Adityaraj Majestic
by ADITYARAJ HOUSING LLP · Chembur East, Mumbai 400071
What’s in the report? →Possession date of Adityaraj Majestic (MahaRERA P51800055402): 30 April 2028. It has 164 homes (1 BHK and 2 BHK, 422–681 sq ft carpet), 70% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800055402, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51800055402, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Adityaraj Majestic?
1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Adityaraj Majestic has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Adityaraj Majestic’s extension records on MahaRERA (P51800055402), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Adityaraj Majestic
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800055402
- Status
- Registered and active
- Builder
- ADITYARAJ HOUSING LLP
- Location
- Chembur East, Mumbai · 400071
- Project type
- Others
- Registered on
- 22 Mar 2024
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 164
- Sold or booked
- 70%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of Adityaraj Majestic, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ADITYARAJ MAJESTIC-Wing A | 100% | 94% | 24% | 0% |
| ADITYARAJ MAJESTIC-Wing B | 100% | 94% | 24% | 0% |
| ADITYARAJ MAJESTIC-Wing C | 100% | 94% | 24% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- ADITYARAJ MAJESTIC-Wing A: covers 5 floors
- ADITYARAJ MAJESTIC-Wing B: covers 5 floors
- ADITYARAJ MAJESTIC-Wing C: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Adityaraj Majestic every 1–2 months.
Adityaraj Majestic: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 422 – 510 | 134 |
| 2 BHK | 560 – 681 | 30 |
| Shops | 200 – 476 | 12 |
- Land: 1,730 sq m (about 0.4 acres) · sanctioned built-up 10,261 sq m
- Land, as filed: CITY SURVEY No. 826
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Adityaraj Majestic →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Adityaraj Majestic: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Adityaraj Majestic
What is the possession date of Adityaraj Majestic?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Adityaraj Majestic in Chembur East, Mumbai is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Adityaraj Majestic?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Adityaraj Majestic's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Adityaraj Majestic?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Adityaraj Majestic in Chembur East, Mumbai is P51800055402.
Is Adityaraj Majestic registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Adityaraj Majestic is registered as P51800055402 and its status is "Registered and active".
What is the current construction status of Adityaraj Majestic? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Adityaraj Majestic's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 94% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Adityaraj Majestic have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Adityaraj Majestic safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Adityaraj Majestic is registered on MahaRERA as P51800055402, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Adityaraj Majestic?
Adityaraj Majestic is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Adityaraj Majestic are 422 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Adityaraj Majestic?
For a flat in Adityaraj Majestic (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Adityaraj Majestic received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Adityaraj Majestic is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Adityaraj Majestic uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Adityaraj Majestic was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Adityaraj Majestic's possession date changes?
The latest dates are on Adityaraj Majestic's MahaRERA page (P51800055402). GharKundli's Kundli Watch sends a free WhatsApp update on Adityaraj Majestic every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
What are the flat sizes (carpet area) in Adityaraj Majestic?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Adityaraj Majestic: 1 BHK: 422 to 510 sq ft carpet (134 homes); 2 BHK: 560 to 681 sq ft carpet (30 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Adityaraj Majestic?
According to GharKundli's check of MahaRERA records (updated October 2026), Adityaraj Majestic stands on 1,730 sq m of land (about 0.4 acres), with 10,261 sq m of sanctioned built-up area.
What are the reviews of Adityaraj Majestic?
Google Maps has reviews of Adityaraj Majestic written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Adityaraj Majestic?
Adityaraj Majestic by ADITYARAJ HOUSING LLP is in Chembur East, Mumbai, pincode 400071, Maharashtra, and is registered on MahaRERA as P51800055402, per GharKundli's check of MahaRERA records. Its land is filed as CITY SURVEY No. 826. GharKundli lists all 318 MahaRERA projects in Chembur (400071).
How many flats are in Adityaraj Majestic, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Adityaraj Majestic has 164 homes in 3 towers registered on MahaRERA, and 70% of them are sold or booked.
When was Adityaraj Majestic registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Adityaraj Majestic was registered on MahaRERA on 22 March 2024. GharKundli did not find a title report on the land on file there.
Does Adityaraj Majestic have any legal issues or court cases?
1 court case is listed for Adityaraj Majestic on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Adityaraj Majestic?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ADITYARAJ HOUSING LLP.
Check it yourself on MahaRERA
- How to check the possession date of Adityaraj Majestic
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Chembur (400071)
- 71 Pardis
- Tulsi Chamber Phase II
- Queens Park
- Sampoorna
- Shree Saraswati CHS LTD Plot 8B
- Icons 71
- Viera Golf Greens
- Arham Mourya
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.