by Aarav Developers (Ruparel) · Mulund West, Mumbai 400080Also near Mulund East

What’s in the report? →

Possession date of Ruparel Premia (MahaRERA P51800077584): 30 April 2028. It has 95 homes (1 BHK, 311–458 sq ft carpet), 46% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800077584, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800077584, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Ruparel Premia?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Ruparel Premia has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Ruparel Premia’s extension records on MahaRERA (P51800077584), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ruparel Premia

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800077584
Status
Registered and active
Builder
Aarav Developers
Location
Mulund West, Mumbai · 400080
Project type
Others
Registered on
15 Oct 2024
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
95
Sold or booked
46%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Ruparel Premia, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Ruparel Premia100%64%40%0%

Commencement certificate (CC), as filed on MahaRERA

  • Ruparel Premia: covers C.C. is further extended up to 4th upper floors of Sale Building u/ref. as per IOA dtd. 12/08/2024.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ruparel Premia every 1–2 months.

Ruparel Premia: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK311 – 45895
Shops217 – 1,0667
Other1,4491
  • Buildings: Ruparel Premia (22 floors, 103 units)
  • Land: 803 sq m (about 0.2 acres) · sanctioned built-up 4,339 sq m
  • Boundaries filed include: Jawahar lal Nehru Existing Road
  • Land, as filed: Plot No. 236B CTS No. 1456/A
  • Map: Get directions

The builder’s record and reviews

Ruparel Infra & Realty (a group of 13 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 26 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 47 months); 15 still being built, 9 past the promised date (typically 30 months late); 10 lapsed. 867 complaints on MahaRERA across 21 projects.

Read Google reviews of Ruparel Premia →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ruparel Premia: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Ruparel Premia

What is the possession date of Ruparel Premia?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ruparel Premia in Mulund West, Mumbai is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Ruparel Premia?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ruparel Premia's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Ruparel Premia?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ruparel Premia in Mulund West, Mumbai is P51800077584.

Is Ruparel Premia registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Premia is registered as P51800077584 and its status is "Registered and active".

What is the current construction status of Ruparel Premia? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Premia's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Ruparel Premia is 64% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.

Does Ruparel Premia have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Ruparel Premia safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Premia is registered on MahaRERA as P51800077584, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Ruparel Premia?

Ruparel Premia is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Ruparel Premia are 311 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Ruparel Premia?

For a flat in Ruparel Premia (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Ruparel Premia received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Premia is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Ruparel Premia uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ruparel Premia was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Ruparel Premia's possession date changes?

The latest dates are on Ruparel Premia's MahaRERA page (P51800077584). GharKundli's Kundli Watch sends a free WhatsApp update on Ruparel Premia every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ruparel Premia have?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Premia has one building filed: Ruparel Premia with 22 floors and 103 units.

What are the flat sizes (carpet area) in Ruparel Premia?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Ruparel Premia: 1 BHK: 311 to 458 sq ft carpet (95 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Ruparel Premia?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Premia stands on 803 sq m of land (about 0.2 acres), with 4,339 sq m of sanctioned built-up area.

What is the track record of Ruparel Premia's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Infra & Realty (a group of 13 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 26 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 47 months); 15 still being built, 9 past the promised date (typically 30 months late); 10 lapsed. 867 complaints on MahaRERA across 21 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Ruparel Premia?

Google Maps has reviews of Ruparel Premia written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Ruparel Premia?

Ruparel Premia by Aarav Developers (Ruparel) is in Mulund West, Mumbai, pincode 400080 (near Mulund East), Maharashtra, and is registered on MahaRERA as P51800077584, per GharKundli's check of MahaRERA records. Its boundaries filed there include Jawahar lal Nehru Existing Road. Its land is filed as Plot No. 236B CTS No. 1456/A. GharKundli lists all 303 MahaRERA projects in Mulund West (400080).

How many flats are in Ruparel Premia, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Premia has 95 homes in 1 tower registered on MahaRERA, and 46% of them are sold or booked.

When was Ruparel Premia registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Premia was registered on MahaRERA on 15 October 2024. GharKundli did not find a title report on the land on file there.

Does Ruparel Premia have any legal issues or court cases?

No court cases are listed for Ruparel Premia on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Ruparel Premia?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Aarav Developers, the company Ruparel files this project under.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Mulund West (400080)

All 303 projects in Mulund West (400080) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.