Relcon 103 West
by M/s. RELCON ZP JE CONSTRUCTION LLP · Borivali West, Mumbai 400103Also near Borivali East, Daulat Nagar, EksarRegistered on MahaRERA as “103 West”
What’s in the report? →Possession date of Relcon 103 West (MahaRERA P51800066510): 31 July 2029. It has 114 homes (1 BHK, 2 BHK and 3 BHK, 399–1212 sq ft carpet), 66% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800066510, and currently active. Its completion date is now July 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51800066510, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Relcon 103 West?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Relcon 103 West has moved
31 March 2029
Completion date given when the project was registered
31 July 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Relcon 103 West’s extension records on MahaRERA (P51800066510), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Relcon 103 West
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800066510
- Status
- Registered and active
- Builder
- M/s. RELCON ZP JE CONSTRUCTION LLP
- Location
- Borivali West, Mumbai · 400103
- Project type
- Others
- Registered on
- 11 Jun 2024
- Completion date at registration
- March 2029
- Latest completion date
- July 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 114
- Sold or booked
- 66%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Relcon 103 West, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing A | 100% | 100% | 80% | 50% |
| Wing B | 100% | 100% | 80% | 50% |
Commencement certificate (CC), as filed on MahaRERA
- Wing A: covers 19 floors
- Wing B: covers 20 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Relcon 103 West every 1–2 months.
Relcon 103 West: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 551 – 979 | 62 |
| 3 BHK | 866 – 1,212 | 42 |
| Shops | 199 – 1,036 | 21 |
| Office Space | 259 – 1,658 | 15 |
| 1 BHK | 399 – 462 | 10 |
- Buildings: Wing A (19 floors, 74 units) · Wing B (20 floors, 76 units)
- Car parking: 251 covered
- Land: 3,772 sq m (about 0.9 acres) · sanctioned built-up 11,609 sq m
- Boundaries filed include: 27 Meters Wide Devidas Road
- Land, as filed: 1420/A
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Relcon Infraprojects (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, 1 past the promised date (typically 78 months late). No complaints on MahaRERA.
Read Google reviews of Relcon 103 West →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Relcon 103 West: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Relcon 103 West
What is the possession date of Relcon 103 West?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Relcon 103 West in Borivali West, Mumbai is 31 July 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Relcon 103 West?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Relcon 103 West's builder has filed on MahaRERA, the official one, is 31 July 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Relcon 103 West?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Relcon 103 West in Borivali West, Mumbai is P51800066510.
Is Relcon 103 West registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Relcon 103 West is registered as P51800066510 and its status is "Registered and active".
What is the current construction status of Relcon 103 West? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Relcon 103 West's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Relcon 103 West have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Relcon 103 West safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Relcon 103 West is registered on MahaRERA as P51800066510, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Relcon 103 West?
Relcon 103 West is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Relcon 103 West are 399 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Relcon 103 West?
For a flat in Relcon 103 West (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Relcon 103 West received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Relcon 103 West is still under construction, with 31 July 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Relcon 103 West a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Relcon 103 West is a redevelopment: 86 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Relcon 103 West uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Relcon 103 West was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Relcon 103 West's possession date changes?
The latest dates are on Relcon 103 West's MahaRERA page (P51800066510). GharKundli's Kundli Watch sends a free WhatsApp update on Relcon 103 West every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Relcon 103 West have?
According to GharKundli's check of MahaRERA records (updated October 2026), Relcon 103 West has 2 buildings filed: Wing A with 19 floors and 74 units; Wing B with 20 floors and 76 units.
What are the flat sizes (carpet area) in Relcon 103 West?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Relcon 103 West: 2 BHK: 551 to 979 sq ft carpet (62 homes); 3 BHK: 866 to 1212 sq ft carpet (42 homes); 1 BHK: 399 to 462 sq ft carpet (10 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Relcon 103 West have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 251 covered car parking spaces for Relcon 103 West.
How big is the land of Relcon 103 West?
According to GharKundli's check of MahaRERA records (updated October 2026), Relcon 103 West stands on 3,772 sq m of land (about 0.9 acres), with 11,609 sq m of sanctioned built-up area.
What is the track record of Relcon 103 West's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Relcon Infraprojects (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, 1 past the promised date (typically 78 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Relcon 103 West?
Google Maps has reviews of Relcon 103 West written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Relcon 103 West?
Relcon 103 West by M/s. RELCON ZP JE CONSTRUCTION LLP is in Borivali West, Mumbai, pincode 400103 (near Borivali East, Daulat Nagar, Eksar), Maharashtra, and is registered on MahaRERA as P51800066510, per GharKundli's check of MahaRERA records. Its boundaries filed there include 27 Meters Wide Devidas Road. Its land is filed as 1420/A. GharKundli lists all 93 MahaRERA projects in Borivali West (400103).
How many flats are in Relcon 103 West, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Relcon 103 West has 114 homes in 2 towers registered on MahaRERA, and 66% of them are sold or booked.
When was Relcon 103 West registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Relcon 103 West was registered on MahaRERA on 11 June 2024. GharKundli did not find a title report on the land on file there.
Does Relcon 103 West have any legal issues or court cases?
No court cases are listed for Relcon 103 West on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Relcon 103 West?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s. RELCON ZP JE CONSTRUCTION LLP.
Check it yourself on MahaRERA
- How to check the possession date of Relcon 103 West
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai Suburban →
Other projects in Borivali West (400103)
- Shraddha Skyline
- Sparkle Umadarshan
- Crescent Heights
- Aureate
- Gopal Terrace Co-operative Housing Society LTD
- Shivsagar
- Kaveri Heritage
- Lekh Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.