by ROHA REALTY PRIVATE LIMITED (Vida) · Chembur, Mumbai 400071Also near Fci

What’s in the report? →

Possession date of Eva Aspire (MahaRERA P51800079400): 30 April 2028. It has 150 homes (1 BHK and 2 BHK, 373–706 sq ft carpet), 18% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800079400, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800079400, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Eva Aspire?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Eva Aspire has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Eva Aspire’s extension records on MahaRERA (P51800079400), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Eva Aspire

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800079400
Status
Registered and active
Builder
ROHA REALTY PRIVATE LIMITED
Location
Chembur, Mumbai · 400071
Project type
Commercial
Registered on
3 Mar 2025
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
150
Sold or booked
18%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Eva Aspire, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
EVA ASPIRE100%100%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • EVA ASPIRE: covers PLINTH LEVEL

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Eva Aspire every 1–2 months.

Eva Aspire: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK373 – 61787
1 BHK373 – 39153
Shops128 – 36715
Other70610
  • Buildings: EVA ASPIRE (1 floors, 165 units)
  • Land: 1,598 sq m (about 0.4 acres)
  • Land, as filed: CTS No 828 (pt)
  • Map: Get directions

The builder’s record and reviews

Vida Infrahub (a group of 5 linked companies) has 8 projects on MahaRERA since 2021, this one included. Of the 8 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 8 months); 6 still being built, none past the promised date yet. 5 complaints on MahaRERA across 3 projects.

Read Google reviews of Eva Aspire →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Eva Aspire: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Eva Aspire

What is the possession date of Eva Aspire?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Eva Aspire in Chembur, Mumbai is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Eva Aspire?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Eva Aspire's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Eva Aspire?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Eva Aspire in Chembur, Mumbai is P51800079400.

Is Eva Aspire registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Eva Aspire is registered as P51800079400 and its status is "Registered and active".

What is the current construction status of Eva Aspire? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Eva Aspire's status on MahaRERA is "Registered and active". As filed by the builder, slab work on EVA ASPIRE is 100% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Eva Aspire have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Eva Aspire safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Eva Aspire is registered on MahaRERA as P51800079400, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Eva Aspire?

Eva Aspire is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Eva Aspire are 373 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Eva Aspire?

For a flat in Eva Aspire (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Eva Aspire received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Eva Aspire is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Eva Aspire uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Eva Aspire was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Eva Aspire's possession date changes?

The latest dates are on Eva Aspire's MahaRERA page (P51800079400). GharKundli's Kundli Watch sends a free WhatsApp update on Eva Aspire every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Eva Aspire have?

According to GharKundli's check of MahaRERA records (updated October 2026), Eva Aspire has one building filed: EVA ASPIRE with 1 floors and 165 units.

What are the flat sizes (carpet area) in Eva Aspire?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Eva Aspire: 2 BHK: 373 to 617 sq ft carpet (87 homes); 1 BHK: 373 to 391 sq ft carpet (53 homes); Other: 706 sq ft carpet (10 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Eva Aspire?

According to GharKundli's check of MahaRERA records (updated October 2026), Eva Aspire stands on 1,598 sq m of land (about 0.4 acres).

What is the track record of Eva Aspire's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vida Infrahub (a group of 5 linked companies) has 8 projects on MahaRERA since 2021, this one included. Of the 8 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 8 months); 6 still being built, none past the promised date yet. 5 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Eva Aspire?

Google Maps has reviews of Eva Aspire written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Eva Aspire?

Eva Aspire by ROHA REALTY PRIVATE LIMITED (Vida) is in Chembur, Mumbai, pincode 400071 (near Fci), Maharashtra, and is registered on MahaRERA as P51800079400, per GharKundli's check of MahaRERA records. Its land is filed as CTS No 828 (pt). GharKundli lists all 318 MahaRERA projects in Chembur (400071).

How many flats are in Eva Aspire, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Eva Aspire has 150 homes in 1 tower registered on MahaRERA, and 18% of them are sold or booked.

When was Eva Aspire registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Eva Aspire was registered on MahaRERA on 3 March 2025. GharKundli did not find a title report on the land on file there.

Does Eva Aspire have any legal issues or court cases?

No court cases are listed for Eva Aspire on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Eva Aspire?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ROHA REALTY PRIVATE LIMITED, the company Vida files this project under, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Chembur (400071)

All 318 projects in Chembur (400071) →

Other projects by ROHA REALTY PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.