Skip to content
GharKundli

Lotus Kuber Villa

by M/s. LOTUS VENTURES LLP · Vile Parle West, Mumbai 400056Also near Juhu, Vile Parle East, Santacruz WestRegistered on MahaRERA as “KUBER VILLA”

What’s in the report? →

Possession date of Lotus Kuber Villa (MahaRERA P51800054808): 30 October 2026, and it has already passed. It has 15 homes, 47% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800054808, and currently active. Its completion date is now October 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800054808, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about Lotus Kuber Villa?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Lotus Kuber Villa has moved

  1. 30 June 2026

    Completion date given when the project was registered

  2. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Lotus Kuber Villa’s extension records on MahaRERA (P51800054808), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Lotus Kuber Villa

Ready · October 2026 · 39 filings read

Risk & trust score locked/100
  • Risk & trust score, every point explained
  • What the title report on MahaRERA says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800054808
Status
Registered and active
Builder
M/s. LOTUS VENTURES LLP
Location
Vile Parle West, Mumbai · 400056
Project type
Residential / Group Housing
Registered on
12 Feb 2024
Completion date at registration
June 2026
Latest completion date
October 2026
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
15
Sold or booked
47%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Yes
Latest construction certificate
28 May 2024

Construction progress of Lotus Kuber Villa, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KUBER VILLA100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • KUBER VILLA: covers 14 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lotus Kuber Villa every 1–2 months.

Lotus Kuber Villa: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
5 BHK—9
3 BHK—4
4 BHK—2

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Lotus Kuber Villa →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Lotus Kuber Villa: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Lotus Kuber Villa

What is the possession date of Lotus Kuber Villa?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Lotus Kuber Villa in Vile Parle West, Mumbai is 30 October 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Lotus Kuber Villa?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Lotus Kuber Villa's builder has filed on MahaRERA, the official one, is 30 October 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Lotus Kuber Villa?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Lotus Kuber Villa in Vile Parle West, Mumbai is P51800054808.

Is Lotus Kuber Villa registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lotus Kuber Villa is registered as P51800054808 and its status is "Registered and active".

What is the current construction status of Lotus Kuber Villa? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Lotus Kuber Villa's status on MahaRERA is "Registered and active". As filed by the builder, slab work on KUBER VILLA is 100% done and internal work 100%. The latest construction certificate the builder filed there is dated 28 May 2024. GharKundli's full report compares construction progress with the deadline.

Does Lotus Kuber Villa have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Lotus Kuber Villa safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Lotus Kuber Villa is registered on MahaRERA as P51800054808, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Lotus Kuber Villa?

Lotus Kuber Villa is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Lotus Kuber Villa?

For a flat in Lotus Kuber Villa (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Lotus Kuber Villa received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Lotus Kuber Villa is still under construction, with 30 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Lotus Kuber Villa uploaded its title report on MahaRERA?

Yes. According to GharKundli's check of MahaRERA records (updated October 2026), an advocate's title report for Lotus Kuber Villa is uploaded on MahaRERA. It says who owns the land and whether there's any loan, case or claim on it. GharKundli's full report reads it and lists anything that needs a written answer from the builder.

A loan or claim on the land can hold up your flat or your home loan. See what the title report says →

How can I get updates if Lotus Kuber Villa's possession date changes?

The latest dates are on Lotus Kuber Villa's MahaRERA page (P51800054808). GharKundli's Kundli Watch sends a free WhatsApp update on Lotus Kuber Villa every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Lotus Kuber Villa have?

According to GharKundli's check of MahaRERA records (updated October 2026), Lotus Kuber Villa has one building filed: KUBER VILLA with 14 floors and 15 units.

How big is the land of Lotus Kuber Villa?

According to GharKundli's check of MahaRERA records (updated October 2026), Lotus Kuber Villa stands on 702 sq m of land (about 0.2 acres), with 2,589 sq m of sanctioned built-up area.

What are the reviews of Lotus Kuber Villa?

Google Maps has reviews of Lotus Kuber Villa written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Lotus Kuber Villa?

Lotus Kuber Villa by M/s. LOTUS VENTURES LLP is in Vile Parle West, Mumbai, pincode 400056 (near Juhu, Vile Parle East, Santacruz West), Maharashtra, and is registered on MahaRERA as P51800054808, per GharKundli's check of MahaRERA records. Its land is filed as 305. GharKundli lists all 88 MahaRERA projects in Vile Parle West (400056).

How many flats are in Lotus Kuber Villa, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Lotus Kuber Villa has 15 homes in 1 tower registered on MahaRERA, and 47% of them are sold or booked.

When was Lotus Kuber Villa registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lotus Kuber Villa was registered on MahaRERA on 12 February 2024. A title report on the land is on file there.

Does Lotus Kuber Villa have any legal issues or court cases?

No court cases are listed for Lotus Kuber Villa on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Lotus Kuber Villa?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s. LOTUS VENTURES LLP.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Vile Parle West (400056)

All 88 projects in Vile Parle West (400056) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.