by M/S. SURYASHOBHA HOMES LLP · Vile Parle East, Mumbai 400057Also near Vile Parle West, Vileparle East, Andheri EastRegistered on MahaRERA as “RAMKRISHNA”

What’s in the report? →

Possession date of Suryashobha Ramkrishna (MahaRERA P51800054622): 30 April 2027, moved from 31 March 2025 (21 months later). It has 38 homes (1 Room Kitchen, 1 BHK and 2 BHK, 169–1053 sq ft carpet), 38% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800054622, and currently active. Its completion date has moved from March 2025 to April 2027: 21 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800054622, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Suryashobha Ramkrishna?

1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Suryashobha Ramkrishna has moved

  1. 31 March 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA08092502527)

    Reason the builder gave MahaRERA:
    “The project was originally scheduled for completion by March 31, 2025. However, due to low sales and the lack of additional Floor Space Index (FSI) available under Regulation 33(12)B of the DCPR 2034, we were unable to meet this deadline. W…” Read the full reason“The project was originally scheduled for completion by March 31, 2025. However, due to low sales and the lack of additional Floor Space Index (FSI) available under Regulation 33(12)B of the DCPR 2034, we were unable to meet this deadline. We assure the authorities that we will complete the project no later than December 31, 2026, in time for the issuance of the full occupancy certificate.”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Suryashobha Ramkrishna’s extension records on MahaRERA (P51800054622), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Suryashobha Ramkrishna

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800054622
Status
Registered and active
Builder
M/S. SURYASHOBHA HOMES LLP
Location
Vile Parle East, Mumbai · 400057
Project type
Residential / Group Housing
Registered on
2 Feb 2024
Completion date at registration
March 2025
Latest completion date
April 2027
Delay so far
21 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
38
Sold or booked
38%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found

Construction progress of Suryashobha Ramkrishna, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
RAMKRISHNA100%100%100%75%

Commencement certificate (CC), as filed on MahaRERA

  • RAMKRISHNA: covers C.C. up to 10th floor

Latest CC order on MahaRERA: dated 22/04/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Suryashobha Ramkrishna every 1–2 months.

Suryashobha Ramkrishna: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK530 – 1,05320
1 Room Kitchen169 – 4029
1 BHK398 – 6547
3 BHK809 – 8752

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Suryashobha Ramkrishna →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Suryashobha Ramkrishna: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Suryashobha Ramkrishna

What is the possession date of Suryashobha Ramkrishna?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Suryashobha Ramkrishna in Vile Parle East, Mumbai is 30 April 2027 — 21 months later than 31 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 21 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Suryashobha Ramkrishna?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Suryashobha Ramkrishna's builder has filed on MahaRERA, the official one, is 30 April 2027, already 21 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Suryashobha Ramkrishna extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Suryashobha Ramkrishna's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The project was originally scheduled for completion by March 31, 2025. However, due to low sales and the lack of additional Floor Space Index (FSI) available under Regulation 33(12)B of the DCPR 2034, we were unable to meet this deadline. We assure the authorities that we will complete the project no later than December 31, 2026, in time for the issuance of the full occupancy certificate.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Suryashobha Ramkrishna?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Suryashobha Ramkrishna in Vile Parle East, Mumbai is P51800054622.

Is Suryashobha Ramkrishna registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Suryashobha Ramkrishna is registered as P51800054622 and its status is "Registered and active".

What is the current construction status of Suryashobha Ramkrishna? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Suryashobha Ramkrishna's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RAMKRISHNA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Suryashobha Ramkrishna have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Suryashobha Ramkrishna safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Suryashobha Ramkrishna is registered on MahaRERA as P51800054622, its completion date has moved 21 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Suryashobha Ramkrishna?

Suryashobha Ramkrishna is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Suryashobha Ramkrishna are 169 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Suryashobha Ramkrishna?

For a flat in Suryashobha Ramkrishna (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Suryashobha Ramkrishna received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Suryashobha Ramkrishna is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Suryashobha Ramkrishna a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Suryashobha Ramkrishna is a redevelopment: 22 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Suryashobha Ramkrishna uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Suryashobha Ramkrishna was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Suryashobha Ramkrishna's possession date changes?

The latest dates are on Suryashobha Ramkrishna's MahaRERA page (P51800054622). GharKundli's Kundli Watch sends a free WhatsApp update on Suryashobha Ramkrishna every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Suryashobha Ramkrishna have?

According to GharKundli's check of MahaRERA records (updated October 2026), Suryashobha Ramkrishna has one building filed: RAMKRISHNA with 10 floors and 38 units.

What are the flat sizes (carpet area) in Suryashobha Ramkrishna?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Suryashobha Ramkrishna: 2 BHK: 530 to 1053 sq ft carpet (20 homes); 1 Room Kitchen: 169 to 402 sq ft carpet (9 homes); 1 BHK: 398 to 654 sq ft carpet (7 homes); 3 BHK: 809 to 875 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Suryashobha Ramkrishna have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 22 covered car parking spaces for Suryashobha Ramkrishna.

How big is the land of Suryashobha Ramkrishna?

According to GharKundli's check of MahaRERA records (updated October 2026), Suryashobha Ramkrishna stands on 386 sq m of land (about 0.1 acres), with 1,974 sq m of sanctioned built-up area.

What are the reviews of Suryashobha Ramkrishna?

Google Maps has reviews of Suryashobha Ramkrishna written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Suryashobha Ramkrishna?

Suryashobha Ramkrishna by M/S. SURYASHOBHA HOMES LLP is in Vile Parle East, Mumbai, pincode 400057 (near Vile Parle West, Vileparle East, Andheri East), Maharashtra, and is registered on MahaRERA as P51800054622, per GharKundli's check of MahaRERA records. Its boundaries filed there include SANT MUKTABAI ROAD. Its land is filed as 312. GharKundli lists all 251 MahaRERA projects in Vile Parle East (400057).

How many flats are in Suryashobha Ramkrishna, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Suryashobha Ramkrishna has 38 homes in 1 tower registered on MahaRERA, and 38% of them are sold or booked.

When was Suryashobha Ramkrishna registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Suryashobha Ramkrishna was registered on MahaRERA on 2 February 2024. GharKundli did not find a title report on the land on file there.

Does Suryashobha Ramkrishna have any legal issues or court cases?

1 court case is listed for Suryashobha Ramkrishna on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Suryashobha Ramkrishna?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S. SURYASHOBHA HOMES LLP.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Vile Parle East (400057)

All 251 projects in Vile Parle East (400057) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.