INARA
by M/S S Square Construction · Dongri Mandvi, Mumbai
Possession date of INARA: 30 April 2027, moved from 25 December 2022 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900032522, and currently active. Its completion date has moved from December 2022 to April 2027: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about INARA?
How the possession date of INARA has moved
25 December 2022
Completion date given when the project was registered
25 December 2023
Extended at the builder's request (MahaRERA application EXT51900013562)
Reason the builder gave MahaRERA: “The required permission from the competent authority Municipal Corporation of Greater Mumbai for the construction of the building is delayed”
31 December 2024
Extended at the builder's request (MahaRERA application EXT51900018780)
Reason the builder gave MahaRERA: “Delay in permission of Competent Authority”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51900027314)
Reason the builder gave MahaRERA: “Due to a delay in the Electric Meter form of the Competent Authority BEST”
31 December 2026
Extended at the builder's request (MahaRERA application EA01032620054)
Reason the builder gave MahaRERA: “Dear Si/Madam, we have completed 95% of all the construction activities. We are in process of completion of balance work and applying for OC.”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: INARA’s extension records on MahaRERA (P51900032522), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on INARA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900032522
- Status
- Registered and active
- Builder
- M/S S Square Construction
- Location
- Dongri Mandvi, Mumbai · 400009
- Project type
- Residential / Group Housing
- Registered on
- 10 Jan 2022
- Completion date at registration
- December 2022
- Latest completion date
- April 2027
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 60
- Sold or booked
- 78%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of INARA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| INARA | 100% | 100% | 95% | 80% |
Commencement certificate (CC), as filed on MahaRERA
- INARA: covers 10 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on INARA every month.
INARA: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 329 – 401 | 40 |
| 2 BHK | 492 – 623 | 20 |
- Buildings: INARA (11 floors, 60 units)
- Car parking: 1 covered
- Land: 1,008 sq m (about 0.2 acres) · sanctioned built-up 2,632 sq m · recreational space 169 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of INARA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
INARA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about INARA
What is the possession date of INARA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for INARA in Dongri Mandvi, Mumbai is 30 April 2027 — 48 months later than 25 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for INARA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date INARA's builder has filed on MahaRERA, the official one, is 30 April 2027, already 48 months later than the 25 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of INARA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), INARA's builder applied to MahaRERA to extend the completion date 4 times: to 25 December 2023, giving the reason "The required permission from the competent authority Municipal Corporation of Greater Mumbai for the construction of the building is delayed"; to 31 December 2024, giving the reason "Delay in permission of Competent Authority"; to 31 December 2025, giving the reason "Due to a delay in the Electric Meter form of the Competent Authority BEST"; to 31 December 2026, giving the reason "Dear Si/Madam, we have completed 95% of all the construction activities. We are in process of completion of balance work and applying for OC.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of INARA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of INARA in Dongri Mandvi, Mumbai is P51900032522.
Is INARA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), INARA is registered as P51900032522 and its status is "Registered and active".
What is the construction status of INARA?
According to GharKundli's check of MahaRERA records (updated October 2026), INARA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on INARA is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does INARA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is INARA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), INARA is registered on MahaRERA as P51900032522, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if INARA's possession date changes?
The latest dates are on INARA's MahaRERA page (P51900032522). GharKundli's Kundli Watch sends a free WhatsApp update on INARA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does INARA have?
According to GharKundli's check of MahaRERA records (updated October 2026), INARA has one building filed: INARA with 11 floors and 60 units.
What are the flat sizes (carpet area) in INARA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for INARA: 1 BHK: 329 to 401 sq ft carpet (40 homes); 2 BHK: 492 to 623 sq ft carpet (20 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does INARA have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for INARA.
How big is the land of INARA?
According to GharKundli's check of MahaRERA records (updated October 2026), INARA stands on 1,008 sq m of land (about 0.2 acres), with 2,632 sq m of sanctioned built-up area and 169 sq m of recreational open space.
Where can I read reviews of INARA?
Google Maps has reviews of INARA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is INARA?
INARA by M/S S Square Construction is in Dongri Mandvi, Mumbai (pincode 400009), Maharashtra, and is registered on MahaRERA as P51900032522, per GharKundli's check of MahaRERA records.
How many homes are in INARA?
According to GharKundli's check of MahaRERA records (updated October 2026), INARA has 60 homes in 1 tower registered on MahaRERA, and 78% of them are sold or booked.
When was INARA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), INARA was registered on MahaRERA on 10 January 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on INARA?
No court cases are listed for INARA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of INARA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S S Square Construction.
Check it yourself on MahaRERA
- How to check the possession date of INARA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in Ward ABCD
- BURJ ASHRAFI
- AADITYA LUXURIA
- Shakuntala Sadan
- AL MEHDI HEIGHTS
- Meadows
- MEHTA SUNSHINE HEIGHTS B WING
- Shapoorji Pallonji The Odyssey 1
- ONYX
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.