Contemporary Builder Private Limited Tardeo Project
by Contemporary builders private Limited · Tardeo, Mumbai 400034Also near Malabar Hill, mumbai central, Grant Road East
What’s in the report? →Possession date of Contemporary Builder Private Limited Tardeo Project (MahaRERA P51900014964): 30 April 2028, moved from 30 December 2023 (48 months later). It has 117 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900014964, and currently active. Its completion date has moved from December 2023 to April 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51900014964, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Contemporary Builder Private Limited Tardeo Project?
1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Contemporary Builder Private Limited Tardeo Project has moved
30 December 2023
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EXT51900025194)
Reason the builder gave MahaRERA:
“With reference to above we would like to state that project is fully completed in all respect. OC was received for our project except one flat no-1901 which is not sold by us. For Full occupation BMC requires single Property Card in owner’s…” Read the full reason
“With reference to above we would like to state that project is fully completed in all respect. OC was received for our project except one flat no-1901 which is not sold by us. For Full occupation BMC requires single Property Card in owner’s name. At present there are 2 different Property Card on which said project is completed. Tenure for property bearing CTS no-384 is Free of Assessment and Tenure for property bearing no-385 is Land Newly Assessed. Both CTS numbers of plots in our Company name. We further state that for amalgamation of CTS no-384 and 385 we already applied with SLR on 23rd…”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Contemporary Builder Private Limited Tardeo Project’s extension records on MahaRERA (P51900014964), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Contemporary Builder Private Limited Tardeo Project
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900014964
- Status
- Registered and active
- Builder
- Contemporary builders private Limited
- Location
- Tardeo, Mumbai · 400034
- Project type
- Others
- Registered on
- 15 Jan 2018
- Completion date at registration
- December 2023
- Latest completion date
- April 2028
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 117
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of Contemporary Builder Private Limited Tardeo Project, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Krishiv Tower | 100% | 100% | 100% | 95% |
| Shri Krishna Apartment | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Contemporary Builder Private Limited Tardeo Project every 1–2 months.
Contemporary Builder Private Limited Tardeo Project: buildings, flats and land, as filed on MahaRERA
- Buildings: Krishiv Tower (27 floors) · Shri Krishna Apartment (19 floors)
- Land: 1,601 sq m (about 0.4 acres) · sanctioned built-up 5,530 sq m · recreational space 126 sq m
- Land, as filed: 384 385 tardeo
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
City Estate Developers (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 6 months); 1 still being built, 1 past the promised date (typically 18 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of Contemporary Builder Private Limited Tardeo Project →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Contemporary Builder Private Limited Tardeo Project: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Contemporary Builder Private Limited Tardeo Project
What is the possession date of Contemporary Builder Private Limited Tardeo Project?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Contemporary Builder Private Limited Tardeo Project in Tardeo, Mumbai is 30 April 2028 — 48 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 48 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Contemporary Builder Private Limited Tardeo Project?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Contemporary Builder Private Limited Tardeo Project's builder has filed on MahaRERA, the official one, is 30 April 2028, already 48 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Contemporary Builder Private Limited Tardeo Project extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Contemporary Builder Private Limited Tardeo Project's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "With reference to above we would like to state that project is fully completed in all respect. OC was received for our project except one flat no-1901 which is not sold by us. For Full occupation BMC requires single Property Card in owner’s name. At present there are 2 different Property Card on which said project is completed. Tenure for property bearing CTS no-384 is Free of Assessment and Tenure for property bearing no-385 is Land Newly Assessed. Both CTS numbers of plots in our Company name. We further state that for amalgamation of CTS no-384 and 385 we already applied with SLR on 23rd…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Contemporary Builder Private Limited Tardeo Project?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Contemporary Builder Private Limited Tardeo Project in Tardeo, Mumbai is P51900014964.
Is Contemporary Builder Private Limited Tardeo Project registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Contemporary Builder Private Limited Tardeo Project is registered as P51900014964 and its status is "Registered and active".
What is the current construction status of Contemporary Builder Private Limited Tardeo Project? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Contemporary Builder Private Limited Tardeo Project's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Contemporary Builder Private Limited Tardeo Project have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Contemporary Builder Private Limited Tardeo Project safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Contemporary Builder Private Limited Tardeo Project is registered on MahaRERA as P51900014964, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Contemporary Builder Private Limited Tardeo Project?
Contemporary Builder Private Limited Tardeo Project is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Contemporary Builder Private Limited Tardeo Project?
For a flat in Contemporary Builder Private Limited Tardeo Project (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Contemporary Builder Private Limited Tardeo Project received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Contemporary Builder Private Limited Tardeo Project is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Contemporary Builder Private Limited Tardeo Project uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Contemporary Builder Private Limited Tardeo Project was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Contemporary Builder Private Limited Tardeo Project's possession date changes?
The latest dates are on Contemporary Builder Private Limited Tardeo Project's MahaRERA page (P51900014964). GharKundli's Kundli Watch sends a free WhatsApp update on Contemporary Builder Private Limited Tardeo Project every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Contemporary Builder Private Limited Tardeo Project have?
According to GharKundli's check of MahaRERA records (updated October 2026), Contemporary Builder Private Limited Tardeo Project has 2 buildings filed: Krishiv Tower with 27 floors; Shri Krishna Apartment with 19 floors.
How big is the land of Contemporary Builder Private Limited Tardeo Project?
According to GharKundli's check of MahaRERA records (updated October 2026), Contemporary Builder Private Limited Tardeo Project stands on 1,601 sq m of land (about 0.4 acres), with 5,530 sq m of sanctioned built-up area and 126 sq m of recreational open space.
What is the track record of Contemporary Builder Private Limited Tardeo Project's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), City Estate Developers (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 6 months); 1 still being built, 1 past the promised date (typically 18 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Contemporary Builder Private Limited Tardeo Project?
Google Maps has reviews of Contemporary Builder Private Limited Tardeo Project written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Contemporary Builder Private Limited Tardeo Project?
Contemporary Builder Private Limited Tardeo Project by Contemporary builders private Limited is in Tardeo, Mumbai, pincode 400034 (near Malabar Hill, mumbai central, Grant Road East), Maharashtra, and is registered on MahaRERA as P51900014964, per GharKundli's check of MahaRERA records. Its land is filed as 384 385 tardeo. GharKundli lists all 19 MahaRERA projects in Tardeo (400034).
How many flats are in Contemporary Builder Private Limited Tardeo Project?
According to GharKundli's check of MahaRERA records (updated October 2026), Contemporary Builder Private Limited Tardeo Project has 117 homes in 2 towers registered on MahaRERA.
When was Contemporary Builder Private Limited Tardeo Project registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Contemporary Builder Private Limited Tardeo Project was registered on MahaRERA on 15 January 2018. GharKundli did not find a title report on the land on file there.
Does Contemporary Builder Private Limited Tardeo Project have any legal issues or court cases?
1 court case is listed for Contemporary Builder Private Limited Tardeo Project on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Contemporary Builder Private Limited Tardeo Project?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Contemporary builders private Limited.
Check it yourself on MahaRERA
- How to check the possession date of Contemporary Builder Private Limited Tardeo Project
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai City →
Other projects in Tardeo (400034)
- Raheja Sobo Residences
- 25 Downtown-Wing 5-Amber Oasis
- Aplite Sapphire
- 25 Downtown – The Galleria
- Imperial T3 Wing C1
- Marq
- Imperial T3 Wing C
- The Imperial I
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.