Simandhar
by MANSUKH POPATLAL SHAH · Bhuleshwar, Chira Bazar, Mumbai 400002Also near Girgaon, Charni Road, Neral
What’s in the report? →Possession date of Simandhar (MahaRERA P51900013585): 31 March 2024, moved from 31 December 2017 (75 months later), and it has already passed. It has 18 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900013585. Status: Lapsed (registration period ended). MahaRERA has issued a regulatory order on this project.
Source: MahaRERA website — records for P51900013585, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (March 2024) has passed.
What do you want to know about Simandhar?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Simandhar has moved
31 December 2017
Completion date given when the project was registered
31 December 2018
Extended at the builder's request (MahaRERA application EXT51900000773)
Reason the builder gave MahaRERA: “The project has got delayed because flat interior works are pending which we were expecting to complete by 31st December, 2017. As per the current scenario of working we expect that the project would get complete by 31st October, 2018.”
30 September 2021
Extended at the builder's request (MahaRERA application EXT51900006264)
Reason the builder gave MahaRERA:
“The delay of the project was due to no permission from BMC for construction. We applied to rise of floors from 18th to 22nd and moreover new DCR 2034 rules were also going to come in effect from BMC. Now due to Corona Virus and Lockdown our…” Read the full reason
“The delay of the project was due to no permission from BMC for construction. We applied to rise of floors from 18th to 22nd and moreover new DCR 2034 rules were also going to come in effect from BMC. Now due to Corona Virus and Lockdown our workers gone to their native place and we are in contact with them and called them to come back soon to complete the project on time. We want extension of this project upto September 2021.”31 March 2024
Extended at the builder's request (MahaRERA application EXT51900016468)
Reason the builder gave MahaRERA: “As as per regulatory order 32 extension has been sanctioned upto 31.3.24.”
Source: Simandhar’s extension records on MahaRERA (P51900013585), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Simandhar
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900013585
- Status
- Lapsed (registration period ended)
- Builder
- MANSUKH POPATLAL SHAH
- Location
- Bhuleshwar, Chira Bazar, Mumbai · 400002
- Project type
- Residential / Group Housing
- Registered on
- 16 Oct 2017
- Completion date at registration
- December 2017
- Latest completion date
- March 2024
- Delay so far
- 75 months
- Homes
- 18
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
Construction progress of Simandhar, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SIMANDHAR | 100% | 100% | 97% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Simandhar every 1–2 months.
Simandhar: buildings, flats and land, as filed on MahaRERA
- Buildings: SIMANDHAR (23 floors)
- Land: 318 sq m (about 0.1 acres) · sanctioned built-up 1,168 sq m
- Boundaries filed include: JSS ROAD
- Land, as filed: 359-399
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Simandhar →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Simandhar: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Simandhar
What is the possession date of Simandhar?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Simandhar in Bhuleshwar, Chira Bazar, Mumbai is 31 March 2024 — 75 months later than 31 December 2017, the date given at registration. That date has already passed.
The date has already moved 75 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Simandhar?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Simandhar's builder has filed on MahaRERA, the official one, is 31 March 2024, already 75 months later than the 31 December 2017 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Simandhar extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Simandhar's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2018, giving the reason "The project has got delayed because flat interior works are pending which we were expecting to complete by 31st December, 2017. As per the current scenario of working we expect that the project would get complete by 31st October, 2018."; to 30 September 2021, giving the reason "The delay of the project was due to no permission from BMC for construction. We applied to rise of floors from 18th to 22nd and moreover new DCR 2034 rules were also going to come in effect from BMC. Now due to Corona Virus and Lockdown our workers gone to their native place and we are in contact with them and called them to come back soon to complete the project on time. We want extension of this project upto September 2021."; to 31 March 2024, giving the reason "As as per regulatory order 32 extension has been sanctioned upto 31.3.24.".
What is the RERA number of Simandhar?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Simandhar in Bhuleshwar, Chira Bazar, Mumbai is P51900013585.
Is Simandhar registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Simandhar is registered as P51900013585 and its status is "Lapsed (registration period ended)".
What is the current construction status of Simandhar? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Simandhar's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SIMANDHAR is 100% done and internal work 97%. GharKundli's full report compares construction progress with the deadline.
Does Simandhar have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Simandhar safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Simandhar is registered on MahaRERA as P51900013585, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 75 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Simandhar?
Simandhar isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Simandhar?
For a flat in Simandhar (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Simandhar received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Simandhar isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 March 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Simandhar?
According to GharKundli's check of MahaRERA records (updated October 2026), Simandhar's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 March 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Simandhar uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Simandhar was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Simandhar's possession date changes?
The latest dates are on Simandhar's MahaRERA page (P51900013585). GharKundli's Kundli Watch sends a free WhatsApp update on Simandhar every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Simandhar have?
According to GharKundli's check of MahaRERA records (updated October 2026), Simandhar has one building filed: SIMANDHAR with 23 floors.
How big is the land of Simandhar?
According to GharKundli's check of MahaRERA records (updated October 2026), Simandhar stands on 318 sq m of land (about 0.1 acres), with 1,168 sq m of sanctioned built-up area.
What are the reviews of Simandhar?
Google Maps has reviews of Simandhar written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Simandhar?
Simandhar by MANSUKH POPATLAL SHAH is in Bhuleshwar, Chira Bazar, Mumbai, pincode 400002 (near Girgaon, Charni Road, Neral), Maharashtra, and is registered on MahaRERA as P51900013585, per GharKundli's check of MahaRERA records. Its boundaries filed there include JSS ROAD. Its land is filed as 359-399. GharKundli lists all 32 MahaRERA projects in Kalbadevi (400002).
How many flats are in Simandhar?
According to GharKundli's check of MahaRERA records (updated October 2026), Simandhar has 18 homes in 1 tower registered on MahaRERA.
When was Simandhar registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Simandhar was registered on MahaRERA on 16 October 2017. GharKundli did not find a title report on the land on file there.
Does Simandhar have any legal issues or court cases?
No court cases are listed for Simandhar on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Simandhar?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MANSUKH POPATLAL SHAH.
Check it yourself on MahaRERA
- How to check the possession date of Simandhar
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Ward ABCD
- Burj Ashrafi
- Aaditya Luxuria
- Shakuntala Sadan
- Al Mehdi Heights
- Meadows
- Mehta Sunshine Heights B Wing
- Shapoorji Pallonji The Odyssey 1
- Onyx
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.