Possession date of Arkade Pearl 2 (MahaRERA P51800077017): 30 April 2027. It has 32 homes (1 BHK, 2 BHK and 3 BHK, 481–1126 sq ft carpet), 81% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800077017, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800077017, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Arkade Pearl 2?

1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Arkade Pearl 2 has moved

  1. 31 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Arkade Pearl 2’s extension records on MahaRERA (P51800077017), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Arkade Pearl 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800077017
Status
Registered and active
Builder
ARKADE DEVELOPERS LIMITED
Location
Vile Parle East, Mumbai · 400057
Project type
Residential / Group Housing
Registered on
16 Jul 2024
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
32
Sold or booked
81%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
8

Construction progress of Arkade Pearl 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A WING100%100%100%88.89%

Commencement certificate (CC), as filed on MahaRERA

  • A WING: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Arkade Pearl 2 every 1–2 months.

Arkade Pearl 2: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK699 – 72116
1 BHK481 – 5308
3 BHK1,1268
  • Buildings: A WING (9 floors, 32 units)
  • Car parking: 1 covered
  • Land: 4,153 sq m (about 1.0 acres) · sanctioned built-up 2,444 sq m
  • Boundaries filed include: Shahaji Raje Road
  • Land, as filed: 418/D
  • Map: Get directions

The builder’s record and reviews

Arkade Developers (a group of 3 linked companies) has 29 projects on MahaRERA since 2017, this one included. Of the 29 GharKundli has checked: 16 finished, all within the promised date; 10 still being built, none past the promised date yet; 3 lapsed. 26 complaints on MahaRERA across 7 projects.

Read Google reviews of Arkade Pearl 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Arkade Pearl 2: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Arkade Pearl 2

What is the possession date of Arkade Pearl 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Arkade Pearl 2 in Vile Parle East, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Arkade Pearl 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Arkade Pearl 2's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Arkade Pearl 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Arkade Pearl 2 in Vile Parle East, Mumbai is P51800077017.

Is Arkade Pearl 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Arkade Pearl 2 is registered as P51800077017 and its status is "Registered and active".

What is the current construction status of Arkade Pearl 2? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Arkade Pearl 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on A WING is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Arkade Pearl 2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Arkade Pearl 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Arkade Pearl 2 is registered on MahaRERA as P51800077017, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Arkade Pearl 2?

Arkade Pearl 2 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Arkade Pearl 2 are 481 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Arkade Pearl 2?

For a flat in Arkade Pearl 2 (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Arkade Pearl 2 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Arkade Pearl 2 is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Arkade Pearl 2 a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Arkade Pearl 2 is a redevelopment: 16 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Arkade Pearl 2 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Arkade Pearl 2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Arkade Pearl 2 have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: ARKADE PEARL 1 (P51800054195, possession 30 Apr 2027); Arkade Pearl 3 (P51800078295, possession 30 Apr 2027); Arkade Pearl 4 (P51800079922, possession 30 Oct 2027). Check that your agreement names the registration of your own wing.

How can I get updates if Arkade Pearl 2's possession date changes?

The latest dates are on Arkade Pearl 2's MahaRERA page (P51800077017). GharKundli's Kundli Watch sends a free WhatsApp update on Arkade Pearl 2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Arkade Pearl 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Arkade Pearl 2 has one building filed: A WING with 9 floors and 32 units.

What are the flat sizes (carpet area) in Arkade Pearl 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Arkade Pearl 2: 2 BHK: 699 to 721 sq ft carpet (16 homes); 1 BHK: 481 to 530 sq ft carpet (8 homes); 3 BHK: 1126 sq ft carpet (8 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Arkade Pearl 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for Arkade Pearl 2.

How big is the land of Arkade Pearl 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Arkade Pearl 2 stands on 4,153 sq m of land (about 1.0 acres), with 2,444 sq m of sanctioned built-up area.

What is the track record of Arkade Pearl 2's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Arkade Developers (a group of 3 linked companies) has 29 projects on MahaRERA since 2017, this one included. Of the 29 GharKundli has checked: 16 finished, all within the promised date; 10 still being built, none past the promised date yet; 3 lapsed. 26 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Arkade Pearl 2?

Google Maps has reviews of Arkade Pearl 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Arkade Pearl 2?

Arkade Pearl 2 by ARKADE DEVELOPERS LIMITED is in Vile Parle East, Mumbai, pincode 400057 (near Vileeparle East, Vileparle West, Andheri East), Maharashtra, and is registered on MahaRERA as P51800077017, per GharKundli's check of MahaRERA records. Its boundaries filed there include Shahaji Raje Road. Its land is filed as 418/D. GharKundli lists all 251 MahaRERA projects in Vile Parle East (400057).

How many flats are in Arkade Pearl 2, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Arkade Pearl 2 has 32 homes in 1 tower registered on MahaRERA, and 81% of them are sold or booked.

When was Arkade Pearl 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Arkade Pearl 2 was registered on MahaRERA on 16 July 2024. GharKundli did not find a title report on the land on file there.

Does Arkade Pearl 2 have any legal issues or court cases?

1 court case is listed for Arkade Pearl 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Arkade Pearl 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARKADE DEVELOPERS LIMITED, which has 8 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Vile Parle East (400057)

All 251 projects in Vile Parle East (400057) →

Other projects by ARKADE DEVELOPERS LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.