Ashford Regal - Phase IV- Wing C Project
by WMI Real Estate Developers LLP · BHANDUP, Mumbai
Registered on MahaRERA under PM1183032400064, and currently active. Its completion date has moved from June 2029 to October 2029, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
- MahaRERA registration
- PM1183032400064
- Status
- Registered and active
- Builder
- WMI Real Estate Developers LLP
- Location
- BHANDUP, Mumbai · 400078
- Project type
- Mixed
- Registered on
- 8 Oct 2024
- Completion date at registration
- June 2029
- Latest completion date
- October 2029
- Delay so far
- 4 months
- Homes
- 279
- Sold or booked
- 74%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
GharKundli’s full report on Ashford Regal - Phase IV- Wing C Project
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Join Ashford Regal - Phase IV- Wing C Project’s buyer community
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Ashford Regal - Phase IV- Wing C Project
Is Ashford Regal - Phase IV- Wing C Project registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ashford Regal - Phase IV- Wing C Project is registered as PM1183032400064 and its status is "Registered and active".
When is possession of Ashford Regal - Phase IV- Wing C Project due?
According to GharKundli's check of MahaRERA records (updated October 2026), the completion date is October 2029, 4 months later than the June 2029 date given at registration.
Does Ashford Regal - Phase IV- Wing C Project have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Ashford Regal - Phase IV- Wing C Project?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is WMI Real Estate Developers LLP, which has 4 other projects registered on MahaRERA.
Other projects in pincode 400078
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.