by SSD HOUSING LLP (Notan) · Juhu, Vile Parle West, Mumbai 400049Also near JVPD Scheme, Santacruz West, Vileparle West

What’s in the report? →

Possession date of Notan DC (MahaRERA PR1180002501929): 30 January 2030. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1180002501929, and currently active. Its completion date is now January 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1180002501929, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Notan DC?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Notan DC has moved

  1. 30 September 2029

    Completion date given when the project was registered

  2. 30 January 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Notan DC’s extension records on MahaRERA (PR1180002501929), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Notan DC

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1180002501929
Status
Registered and active
Builder
SSD HOUSING LLP
Location
Juhu, Vile Parle West, Mumbai · 400049
Project type
Residential / Group Housing
Registered on
29 Dec 2025
Completion date at registration
September 2029
Latest completion date
January 2030
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Notan DC, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NOTAN DC0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • NOTAN DC: covers Plinth C.C. for work up to Top of Stilt level

Latest CC order on MahaRERA: dated 03/10/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Notan DC every 1–2 months.

Notan DC: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Notan House (a group of 8 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 14 months); 6 still being built, 1 past the promised date (typically 82 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Notan DC →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Notan DC: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Notan DC

What is the possession date of Notan DC?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Notan DC in Juhu, Vile Parle West, Mumbai is 30 January 2030, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Notan DC?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Notan DC's builder has filed on MahaRERA, the official one, is 30 January 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Notan DC?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Notan DC in Juhu, Vile Parle West, Mumbai is PR1180002501929.

Is Notan DC registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Notan DC is registered as PR1180002501929 and its status is "Registered and active".

What is the current construction status of Notan DC? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Notan DC's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NOTAN DC is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Notan DC have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Notan DC safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Notan DC is registered on MahaRERA as PR1180002501929, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Notan DC?

Notan DC is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Notan DC?

For a flat in Notan DC (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Notan DC received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Notan DC is still under construction, with 30 January 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Notan DC a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Notan DC's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Notan DC uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Notan DC was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Notan DC's possession date changes?

The latest dates are on Notan DC's MahaRERA page (PR1180002501929). GharKundli's Kundli Watch sends a free WhatsApp update on Notan DC every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Notan DC have?

According to GharKundli's check of MahaRERA records (updated October 2026), Notan DC has one building filed: NOTAN DC with 3 floors.

How big is the land of Notan DC?

According to GharKundli's check of MahaRERA records (updated October 2026), Notan DC stands on 670 sq m of land (about 0.2 acres).

What is the track record of Notan DC's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Notan House (a group of 8 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 14 months); 6 still being built, 1 past the promised date (typically 82 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Notan DC?

Google Maps has reviews of Notan DC written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Notan DC?

Notan DC by SSD HOUSING LLP (Notan) is in Juhu, Vile Parle West, Mumbai, pincode 400049 (near JVPD Scheme, Santacruz West, Vileparle West), Maharashtra, and is registered on MahaRERA as PR1180002501929, per GharKundli's check of MahaRERA records. GharKundli lists all 78 MahaRERA projects in Juhu (400049).

When was Notan DC registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Notan DC was registered on MahaRERA on 29 December 2025. GharKundli did not find a title report on the land on file there.

Does Notan DC have any legal issues or court cases?

No court cases are listed for Notan DC on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Notan DC?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SSD HOUSING LLP, the company Notan files this project under.

All projects with possession due in 2030 in Mumbai Suburban →

Other projects in Juhu (400049)

All 78 projects in Juhu (400049) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.