259 PARK CREST
by SHREE KRISHNA HOMES PVT LTD · Khar West, MumbaiAlso near Santacruz West, Bandra West, Bandra East
Possession date of 259 PARK CREST: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800056195, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about 259 PARK CREST?
How the possession date of 259 PARK CREST has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: 259 PARK CREST’s extension records on MahaRERA (P51800056195), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on 259 PARK CREST
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800056195
- Status
- Registered and active
- Builder
- SHREE KRISHNA HOMES PVT LTD
- Location
- Khar West, Mumbai · 400052
- Project type
- Residential / Group Housing
- Registered on
- 16 May 2024
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 19
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 6
Construction progress of 259 PARK CREST, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PARK CREST | 100% | 100% | 75% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on 259 PARK CREST every month.
259 PARK CREST: buildings, flats and land, as filed on MahaRERA
- Buildings: PARK CREST (9 floors)
- Land: 651 sq m (about 0.2 acres) · sanctioned built-up 869 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Shree Krishna Properties (a group of 8 linked companies) has 34 projects on MahaRERA since 2017, this one included. Of the 34 GharKundli has checked: 23 finished, 21 within the promised date and 2 needed more time (typically 17 months); 10 still being built, none past the promised date yet; 1 lapsed. 2 complaints on MahaRERA across 2 projects.
Read Google reviews of 259 PARK CREST →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
259 PARK CREST: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about 259 PARK CREST
What is the possession date of 259 PARK CREST?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for 259 PARK CREST in Khar West, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for 259 PARK CREST?
Builders and listing sites often quote an earlier "target" date for handover. The completion date 259 PARK CREST's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of 259 PARK CREST?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of 259 PARK CREST in Khar West, Mumbai is P51800056195.
Is 259 PARK CREST registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), 259 PARK CREST is registered as P51800056195 and its status is "Registered and active".
What is the construction status of 259 PARK CREST?
According to GharKundli's check of MahaRERA records (updated October 2026), 259 PARK CREST's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PARK CREST is 100% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.
Does 259 PARK CREST have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is 259 PARK CREST safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), 259 PARK CREST is registered on MahaRERA as P51800056195, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if 259 PARK CREST's possession date changes?
The latest dates are on 259 PARK CREST's MahaRERA page (P51800056195). GharKundli's Kundli Watch sends a free WhatsApp update on 259 PARK CREST every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does 259 PARK CREST have?
According to GharKundli's check of MahaRERA records (updated October 2026), 259 PARK CREST has one building filed: PARK CREST with 9 floors.
How big is the land of 259 PARK CREST?
According to GharKundli's check of MahaRERA records (updated October 2026), 259 PARK CREST stands on 651 sq m of land (about 0.2 acres), with 869 sq m of sanctioned built-up area.
What is the track record of 259 PARK CREST's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Krishna Properties (a group of 8 linked companies) has 34 projects on MahaRERA since 2017, this one included. Of the 34 GharKundli has checked: 23 finished, 21 within the promised date and 2 needed more time (typically 17 months); 10 still being built, none past the promised date yet; 1 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of 259 PARK CREST?
Google Maps has reviews of 259 PARK CREST written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is 259 PARK CREST?
259 PARK CREST by SHREE KRISHNA HOMES PVT LTD is in Khar West, Mumbai (pincode 400052), near Santacruz West, Bandra West, Bandra East, Maharashtra, and is registered on MahaRERA as P51800056195, per GharKundli's check of MahaRERA records.
How many homes are in 259 PARK CREST?
According to GharKundli's check of MahaRERA records (updated October 2026), 259 PARK CREST has 19 homes in 1 tower registered on MahaRERA.
When was 259 PARK CREST registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), 259 PARK CREST was registered on MahaRERA on 16 May 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on 259 PARK CREST?
No court cases are listed for 259 PARK CREST on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of 259 PARK CREST?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE KRISHNA HOMES PVT LTD, which has 6 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of 259 PARK CREST
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400052
- SM ROYALE
- BENCHMARK PLAZA
- ATLANTIS TOWER
- Yogi Sea
- EVERSHINE BLISS
- Rustomjee Crescent
- WORQ BY S RAHEJA
- DLH One
Other projects by SHREE KRISHNA HOMES PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.