by M/s. Earth Graphics · Chinch Bunder, Mumbai 400009Also near Masjid Bunder, Dongri, Mandvi
What’s in the report? →Possession date of Earth Anand (MahaRERA P51900021985): 31 May 2025, moved from 22 December 2023 (17 months later), and it has already passed. It has 53 homes (2 BHK, 477–671 sq ft carpet), 30% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900021985. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51900021985, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (May 2025) has passed.
What do you want to know about Earth Anand?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Earth Anand has moved
22 December 2023
Completion date given when the project was registered
21 December 2024
Extended at the builder's request (MahaRERA application EXT51900018236)
Reason the builder gave MahaRERA: “We have received approval of additional floor in this project and therefore we require extension for one year to complete the project with receive occupancy certificate and Form 4.”
31 May 2025
Extended at the builder's request (MahaRERA application EXT51900027139)
Reason the builder gave MahaRERA: “WE HAVE APPLIED FOR RERA EXTENSION BECAUSE THE FORMALITY IS PENDING FOR OC APPLICATION AND THEREFORE AS PER RULES AND REGULATION WE APPLIED LESS THAN 1 YEAR. PLEASE APPROVE THE EXTENSTION”
Source: Earth Anand’s extension records on MahaRERA (P51900021985), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Earth Anand
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the May 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900021985
- Status
- Lapsed (registration period ended)
- Builder
- M/s. Earth Graphics
- Location
- Chinch Bunder, Mumbai · 400009
- Project type
- Others
- Registered on
- 25 Aug 2019
- Completion date at registration
- December 2023
- Latest completion date
- May 2025
- Delay so far
- 17 months
- Homes
- 53
- Sold or booked
- 30%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Earth Anand, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Earth Anand | 100% | 100% | 60% | 50% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Earth Anand every 1–2 months.
Earth Anand: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 477 – 671 | 53 |
- Buildings: Earth Anand (19 floors)
- Land: 1,044 sq m (about 0.3 acres) · sanctioned built-up 5,260 sq m · recreational space 85 sq m
- Boundaries filed include: Keshavji Naik Road
- Land, as filed: 28/1721 and 29/1721 of mandvi division
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Earth Graphics (a group of 6 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 5 finished, 2 within the promised date and 3 needed more time (typically 14 months); 3 still being built, 1 past the promised date (typically 23 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Earth Anand →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Earth Anand: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Earth Anand
What is the possession date of Earth Anand?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Earth Anand in Chinch Bunder, Mumbai is 31 May 2025 — 17 months later than 22 December 2023, the date given at registration. That date has already passed.
The date has already moved 17 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Earth Anand?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Earth Anand's builder has filed on MahaRERA, the official one, is 31 May 2025, already 17 months later than the 22 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Earth Anand extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Earth Anand's builder applied to MahaRERA to extend the completion date 2 times: to 21 December 2024, giving the reason "We have received approval of additional floor in this project and therefore we require extension for one year to complete the project with receive occupancy certificate and Form 4."; to 31 May 2025, giving the reason "WE HAVE APPLIED FOR RERA EXTENSION BECAUSE THE FORMALITY IS PENDING FOR OC APPLICATION AND THEREFORE AS PER RULES AND REGULATION WE APPLIED LESS THAN 1 YEAR. PLEASE APPROVE THE EXTENSTION".
What is the RERA number of Earth Anand?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Earth Anand in Chinch Bunder, Mumbai is P51900021985.
Is Earth Anand registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Earth Anand is registered as P51900021985 and its status is "Lapsed (registration period ended)".
What is the current construction status of Earth Anand? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Earth Anand's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Earth Anand is 100% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.
Does Earth Anand have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Earth Anand safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Earth Anand is registered on MahaRERA as P51900021985, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 17 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Earth Anand?
Earth Anand isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Earth Anand are 477 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Earth Anand?
For a flat in Earth Anand (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Earth Anand received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Earth Anand isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 May 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Earth Anand?
According to GharKundli's check of MahaRERA records (updated October 2026), Earth Anand's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 May 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Earth Anand uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Earth Anand was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Earth Anand's possession date changes?
The latest dates are on Earth Anand's MahaRERA page (P51900021985). GharKundli's Kundli Watch sends a free WhatsApp update on Earth Anand every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Earth Anand have?
According to GharKundli's check of MahaRERA records (updated October 2026), Earth Anand has one building filed: Earth Anand with 19 floors.
What are the flat sizes (carpet area) in Earth Anand?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Earth Anand: 2 BHK: 477 to 671 sq ft carpet (53 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Earth Anand?
According to GharKundli's check of MahaRERA records (updated October 2026), Earth Anand stands on 1,044 sq m of land (about 0.3 acres), with 5,260 sq m of sanctioned built-up area and 85 sq m of recreational open space.
What is the track record of Earth Anand's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Earth Graphics (a group of 6 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 5 finished, 2 within the promised date and 3 needed more time (typically 14 months); 3 still being built, 1 past the promised date (typically 23 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Earth Anand?
Google Maps has reviews of Earth Anand written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Earth Anand?
Earth Anand by M/s. Earth Graphics is in Chinch Bunder, Mumbai, pincode 400009 (near Masjid Bunder, Dongri, Mandvi), Maharashtra, and is registered on MahaRERA as P51900021985, per GharKundli's check of MahaRERA records. Its boundaries filed there include Keshavji Naik Road. Its land is filed as 28/1721 and 29/1721 of mandvi division. GharKundli lists all 19 MahaRERA projects in Dongri (400009).
How many flats are in Earth Anand, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Earth Anand has 53 homes in 1 tower registered on MahaRERA, and 30% of them are sold or booked.
When was Earth Anand registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Earth Anand was registered on MahaRERA on 25 August 2019. GharKundli did not find a title report on the land on file there.
Does Earth Anand have any legal issues or court cases?
No court cases are listed for Earth Anand on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Earth Anand?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s. Earth Graphics, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Earth Anand
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Dongri (400009)
- 21, Baugh-E-Hasnain
- Mittal Elegant
- Venus Grandeur
- Mustafa Arcade
- Al Amir Apartment
- Al Mehdi Heights
- Sauda Heights - Phase II
- Inara
Other projects by M/s. Earth Graphics
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.