by Elite Lifespaces · New Tilak Nagar Chembur, MumbaiAlso near Nehru nagar, Bhandup West, Kurla East
Possession date of SHUBH: 30 September 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1180002500062, and currently active. Its completion date is now September 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHUBH?
How the possession date of SHUBH has moved
31 May 2029
Completion date given when the project was registered
30 September 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SHUBH’s extension records on MahaRERA (PR1180002500062), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHUBH
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the September 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1180002500062
- Status
- Registered and active
- Builder
- Elite Lifespaces
- Location
- New Tilak Nagar Chembur, Mumbai · 400089
- Project type
- Residential / Group Housing
- Registered on
- 2 Jun 2025
- Completion date at registration
- May 2029
- Latest completion date
- September 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Towers
- 3
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SHUBH, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A-Wing, B-Wing and C-Wing / A Wing | 70% | 0% | 0% | 0% |
| A-Wing, B-Wing and C-Wing / B Wing | 70% | 0% | 0% | 0% |
| A-Wing, B-Wing and C-Wing / C Wing | 70% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- A-Wing, B-Wing and C-Wing: covers 2 floors
- A-Wing, B-Wing and C-Wing: covers 2 floors
- A-Wing, B-Wing and C-Wing: covers 2 floors
Latest CC order on MahaRERA: dated 14/05/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHUBH every month.
SHUBH: buildings, flats and land, as filed on MahaRERA
- Buildings: A-Wing, B-Wing and C-Wing (2 floors) · A-Wing, B-Wing and C-Wing (2 floors) · A-Wing, B-Wing and C-Wing (2 floors)
- Land: 1,260 sq m (about 0.3 acres)
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Elite Lifespaces (a group of 2 linked companies) has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project.
Read Google reviews of SHUBH →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHUBH: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHUBH
What is the possession date of SHUBH?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHUBH in New Tilak Nagar Chembur, Mumbai is 30 September 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SHUBH?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHUBH's builder has filed on MahaRERA, the official one, is 30 September 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SHUBH?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHUBH in New Tilak Nagar Chembur, Mumbai is PR1180002500062.
Is SHUBH registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBH is registered as PR1180002500062 and its status is "Registered and active".
What is the construction status of SHUBH?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBH's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does SHUBH have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SHUBH safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBH is registered on MahaRERA as PR1180002500062, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHUBH's possession date changes?
The latest dates are on SHUBH's MahaRERA page (PR1180002500062). GharKundli's Kundli Watch sends a free WhatsApp update on SHUBH every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHUBH have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBH has 3 buildings filed: A-Wing, B-Wing and C-Wing with 2 floors; A-Wing, B-Wing and C-Wing with 2 floors; A-Wing, B-Wing and C-Wing with 2 floors.
How big is the land of SHUBH?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBH stands on 1,260 sq m of land (about 0.3 acres).
What is the track record of SHUBH's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Elite Lifespaces (a group of 2 linked companies) has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHUBH?
Google Maps has reviews of SHUBH written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHUBH?
SHUBH by Elite Lifespaces is in New Tilak Nagar Chembur, Mumbai (pincode 400089), near Nehru nagar, Bhandup West, Kurla East, Maharashtra, and is registered on MahaRERA as PR1180002500062, per GharKundli's check of MahaRERA records.
When was SHUBH registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHUBH was registered on MahaRERA on 2 June 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on SHUBH?
No court cases are listed for SHUBH on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SHUBH?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Elite Lifespaces.
Check it yourself on MahaRERA
- How to check the possession date of SHUBH
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai Suburban →
Other projects in Kurla
- SUDHANSHU HEIGHTS
- Saptashringi
- Jai Arihant
- Kalyan Kutir Co-operative Housing Society Limited
- Heritage Lakeside
- Kanakdhara
- Privilon
- Valentina CHS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.