What’s in the report? →Possession date of Parsn Bhagyalakshmi (MahaRERA P51800053232): 31 May 2027, moved from 31 July 2026 (6 months later). It has 32 homes (2 BHK, 638–792 sq ft carpet), 89% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800053232, and currently active. Its completion date has moved from July 2026 to May 2027: 6 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800053232, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Parsn Bhagyalakshmi?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Parsn Bhagyalakshmi has moved
31 July 2026
Completion date given when the project was registered
31 January 2027
Extended at the builder's request (MahaRERA application EA25062621529)
Reason the builder gave MahaRERA:
“Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of…” Read the full reason
“Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely impacted the financial inflow required for the timely completion of the project, as the anticipated funding from customer bookings could not be realized. Despite these challenges, the promoters have demonstrated unwavering commitment to the project's completion by arranging the necessary funds through the liquidation of…”31 May 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Parsn Bhagyalakshmi’s extension records on MahaRERA (P51800053232), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Parsn Bhagyalakshmi
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the May 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800053232
- Status
- Registered and active
- Builder
- PARSN LIFESPACES
- Location
- Chembur, Mumbai · 400071
- Project type
- Residential / Group Housing
- Registered on
- 23 Oct 2023
- Completion date at registration
- July 2026
- Latest completion date
- May 2027
- Delay so far
- 6 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 32
- Sold or booked
- 89%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Parsn Bhagyalakshmi, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PARSN BHAGYALAKSHMI | 100% | 100% | 85% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- PARSN BHAGYALAKSHMI: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Parsn Bhagyalakshmi every 1–2 months.
Parsn Bhagyalakshmi: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 638 – 792 | 32 |
- Buildings: PARSN BHAGYALAKSHMI (5 floors, 32 units)
- Car parking: 12 covered
- Land: 845 sq m (about 0.2 acres) · sanctioned built-up 1,259 sq m
- Boundaries filed include: GAOTHAN ROAD NO 3, GAOTHAN ROAD NO 2
- Land, as filed: 1086, 1086 1 to 4
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Parsn Construction AND Developers (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 57 months); 6 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 18 complaints on MahaRERA across 3 projects.
Read Google reviews of Parsn Bhagyalakshmi →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Parsn Bhagyalakshmi: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Parsn Bhagyalakshmi
What is the possession date of Parsn Bhagyalakshmi?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Parsn Bhagyalakshmi in Chembur, Mumbai is 31 May 2027 — 6 months later than 31 July 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 6 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Parsn Bhagyalakshmi?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Parsn Bhagyalakshmi's builder has filed on MahaRERA, the official one, is 31 May 2027, already 6 months later than the 31 July 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Parsn Bhagyalakshmi extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Parsn Bhagyalakshmi's builder applied to MahaRERA to extend the completion date once: to 31 January 2027, giving the reason "Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely impacted the financial inflow required for the timely completion of the project, as the anticipated funding from customer bookings could not be realized. Despite these challenges, the promoters have demonstrated unwavering commitment to the project's completion by arranging the necessary funds through the liquidation of…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Parsn Bhagyalakshmi?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Parsn Bhagyalakshmi in Chembur, Mumbai is P51800053232.
Is Parsn Bhagyalakshmi registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Parsn Bhagyalakshmi is registered as P51800053232 and its status is "Registered and active".
What is the current construction status of Parsn Bhagyalakshmi? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Parsn Bhagyalakshmi's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PARSN BHAGYALAKSHMI is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.
Does Parsn Bhagyalakshmi have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Parsn Bhagyalakshmi safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Parsn Bhagyalakshmi is registered on MahaRERA as P51800053232, its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Parsn Bhagyalakshmi?
Parsn Bhagyalakshmi is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Parsn Bhagyalakshmi are 638 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Parsn Bhagyalakshmi?
For a flat in Parsn Bhagyalakshmi (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Parsn Bhagyalakshmi received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Parsn Bhagyalakshmi is still under construction, with 31 May 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Parsn Bhagyalakshmi uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Parsn Bhagyalakshmi was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Parsn Bhagyalakshmi's possession date changes?
The latest dates are on Parsn Bhagyalakshmi's MahaRERA page (P51800053232). GharKundli's Kundli Watch sends a free WhatsApp update on Parsn Bhagyalakshmi every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Parsn Bhagyalakshmi have?
According to GharKundli's check of MahaRERA records (updated October 2026), Parsn Bhagyalakshmi has one building filed: PARSN BHAGYALAKSHMI with 5 floors and 32 units.
What are the flat sizes (carpet area) in Parsn Bhagyalakshmi?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Parsn Bhagyalakshmi: 2 BHK: 638 to 792 sq ft carpet (32 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Parsn Bhagyalakshmi have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 12 covered car parking spaces for Parsn Bhagyalakshmi.
How big is the land of Parsn Bhagyalakshmi?
According to GharKundli's check of MahaRERA records (updated October 2026), Parsn Bhagyalakshmi stands on 845 sq m of land (about 0.2 acres), with 1,259 sq m of sanctioned built-up area.
What is the track record of Parsn Bhagyalakshmi's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Parsn Construction AND Developers (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 57 months); 6 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 18 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Parsn Bhagyalakshmi?
Google Maps has reviews of Parsn Bhagyalakshmi written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Parsn Bhagyalakshmi?
Parsn Bhagyalakshmi by PARSN LIFESPACES is in Chembur, Mumbai, pincode 400071 (near Santacruz East, Vakola, Andheri), Maharashtra, and is registered on MahaRERA as P51800053232, per GharKundli's check of MahaRERA records. Its boundaries filed there include GAOTHAN ROAD NO 3, GAOTHAN ROAD NO 2. Its land is filed as 1086, 1086 1 to 4. GharKundli lists all 318 MahaRERA projects in Chembur (400071).
How many flats are in Parsn Bhagyalakshmi, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Parsn Bhagyalakshmi has 32 homes in 1 tower registered on MahaRERA, and 89% of them are sold or booked.
When was Parsn Bhagyalakshmi registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Parsn Bhagyalakshmi was registered on MahaRERA on 23 October 2023. GharKundli did not find a title report on the land on file there.
Does Parsn Bhagyalakshmi have any legal issues or court cases?
No court cases are listed for Parsn Bhagyalakshmi on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Parsn Bhagyalakshmi?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PARSN LIFESPACES.
Check it yourself on MahaRERA
- How to check the possession date of Parsn Bhagyalakshmi
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Chembur (400071)
- 71 Pardis
- Tulsi Chamber Phase II
- Queens Park
- Sampoorna
- Shree Saraswati CHS LTD Plot 8B
- Icons 71
- Viera Golf Greens
- Arham Mourya
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.