by LIONDALE SKYSCRAPER LLP · Maldad West, Mumbai

Registered on MahaRERA under P51800077267, and currently active. Its completion date has moved from December 2025 to April 2027, 16 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

MahaRERA registration
P51800077267
Status
Registered and active
Builder
LIONDALE SKYSCRAPER LLP
Location
Maldad West, Mumbai · 400064
Project type
Residential / Group Housing
Registered on
2 Aug 2024
Completion date at registration
December 2025
Latest completion date
April 2027
Delay so far
16 months
Homes
23
Sold or booked
58%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

GharKundli’s full report on THE WEST

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Kundli Watch

THE WEST: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about THE WEST

Is THE WEST registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), THE WEST is registered as P51800077267 and its status is "Registered and active".

Where is THE WEST?

THE WEST by LIONDALE SKYSCRAPER LLP is in Maldad West, Mumbai (pincode 400064), Maharashtra, and is registered on MahaRERA as P51800077267, per GharKundli's check of MahaRERA records.

When is possession of THE WEST due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for THE WEST in Maldad West, Mumbai is 30 April 2027 — 16 months later than 31 December 2025, the date given at registration.

Does THE WEST have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of THE WEST?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LIONDALE SKYSCRAPER LLP.

Other projects in pincode 400064

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.