by MAMTORA FOUNDATION · Malad West, Mumbai 400064Also near Malad East, Motilal Nagar

What’s in the report? →

Possession date of Shree Hari Krupa (MahaRERA P51800055568): 30 September 2026, moved from 31 December 2025 (9 months later), and it has already passed. It has 27 homes (2 BHK and 3 BHK, 514–801 sq ft carpet), 6% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800055568. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800055568, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (September 2026) has passed.

What do you want to know about Shree Hari Krupa?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Shree Hari Krupa has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 30 September 2026

    Extended at the builder's request (MahaRERA application EA27022620032)

    Reason the builder gave MahaRERA:
    “THE CONSTRUCTION OF THE PROJECT UNDER REFERENCE IS DELAY AS THE VARIOUS APPROVALS FROM CONCERNED DEPARTMENT LIKE FIRE NOC, LIFT CERTIFICATES TOOK LONGER TIME THEN ESTIMATED. ALLOUR CIVIL WORK WAS COMPLETED UPTO THE PROJECT COMPLETION DATE i…” Read the full reason“THE CONSTRUCTION OF THE PROJECT UNDER REFERENCE IS DELAY AS THE VARIOUS APPROVALS FROM CONCERNED DEPARTMENT LIKE FIRE NOC, LIFT CERTIFICATES TOOK LONGER TIME THEN ESTIMATED. ALLOUR CIVIL WORK WAS COMPLETED UPTO THE PROJECT COMPLETION DATE i.e. 31-12-2025 BUT FURTHER APPROVALS FROM THE CONCERNED DEPARTMENTS TOOK LONGER TIME THAN ESTIMATED. WE ARE IN THE PROCESS OF OBTAINING VARIOUS APPROVALS AND THE OCCUPATION CERTIFICATE FROM THE CONCERNED DEPARTMENT AND SINCE THE OCCUPATION CERTIFICATE HAS NOT BEEN OBTAINED UPTO THE PROJECT COMPLETION DATE OF 31-12-2025 WE ARE SEEKING FOR EXTENTION OF THE…”

Source: Shree Hari Krupa’s extension records on MahaRERA (P51800055568), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shree Hari Krupa

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800055568
Status
Lapsed (registration period ended)
Builder
MAMTORA FOUNDATION
Location
Malad West, Mumbai · 400064
Project type
Residential / Group Housing
Registered on
2 Apr 2024
Completion date at registration
December 2025
Latest completion date
September 2026
Delay so far
9 months
Homes
27
Sold or booked
6%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Shree Hari Krupa, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHREE HARI KRUPA BUILDING NO 2100%100%100%80%

Commencement certificate (CC), as filed on MahaRERA

  • SHREE HARI KRUPA BUILDING NO 2: covers C.C. is granted for the work upto top of Stilt slab level only

Latest CC order on MahaRERA: dated 11/04/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shree Hari Krupa every 1–2 months.

Shree Hari Krupa: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK514 – 63319
3 BHK548 – 8018
  • Buildings: SHREE HARI KRUPA BUILDING NO 2 (4 floors, 27 units)
  • Car parking: 23 covered
  • Land: 1,850 sq m (about 0.5 acres) · sanctioned built-up 702 sq m
  • Land, as filed: C.T.S. No. 664A, 664A/1 to 9, 664B and 666
  • Map: Get directions

The builder’s record and reviews

Mamtora Enterprise (a group of 7 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 5 finished, 2 within the promised date and 3 needed more time (typically 12 months); 3 still being built, 2 past the promised date (typically 5 months late); 3 lapsed. 2 complaints on MahaRERA across 2 projects.

Read Google reviews of Shree Hari Krupa →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shree Hari Krupa: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shree Hari Krupa

What is the possession date of Shree Hari Krupa?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shree Hari Krupa in Malad West, Mumbai is 30 September 2026 — 9 months later than 31 December 2025, the date given at registration. That date has already passed.

