SIGNATURE
by MANGAL BUILDHOME PRIVATE LIMITED · Vile Parle, MumbaiAlso near Vileparle east, Andheri West, Borivali West
Possession date of SIGNATURE: 31 July 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800078445, and currently active. Its completion date is now July 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SIGNATURE?
How the possession date of SIGNATURE has moved
31 March 2028
Completion date given when the project was registered
31 July 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SIGNATURE’s extension records on MahaRERA (P51800078445), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SIGNATURE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 1 court case, and how it ended
- Construction pace against the July 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800078445
- Status
- Registered and active
- Builder
- MANGAL BUILDHOME PRIVATE LIMITED
- Location
- Vile Parle, Mumbai · 400057
- Project type
- Others
- Registered on
- 12 Dec 2024
- Completion date at registration
- March 2028
- Latest completion date
- July 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 120
- Sold or booked
- 48%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of SIGNATURE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING N0 1 WING A B C | 100% | 55% | 10% | 0% |
| BUILDING NO 2 WING D E F | 100% | 65% | 10% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING N0 1 WING A B C: covers 9 floors
- BUILDING NO 2 WING D E F: covers 9 floors
Latest CC order on MahaRERA: dated 17/06/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SIGNATURE every month.
SIGNATURE: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 583 – 818 | 40 |
| 1 BHK | 281 – 575 | 27 |
| Multi Purpose Room | 103 – 653 | 18 |
| 3 BHK | 911 – 1,290 | 17 |
| 4 BHK | 1,323 – 1,902 | 8 |
| 1 Room Kitchen | 228 – 308 | 7 |
| Shops | 260 – 1,286 | 4 |
| 5 BHK | 2,419 – 2,589 | 3 |
- Buildings: BUILDING N0 1 WING A B C (10 floors, 79 units) · BUILDING NO 2 WING D E F (9 floors, 45 units)
- Car parking: 114 covered, 13 open
- Land: 3,004 sq m (about 0.7 acres) · sanctioned built-up 8,847 sq m · recreational space 547 sq m
- Boundaries filed include: G B INDULKAR MARG, SUBHASH ROAD, PARANJPE SCHEME ROAD NO 2
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Mangal Buildhome has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 2 finished, all within the promised date; 4 still being built, 1 past the promised date (typically 46 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of SIGNATURE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SIGNATURE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SIGNATURE
What is the possession date of SIGNATURE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SIGNATURE in Vile Parle, Mumbai is 31 July 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SIGNATURE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SIGNATURE's builder has filed on MahaRERA, the official one, is 31 July 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SIGNATURE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SIGNATURE in Vile Parle, Mumbai is P51800078445.
Is SIGNATURE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SIGNATURE is registered as P51800078445 and its status is "Registered and active".
What is the construction status of SIGNATURE?
According to GharKundli's check of MahaRERA records (updated October 2026), SIGNATURE's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 55% to 65% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does SIGNATURE have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SIGNATURE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SIGNATURE is registered on MahaRERA as P51800078445, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SIGNATURE's possession date changes?
The latest dates are on SIGNATURE's MahaRERA page (P51800078445). GharKundli's Kundli Watch sends a free WhatsApp update on SIGNATURE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SIGNATURE have?
According to GharKundli's check of MahaRERA records (updated October 2026), SIGNATURE has 2 buildings filed: BUILDING N0 1 WING A B C with 10 floors and 79 units; BUILDING NO 2 WING D E F with 9 floors and 45 units.
What are the flat sizes (carpet area) in SIGNATURE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SIGNATURE: 2 BHK: 583 to 818 sq ft carpet (40 homes); 1 BHK: 281 to 575 sq ft carpet (27 homes); Multi Purpose Room: 103 to 653 sq ft carpet (18 homes); 3 BHK: 911 to 1290 sq ft carpet (17 homes); 4 BHK: 1323 to 1902 sq ft carpet (8 homes); 1 Room Kitchen: 228 to 308 sq ft carpet (7 homes); 5 BHK: 2419 to 2589 sq ft carpet (3 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does SIGNATURE have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 114 covered and 13 open car parking spaces for SIGNATURE.
How big is the land of SIGNATURE?
According to GharKundli's check of MahaRERA records (updated October 2026), SIGNATURE stands on 3,004 sq m of land (about 0.7 acres), with 8,847 sq m of sanctioned built-up area and 547 sq m of recreational open space.
What is the track record of SIGNATURE's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Mangal Buildhome has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 2 finished, all within the promised date; 4 still being built, 1 past the promised date (typically 46 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SIGNATURE?
Google Maps has reviews of SIGNATURE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SIGNATURE?
SIGNATURE by MANGAL BUILDHOME PRIVATE LIMITED is in Vile Parle, Mumbai (pincode 400057), near Vileparle east, Andheri West, Borivali West, Maharashtra, and is registered on MahaRERA as P51800078445, per GharKundli's check of MahaRERA records. Its boundaries filed there include G B INDULKAR MARG, SUBHASH ROAD, PARANJPE SCHEME ROAD NO 2.
How many homes are in SIGNATURE?
According to GharKundli's check of MahaRERA records (updated October 2026), SIGNATURE has 120 homes in 2 towers registered on MahaRERA, and 48% of them are sold or booked.
When was SIGNATURE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SIGNATURE was registered on MahaRERA on 12 December 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on SIGNATURE?
1 court case is listed for SIGNATURE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SIGNATURE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MANGAL BUILDHOME PRIVATE LIMITED, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SIGNATURE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in pincode 400057
- Shubhada Co-operative Housing Society Ltd.
- Neumec godawari
- PEARL HERITAGE
- ZODIAC ANJANESHWAR
- ARHAM HERITAGE
- PARIMAL
- Munisuvrat Chhaya
- Pruthvi Symphony
Other projects by MANGAL BUILDHOME PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.