Shambhavi Sai Jyoti
by Shambhavi Enterprises · Khar West, Mumbai 400052Also near Bandra West, Santacruz West, Bandra EastRegistered on MahaRERA as “Sai Jyoti”
What’s in the report? →Possession date of Shambhavi Sai Jyoti (MahaRERA P51800054144): 30 April 2027. It has 17 homes (1 BHK, 2 BHK and 4 BHK, 575–1297 sq ft carpet), 33% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800054144, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51800054144, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shambhavi Sai Jyoti?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shambhavi Sai Jyoti has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shambhavi Sai Jyoti’s extension records on MahaRERA (P51800054144), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shambhavi Sai Jyoti
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800054144
- Status
- Registered and active
- Builder
- Shambhavi Enterprises
- Location
- Khar West, Mumbai · 400052
- Project type
- Residential / Group Housing
- Registered on
- 29 Dec 2023
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 17
- Sold or booked
- 33%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shambhavi Sai Jyoti, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sai Jyoti | 100% | 100% | 50% | 50% |
Commencement certificate (CC), as filed on MahaRERA
- Sai Jyoti: covers 11 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shambhavi Sai Jyoti every 1–2 months.
Shambhavi Sai Jyoti: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 688 – 750 | 9 |
| 4 BHK | 1,297 | 7 |
| 1 BHK | 575 | 1 |
- Buildings: Sai Jyoti (11 floors, 17 units)
- Car parking: 20 covered, 7 open
- Land: 604 sq m (about 0.1 acres) · sanctioned built-up 1,630 sq m
- Land, as filed: E/642
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shambhavi Sai Jyoti →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shambhavi Sai Jyoti: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shambhavi Sai Jyoti
What is the possession date of Shambhavi Sai Jyoti?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shambhavi Sai Jyoti in Khar West, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Shambhavi Sai Jyoti?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shambhavi Sai Jyoti's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Shambhavi Sai Jyoti?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shambhavi Sai Jyoti in Khar West, Mumbai is P51800054144.
Is Shambhavi Sai Jyoti registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shambhavi Sai Jyoti is registered as P51800054144 and its status is "Registered and active".
What is the current construction status of Shambhavi Sai Jyoti? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shambhavi Sai Jyoti's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sai Jyoti is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does Shambhavi Sai Jyoti have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shambhavi Sai Jyoti safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shambhavi Sai Jyoti is registered on MahaRERA as P51800054144, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shambhavi Sai Jyoti?
Shambhavi Sai Jyoti is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Shambhavi Sai Jyoti are 575 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shambhavi Sai Jyoti?
For a flat in Shambhavi Sai Jyoti (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Shambhavi Sai Jyoti received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shambhavi Sai Jyoti is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Shambhavi Sai Jyoti a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Shambhavi Sai Jyoti is a redevelopment: 8 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Shambhavi Sai Jyoti uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shambhavi Sai Jyoti was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shambhavi Sai Jyoti's possession date changes?
The latest dates are on Shambhavi Sai Jyoti's MahaRERA page (P51800054144). GharKundli's Kundli Watch sends a free WhatsApp update on Shambhavi Sai Jyoti every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shambhavi Sai Jyoti have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shambhavi Sai Jyoti has one building filed: Sai Jyoti with 11 floors and 17 units.
What are the flat sizes (carpet area) in Shambhavi Sai Jyoti?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shambhavi Sai Jyoti: 2 BHK: 688 to 750 sq ft carpet (9 homes); 4 BHK: 1297 sq ft carpet (7 homes); 1 BHK: 575 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Shambhavi Sai Jyoti have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 20 covered and 7 open car parking spaces for Shambhavi Sai Jyoti.
How big is the land of Shambhavi Sai Jyoti?
According to GharKundli's check of MahaRERA records (updated October 2026), Shambhavi Sai Jyoti stands on 604 sq m of land (about 0.1 acres), with 1,630 sq m of sanctioned built-up area.
What are the reviews of Shambhavi Sai Jyoti?
Google Maps has reviews of Shambhavi Sai Jyoti written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shambhavi Sai Jyoti?
Shambhavi Sai Jyoti by Shambhavi Enterprises is in Khar West, Mumbai, pincode 400052 (near Bandra West, Santacruz West, Bandra East), Maharashtra, and is registered on MahaRERA as P51800054144, per GharKundli's check of MahaRERA records. Its land is filed as E/642. GharKundli lists all 129 MahaRERA projects in Khar West (400052).
How many flats are in Shambhavi Sai Jyoti, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Shambhavi Sai Jyoti has 17 homes in 1 tower registered on MahaRERA, and 33% of them are sold or booked.
When was Shambhavi Sai Jyoti registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shambhavi Sai Jyoti was registered on MahaRERA on 29 December 2023. GharKundli did not find a title report on the land on file there.
Does Shambhavi Sai Jyoti have any legal issues or court cases?
No court cases are listed for Shambhavi Sai Jyoti on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shambhavi Sai Jyoti?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shambhavi Enterprises.
Check it yourself on MahaRERA
- How to check the possession date of Shambhavi Sai Jyoti
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Khar West (400052)
- Atlantis Tower
- Sach Splendid
- DLH One
- Worq by S Raheja
- Rustomjee Crescent
- Evershine Bliss
- SM Royale
- Benchmark Plaza
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.