Ashapura Meghmala Crysta

by OM ASHAPURA INFRA · Malad West, Mumbai 400064Also near Borivali West, Vile Parle East, Malad EastRegistered on MahaRERA as “MEGHMALA CRYSTA”

What’s in the report? →

Possession date of Ashapura Meghmala Crysta (MahaRERA P51800056100): 30 April 2029, moved from 31 March 2026 (33 months later). It has 70 homes (1 BHK, 2 BHK and 3 BHK, 445–959 sq ft carpet), 35% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800056100, and currently active. Its completion date has moved from March 2026 to April 2029: 33 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800056100, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Ashapura Meghmala Crysta?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Ashapura Meghmala Crysta has moved

  1. 31 March 2026

    Completion date given when the project was registered

  2. 31 December 2028

    Extended at the builder's request (MahaRERA application EXT51800019805)

    Reason the builder gave MahaRERA: “BY MISTAKE ENTERED WRONG DATE WHILE REGISTERING PROJECT”
  3. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Ashapura Meghmala Crysta’s extension records on MahaRERA (P51800056100), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ashapura Meghmala Crysta

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800056100
Status
Registered and active
Builder
OM ASHAPURA INFRA
Location
Malad West, Mumbai · 400064
Project type
Residential / Group Housing
Registered on
10 May 2024
Completion date at registration
March 2026
Latest completion date
April 2029
Delay so far
33 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
70
Sold or booked
35%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Ashapura Meghmala Crysta, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MEGHMALA PHASE -1100%100%100%50%

Commencement certificate (CC), as filed on MahaRERA

  • MEGHMALA PHASE -1: covers 20 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ashapura Meghmala Crysta every 1–2 months.

Ashapura Meghmala Crysta: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK445 – 47138
2 BHK651 – 68017
3 BHK896 – 95915
Shops192 – 6155

The builder’s record and reviews

OM Ashapura Infra (a group of 3 linked companies) has 3 projects on MahaRERA since 2022, this one included. Of the 3 GharKundli has checked: 1 still being built, 1 past the promised date (typically 3 months late); 2 lapsed. No complaints on MahaRERA.

Read Google reviews of Ashapura Meghmala Crysta →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ashapura Meghmala Crysta: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Ashapura Meghmala Crysta

What is the possession date of Ashapura Meghmala Crysta?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ashapura Meghmala Crysta in Malad West, Mumbai is 30 April 2029 — 33 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 33 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Ashapura Meghmala Crysta?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ashapura Meghmala Crysta's builder has filed on MahaRERA, the official one, is 30 April 2029, already 33 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Ashapura Meghmala Crysta extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Meghmala Crysta's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "BY MISTAKE ENTERED WRONG DATE WHILE REGISTERING PROJECT". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Ashapura Meghmala Crysta?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ashapura Meghmala Crysta in Malad West, Mumbai is P51800056100.

Is Ashapura Meghmala Crysta registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Meghmala Crysta is registered as P51800056100 and its status is "Registered and active".

What is the current construction status of Ashapura Meghmala Crysta? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Meghmala Crysta's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MEGHMALA PHASE -1 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Ashapura Meghmala Crysta have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Ashapura Meghmala Crysta safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Meghmala Crysta is registered on MahaRERA as P51800056100, its completion date has moved 33 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Ashapura Meghmala Crysta?

Ashapura Meghmala Crysta is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Ashapura Meghmala Crysta are 445 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Ashapura Meghmala Crysta?

For a flat in Ashapura Meghmala Crysta (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Ashapura Meghmala Crysta received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Meghmala Crysta is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Ashapura Meghmala Crysta a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Meghmala Crysta is a redevelopment: 15 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Ashapura Meghmala Crysta uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ashapura Meghmala Crysta was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Ashapura Meghmala Crysta's possession date changes?

The latest dates are on Ashapura Meghmala Crysta's MahaRERA page (P51800056100). GharKundli's Kundli Watch sends a free WhatsApp update on Ashapura Meghmala Crysta every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ashapura Meghmala Crysta have?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Meghmala Crysta has one building filed: MEGHMALA PHASE -1 with 21 floors and 75 units.

What are the flat sizes (carpet area) in Ashapura Meghmala Crysta?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Ashapura Meghmala Crysta: 1 BHK: 445 to 471 sq ft carpet (38 homes); 2 BHK: 651 to 680 sq ft carpet (17 homes); 3 BHK: 896 to 959 sq ft carpet (15 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Ashapura Meghmala Crysta?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Meghmala Crysta stands on 819 sq m of land (about 0.2 acres), with 4,265 sq m of sanctioned built-up area.

What is the track record of Ashapura Meghmala Crysta's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), OM Ashapura Infra (a group of 3 linked companies) has 3 projects on MahaRERA since 2022, this one included. Of the 3 GharKundli has checked: 1 still being built, 1 past the promised date (typically 3 months late); 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Ashapura Meghmala Crysta?

Google Maps has reviews of Ashapura Meghmala Crysta written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Ashapura Meghmala Crysta?

Ashapura Meghmala Crysta by OM ASHAPURA INFRA is in Malad West, Mumbai, pincode 400064 (near Borivali West, Vile Parle East, Malad East), Maharashtra, and is registered on MahaRERA as P51800056100, per GharKundli's check of MahaRERA records. Its land is filed as 217 A, 217 A/1. GharKundli lists all 301 MahaRERA projects in Malad West (400064).

How many flats are in Ashapura Meghmala Crysta, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Meghmala Crysta has 70 homes in 1 tower registered on MahaRERA, and 35% of them are sold or booked.

When was Ashapura Meghmala Crysta registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ashapura Meghmala Crysta was registered on MahaRERA on 10 May 2024. GharKundli did not find a title report on the land on file there.

Does Ashapura Meghmala Crysta have any legal issues or court cases?

No court cases are listed for Ashapura Meghmala Crysta on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Ashapura Meghmala Crysta?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is OM ASHAPURA INFRA.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in Malad West (400064)

All 301 projects in Malad West (400064) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.