27 Pallazzo
by Siddharth Pankaj Chothani · Wadhavali-M/W, Mumbai 400071Also near Chembur, Kurla, Bandra East
What’s in the report? →Possession date of 27 Pallazzo (MahaRERA P51800055642): 30 April 2027, moved from 31 December 2025 (12 months later). It has 8 homes (3 BHK, 1199 sq ft carpet), 63% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800055642, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800055642, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about 27 Pallazzo?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of 27 Pallazzo has moved
31 December 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA10102518079)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: 27 Pallazzo’s extension records on MahaRERA (P51800055642), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on 27 Pallazzo
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800055642
- Status
- Registered and active
- Builder
- Siddharth Pankaj Chothani
- Location
- Wadhavali-M/W, Mumbai · 400071
- Project type
- Residential / Group Housing
- Registered on
- 5 Apr 2024
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 8
- Sold or booked
- 63%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of 27 Pallazzo, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| 27 Pallazzo | 100% | 70% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- 27 Pallazzo: covers 14 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on 27 Pallazzo every 1–2 months.
27 Pallazzo: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 1,199 | 8 |
- Buildings: 27 Pallazzo (14 floors, 8 units)
- Land: 528 sq m (about 0.1 acres) · sanctioned built-up 1,039 sq m
- Land, as filed: 160
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of 27 Pallazzo →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
27 Pallazzo: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about 27 Pallazzo
What is the possession date of 27 Pallazzo?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for 27 Pallazzo in Wadhavali-M/W, Mumbai is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for 27 Pallazzo?
Builders and listing sites often quote an earlier "target" date for handover. The completion date 27 Pallazzo's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of 27 Pallazzo extended?
According to GharKundli's check of MahaRERA records (updated October 2026), 27 Pallazzo's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of 27 Pallazzo?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of 27 Pallazzo in Wadhavali-M/W, Mumbai is P51800055642.
Is 27 Pallazzo registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), 27 Pallazzo is registered as P51800055642 and its status is "Registered and active".
What is the current construction status of 27 Pallazzo? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), 27 Pallazzo's status on MahaRERA is "Registered and active". As filed by the builder, slab work on 27 Pallazzo is 70% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does 27 Pallazzo have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is 27 Pallazzo safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), 27 Pallazzo is registered on MahaRERA as P51800055642, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in 27 Pallazzo?
27 Pallazzo is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in 27 Pallazzo start at 1199 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in 27 Pallazzo?
For a flat in 27 Pallazzo (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has 27 Pallazzo received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), 27 Pallazzo is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is 27 Pallazzo a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), 27 Pallazzo's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.
Has 27 Pallazzo uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for 27 Pallazzo was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if 27 Pallazzo's possession date changes?
The latest dates are on 27 Pallazzo's MahaRERA page (P51800055642). GharKundli's Kundli Watch sends a free WhatsApp update on 27 Pallazzo every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does 27 Pallazzo have?
According to GharKundli's check of MahaRERA records (updated October 2026), 27 Pallazzo has one building filed: 27 Pallazzo with 14 floors and 8 units.
What are the flat sizes (carpet area) in 27 Pallazzo?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for 27 Pallazzo: 3 BHK: 1199 sq ft carpet (8 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of 27 Pallazzo?
According to GharKundli's check of MahaRERA records (updated October 2026), 27 Pallazzo stands on 528 sq m of land (about 0.1 acres), with 1,039 sq m of sanctioned built-up area.
What are the reviews of 27 Pallazzo?
Google Maps has reviews of 27 Pallazzo written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of 27 Pallazzo?
27 Pallazzo by Siddharth Pankaj Chothani is in Wadhavali-M/W, Mumbai, pincode 400071 (near Chembur, Kurla, Bandra East), Maharashtra, and is registered on MahaRERA as P51800055642, per GharKundli's check of MahaRERA records. Its land is filed as 160. GharKundli lists all 318 MahaRERA projects in Chembur (400071).
How many flats are in 27 Pallazzo, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), 27 Pallazzo has 8 homes in 1 tower registered on MahaRERA, and 63% of them are sold or booked.
When was 27 Pallazzo registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), 27 Pallazzo was registered on MahaRERA on 5 April 2024. GharKundli did not find a title report on the land on file there.
Does 27 Pallazzo have any legal issues or court cases?
No court cases are listed for 27 Pallazzo on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of 27 Pallazzo?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Siddharth Pankaj Chothani.
Check it yourself on MahaRERA
- How to check the possession date of 27 Pallazzo
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Kurla
- Sudhanshu Heights
- Saptashringi
- Jai Arihant
- Kanakdhara
- Kalyan Kutir Co-operative Housing Society Limited
- Privilon
- Heritage Lakeside
- Malhar Guide
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.