Runwal Nexus
by Asmira Ventures Private Limited (Transcon) · Malad, MumbaiAlso near Borivali West, Borivali East, Mandapeshwar
Possession date of Runwal Nexus: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800055982, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Runwal Nexus?
How the possession date of Runwal Nexus has moved
30 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Runwal Nexus’s extension records on MahaRERA (P51800055982), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Runwal Nexus
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints and 36 court cases, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800055982
- Status
- Registered and active
- Builder
- Asmira Ventures Private Limited
- Location
- Malad, Mumbai · 400064
- Project type
- Commercial
- Registered on
- 2 May 2024
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 44%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 36
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Runwal Nexus, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| AURIS NEXUS TOWER 4 COMMERCIAL -SALE BLDG NO1 WING D COMMERCIAL | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- AURIS NEXUS TOWER 4 COMMERCIAL -SALE BLDG NO1 WING D COMMERCIAL: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Runwal Nexus every month.
Runwal Nexus: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 350 – 699 | 17 |
| Shops | 362 – 711 | 8 |
- Buildings: AURIS NEXUS TOWER 4 COMMERCIAL -SALE BLDG NO1 WING D COMMERCIAL (5 floors, 25 units)
- Car parking: 32 covered
- Land: 344 sq m (about 0.1 acres) · sanctioned built-up 1,751 sq m
- Boundaries filed include: LINK ROAD
The builder’s record and reviews
Transcon-sheth Creators (a group of 6 linked companies) has 17 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 3 finished, all within the promised date; 10 still being built, 1 past the promised date (typically 18 months late); 3 lapsed. 144 complaints on MahaRERA across 14 projects.
Read Google reviews of Runwal Nexus →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Runwal Nexus: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Runwal Nexus
What is the possession date of Runwal Nexus?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Runwal Nexus in Malad, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Runwal Nexus?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Runwal Nexus's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Runwal Nexus?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Runwal Nexus in Malad, Mumbai is P51800055982.
Is Runwal Nexus registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Nexus is registered as P51800055982 and its status is "Registered and active".
What is the construction status of Runwal Nexus?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Nexus's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AURIS NEXUS TOWER 4 COMMERCIAL -SALE BLDG NO1 WING D COMMERCIAL is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Runwal Nexus have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Runwal Nexus safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Nexus is registered on MahaRERA as P51800055982, its completion date has not been moved by the builder and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Runwal Nexus's possession date changes?
The latest dates are on Runwal Nexus's MahaRERA page (P51800055982). GharKundli's Kundli Watch sends a free WhatsApp update on Runwal Nexus every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Runwal Nexus have?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Nexus has one building filed: AURIS NEXUS TOWER 4 COMMERCIAL -SALE BLDG NO1 WING D COMMERCIAL with 5 floors and 25 units.
How much parking does Runwal Nexus have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 32 covered car parking spaces for Runwal Nexus.
How big is the land of Runwal Nexus?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Nexus stands on 344 sq m of land (about 0.1 acres), with 1,751 sq m of sanctioned built-up area.
What is the track record of Runwal Nexus's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Transcon-sheth Creators (a group of 6 linked companies) has 17 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 3 finished, all within the promised date; 10 still being built, 1 past the promised date (typically 18 months late); 3 lapsed. 144 complaints on MahaRERA across 14 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Runwal Nexus?
Google Maps has reviews of Runwal Nexus written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Runwal Nexus?
Runwal Nexus by Asmira Ventures Private Limited (Transcon) is in Malad, Mumbai (pincode 400064), near Borivali West, Borivali East, Mandapeshwar, Maharashtra, and is registered on MahaRERA as P51800055982, per GharKundli's check of MahaRERA records. Its boundaries filed there include LINK ROAD.
How many homes are in Runwal Nexus?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Nexus has 0 homes in 1 tower registered on MahaRERA, and 44% of them are sold or booked.
When was Runwal Nexus registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal Nexus was registered on MahaRERA on 2 May 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on Runwal Nexus?
36 court cases are listed for Runwal Nexus on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Runwal Nexus?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Asmira Ventures Private Limited, the company Transcon files this project under, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Runwal Nexus
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400064
- AABIEL AVENUE
- Lotus Sky Garden
- Bhagat Grandeur
- AVIRAHI ELEGANCE
- Rite Amor
- RASHMI ICON
- MARU MANSION
- Florence Residency
Other projects by Asmira Ventures Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.