by MINDSET BUILDCON · Mulund West, MumbaiAlso near Bhandup West, Mulund East, Off Dmart
Possession date of AUM LAXMI KUSUM: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800079984, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about AUM LAXMI KUSUM?
How the possession date of AUM LAXMI KUSUM has moved
30 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: AUM LAXMI KUSUM’s extension records on MahaRERA (P51800079984), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on AUM LAXMI KUSUM
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800079984
- Status
- Registered and active
- Builder
- MINDSET BUILDCON
- Location
- Mulund West, Mumbai · 400080
- Project type
- Residential / Group Housing
- Registered on
- 11 Apr 2025
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 145
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of AUM LAXMI KUSUM, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| AUM LAXMI KUSUM | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on AUM LAXMI KUSUM every month.
AUM LAXMI KUSUM: buildings, flats and land, as filed on MahaRERA
- Buildings: AUM LAXMI KUSUM (26 floors)
- Land: 1,565 sq m (about 0.4 acres) · sanctioned built-up 6,800 sq m · recreational space 145 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of AUM LAXMI KUSUM →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
AUM LAXMI KUSUM: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about AUM LAXMI KUSUM
What is the possession date of AUM LAXMI KUSUM?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AUM LAXMI KUSUM in Mulund West, Mumbai is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for AUM LAXMI KUSUM?
Builders and listing sites often quote an earlier "target" date for handover. The completion date AUM LAXMI KUSUM's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of AUM LAXMI KUSUM?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AUM LAXMI KUSUM in Mulund West, Mumbai is P51800079984.
Is AUM LAXMI KUSUM registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AUM LAXMI KUSUM is registered as P51800079984 and its status is "Registered and active".
What is the construction status of AUM LAXMI KUSUM?
According to GharKundli's check of MahaRERA records (updated October 2026), AUM LAXMI KUSUM's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AUM LAXMI KUSUM is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does AUM LAXMI KUSUM have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is AUM LAXMI KUSUM safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), AUM LAXMI KUSUM is registered on MahaRERA as P51800079984, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if AUM LAXMI KUSUM's possession date changes?
The latest dates are on AUM LAXMI KUSUM's MahaRERA page (P51800079984). GharKundli's Kundli Watch sends a free WhatsApp update on AUM LAXMI KUSUM every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does AUM LAXMI KUSUM have?
According to GharKundli's check of MahaRERA records (updated October 2026), AUM LAXMI KUSUM has one building filed: AUM LAXMI KUSUM with 26 floors.
How big is the land of AUM LAXMI KUSUM?
According to GharKundli's check of MahaRERA records (updated October 2026), AUM LAXMI KUSUM stands on 1,565 sq m of land (about 0.4 acres), with 6,800 sq m of sanctioned built-up area and 145 sq m of recreational open space.
Where can I read reviews of AUM LAXMI KUSUM?
Google Maps has reviews of AUM LAXMI KUSUM written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is AUM LAXMI KUSUM?
AUM LAXMI KUSUM by MINDSET BUILDCON is in Mulund West, Mumbai (pincode 400080), near Bhandup West, Mulund East, Off Dmart, Maharashtra, and is registered on MahaRERA as P51800079984, per GharKundli's check of MahaRERA records.
How many homes are in AUM LAXMI KUSUM?
According to GharKundli's check of MahaRERA records (updated October 2026), AUM LAXMI KUSUM has 145 homes in 1 tower registered on MahaRERA.
When was AUM LAXMI KUSUM registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AUM LAXMI KUSUM was registered on MahaRERA on 11 April 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on AUM LAXMI KUSUM?
No court cases are listed for AUM LAXMI KUSUM on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of AUM LAXMI KUSUM?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MINDSET BUILDCON.
Check it yourself on MahaRERA
- How to check the possession date of AUM LAXMI KUSUM
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai Suburban →
Other projects in pincode 400080
- OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.
- Keshavpada
- ARIHANT ROYALE
- THE SANCTUARY - TOWER 5
- Dhanraj Tower
- Madhuvan Nivanta
- Shraddha Paradise Enclave
- Malhar Guide
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.