ANANTA

by K AJMERA DEVELOPERS · Nahur Mulund West, MumbaiAlso near Bhandup West, Mulund East

Possession date of ANANTA: 31 August 2026, moved from 31 August 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800053780. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (August 2026) has passed.

What do you want to know about ANANTA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ANANTA has moved

  1. 31 August 2025

    Completion date given when the project was registered

  2. 31 August 2026

    Extended at the builder's request (MahaRERA application EA18072502103)

    Reason the builder gave MahaRERA:
    “We Would like to request you that the Project Estella which is located at Plot Bearing CTS no.551/51 of Village Nahur, at Vishwakarma Marg, Mulund West, Mumbai 400 080. having its Registration No P518000053780 was mentioned to be completed…” Read the full reason“We Would like to request you that the Project Estella which is located at Plot Bearing CTS no.551/51 of Village Nahur, at Vishwakarma Marg, Mulund West, Mumbai 400 080. having its Registration No P518000053780 was mentioned to be completed on 31 August 2025. Due to delay from contractor in completing work the project was not able to complete in time. We would like to request you to further grant us extension for 12 Months We request you kindly grant us the certificate at the earliest. Thanking You,”

Source: ANANTA’s extension records on MahaRERA (P51800053780), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ANANTA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the August 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800053780
Status
Lapsed (registration period ended)
Builder
K AJMERA DEVELOPERS
Location
Nahur Mulund West, Mumbai · 400080
Project type
Others
Registered on
28 Nov 2023
Completion date at registration
August 2025
Latest completion date
August 2026
Delay so far
12 months
Homes
75
Sold or booked
36%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of ANANTA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ANANTA100%90%80%0%

Commencement certificate (CC), as filed on MahaRERA

  • ANANTA: covers PLINTH LEVEL

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ANANTA every month.

ANANTA: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK456 – 1,00654
3 BHK819 – 1,16518
Shops2,424 – 2,4922
1 BHK456 – 6192
4 BHK1,1651
  • Buildings: ANANTA (21 floors, 77 units)
  • Car parking: 76 covered
  • Land: 1,583 sq m (about 0.4 acres) · sanctioned built-up 5,069 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of ANANTA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ANANTA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ANANTA

What is the possession date of ANANTA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ANANTA in Nahur Mulund West, Mumbai is 31 August 2026 — 12 months later than 31 August 2025, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for ANANTA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ANANTA's builder has filed on MahaRERA, the official one, is 31 August 2026, already 12 months later than the 31 August 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ANANTA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), ANANTA's builder applied to MahaRERA to extend the completion date once: to 31 August 2026, giving the reason "We Would like to request you that the Project Estella which is located at Plot Bearing CTS no.551/51 of Village Nahur, at Vishwakarma Marg, Mulund West, Mumbai 400 080. having its Registration No P518000053780 was mentioned to be completed on 31 August 2025. Due to delay from contractor in completing work the project was not able to complete in time. We would like to request you to further grant us extension for 12 Months We request you kindly grant us the certificate at the earliest. Thanking You,".

What is the RERA number of ANANTA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ANANTA in Nahur Mulund West, Mumbai is P51800053780.

Is ANANTA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ANANTA is registered as P51800053780 and its status is "Lapsed (registration period ended)".

What is the construction status of ANANTA?

According to GharKundli's check of MahaRERA records (updated October 2026), ANANTA's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on ANANTA is 90% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does ANANTA have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is ANANTA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ANANTA is registered on MahaRERA as P51800053780, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ANANTA's possession date changes?

The latest dates are on ANANTA's MahaRERA page (P51800053780). GharKundli's Kundli Watch sends a free WhatsApp update on ANANTA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ANANTA have?

According to GharKundli's check of MahaRERA records (updated October 2026), ANANTA has one building filed: ANANTA with 21 floors and 77 units.

What are the flat sizes (carpet area) in ANANTA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for ANANTA: 2 BHK: 456 to 1006 sq ft carpet (54 homes); 3 BHK: 819 to 1165 sq ft carpet (18 homes); 1 BHK: 456 to 619 sq ft carpet (2 homes); 4 BHK: 1165 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does ANANTA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 76 covered car parking spaces for ANANTA.

How big is the land of ANANTA?

According to GharKundli's check of MahaRERA records (updated October 2026), ANANTA stands on 1,583 sq m of land (about 0.4 acres), with 5,069 sq m of sanctioned built-up area.

Where can I read reviews of ANANTA?

Google Maps has reviews of ANANTA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ANANTA?

ANANTA by K AJMERA DEVELOPERS is in Nahur Mulund West, Mumbai (pincode 400080), near Bhandup West, Mulund East, Maharashtra, and is registered on MahaRERA as P51800053780, per GharKundli's check of MahaRERA records.

How many homes are in ANANTA?

According to GharKundli's check of MahaRERA records (updated October 2026), ANANTA has 75 homes in 1 tower registered on MahaRERA, and 36% of them are sold or booked.

When was ANANTA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ANANTA was registered on MahaRERA on 28 November 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on ANANTA?

No court cases are listed for ANANTA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of ANANTA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is K AJMERA DEVELOPERS.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in pincode 400080

All 303 projects in Mulund West (400080) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.