SRA) CHS LTD.’ RERA Registration Number: P51900010775. Sir, With reference to the captioned subject, we would like to inform your goodself that, our/the promoter’s project ‘OM SIDDHI (SRA) CHS LTD’ is registered on the MahaRERA Web Portal vide Registration Number: P51900010775. The Registration Certificate was issued for the period ending 30th June, 2022 (A…".
What is the RERA number of OM SIDDHI SRA CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of OM SIDDHI SRA CHS LTD in Dadar West, Mumbai is P51900010775.
Is OM SIDDHI SRA CHS LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SIDDHI SRA CHS LTD is registered as P51900010775 and its status is "Lapsed (registration period ended)".
What is the construction status of OM SIDDHI SRA CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SIDDHI SRA CHS LTD's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does OM SIDDHI SRA CHS LTD have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is OM SIDDHI SRA CHS LTD safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SIDDHI SRA CHS LTD is registered on MahaRERA as P51900010775, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 60 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if OM SIDDHI SRA CHS LTD's possession date changes?
The latest dates are on OM SIDDHI SRA CHS LTD's MahaRERA page (P51900010775). GharKundli's Kundli Watch sends a free WhatsApp update on OM SIDDHI SRA CHS LTD every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does OM SIDDHI SRA CHS LTD have?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SIDDHI SRA CHS LTD has 2 buildings filed: OM SIDDHI SRA CHS LTD with 23 floors and 14 units; GRAND PALLAZO with 25 floors and 40 units.
How big is the land of OM SIDDHI SRA CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SIDDHI SRA CHS LTD stands on 2,151 sq m of land (about 0.5 acres), with 6,451 sq m of sanctioned built-up area and 212 sq m of recreational open space.
Where can I read reviews of OM SIDDHI SRA CHS LTD?
Google Maps has reviews of OM SIDDHI SRA CHS LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is OM SIDDHI SRA CHS LTD?
OM SIDDHI SRA CHS LTD by M/S. OM SIDDHI VENTURE is in Dadar West, Mumbai (pincode 400028), near Shivaji Park, Matunga, Mahim, Maharashtra, and is registered on MahaRERA as P51900010775, per GharKundli's check of MahaRERA records. Its boundaries filed there include SHANKAR GHANEKAR MARG, GOKHALE ROAD SOUTH.
How many homes are in OM SIDDHI SRA CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SIDDHI SRA CHS LTD has 49 homes in 2 towers registered on MahaRERA, and 89% of them are sold or booked.
When was OM SIDDHI SRA CHS LTD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), OM SIDDHI SRA CHS LTD was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on OM SIDDHI SRA CHS LTD?
No court cases are listed for OM SIDDHI SRA CHS LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of OM SIDDHI SRA CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/S. OM SIDDHI VENTURE.
Check it yourself on MahaRERA
- How to check the possession date of OM SIDDHI SRA CHS LTD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Ward GNorth
All 148 projects in Dadar West (400028) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.