The date has already moved 9 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Shree Hari Krupa?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shree Hari Krupa's builder has filed on MahaRERA, the official one, is 30 September 2026, already 9 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shree Hari Krupa extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Hari Krupa's builder applied to MahaRERA to extend the completion date once: to 30 September 2026, giving the reason "THE CONSTRUCTION OF THE PROJECT UNDER REFERENCE IS DELAY AS THE VARIOUS APPROVALS FROM CONCERNED DEPARTMENT LIKE FIRE NOC, LIFT CERTIFICATES TOOK LONGER TIME THEN ESTIMATED. ALLOUR CIVIL WORK WAS COMPLETED UPTO THE PROJECT COMPLETION DATE i.e. 31-12-2025 BUT FURTHER APPROVALS FROM THE CONCERNED DEPARTMENTS TOOK LONGER TIME THAN ESTIMATED. WE ARE IN THE PROCESS OF OBTAINING VARIOUS APPROVALS AND THE OCCUPATION CERTIFICATE FROM THE CONCERNED DEPARTMENT AND SINCE THE OCCUPATION CERTIFICATE HAS NOT BEEN OBTAINED UPTO THE PROJECT COMPLETION DATE OF 31-12-2025 WE ARE SEEKING FOR EXTENTION OF THE…".

What is the RERA number of Shree Hari Krupa?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shree Hari Krupa in Malad West, Mumbai is P51800055568.

Is Shree Hari Krupa registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Hari Krupa is registered as P51800055568 and its status is "Lapsed (registration period ended)".

What is the current construction status of Shree Hari Krupa? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Hari Krupa's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHREE HARI KRUPA BUILDING NO 2 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Shree Hari Krupa have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shree Hari Krupa safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Hari Krupa is registered on MahaRERA as P51800055568, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shree Hari Krupa?

Shree Hari Krupa isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Shree Hari Krupa are 514 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shree Hari Krupa?

For a flat in Shree Hari Krupa (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Shree Hari Krupa received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shree Hari Krupa isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Shree Hari Krupa?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Hari Krupa's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Is Shree Hari Krupa a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Hari Krupa is a redevelopment: 11 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Shree Hari Krupa uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shree Hari Krupa was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shree Hari Krupa's possession date changes?

The latest dates are on Shree Hari Krupa's MahaRERA page (P51800055568). GharKundli's Kundli Watch sends a free WhatsApp update on Shree Hari Krupa every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shree Hari Krupa have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Hari Krupa has one building filed: SHREE HARI KRUPA BUILDING NO 2 with 4 floors and 27 units.

What are the flat sizes (carpet area) in Shree Hari Krupa?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shree Hari Krupa: 2 BHK: 514 to 633 sq ft carpet (19 homes); 3 BHK: 548 to 801 sq ft carpet (8 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Shree Hari Krupa have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 23 covered car parking spaces for Shree Hari Krupa.

How big is the land of Shree Hari Krupa?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Hari Krupa stands on 1,850 sq m of land (about 0.5 acres), with 702 sq m of sanctioned built-up area.

What is the track record of Shree Hari Krupa's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Mamtora Enterprise (a group of 7 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 5 finished, 2 within the promised date and 3 needed more time (typically 12 months); 3 still being built, 2 past the promised date (typically 5 months late); 3 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shree Hari Krupa?

Google Maps has reviews of Shree Hari Krupa written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shree Hari Krupa?

Shree Hari Krupa by MAMTORA FOUNDATION is in Malad West, Mumbai, pincode 400064 (near Malad East, Motilal Nagar), Maharashtra, and is registered on MahaRERA as P51800055568, per GharKundli's check of MahaRERA records. Its land is filed as C.T.S. No. 664A, 664A/1 to 9, 664B and 666. GharKundli lists all 301 MahaRERA projects in Malad West (400064).

How many flats are in Shree Hari Krupa, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Hari Krupa has 27 homes in 1 tower registered on MahaRERA, and 6% of them are sold or booked.

When was Shree Hari Krupa registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Hari Krupa was registered on MahaRERA on 2 April 2024. GharKundli did not find a title report on the land on file there.

Does Shree Hari Krupa have any legal issues or court cases?

No court cases are listed for Shree Hari Krupa on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Shree Hari Krupa?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MAMTORA FOUNDATION, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Malad West (400064)

All 301 projects in Malad West (400064) →

Other projects by MAMTORA FOUNDATION

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.