by PUNEET EDIFICE PVT LTD · Vikhroli East, MumbaiAlso near kanamwar Nagar, Tagore Nagar, Hariyali, Vikhroli

Possession date of Puneet Allure: 30 April 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1180002500687, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Puneet Allure?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Puneet Allure has moved

  1. 31 December 2029

    Completion date given when the project was registered

  2. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Puneet Allure’s extension records on MahaRERA (PR1180002500687), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Puneet Allure

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1180002500687
Status
Registered and active
Builder
PUNEET EDIFICE PVT LTD
Location
Vikhroli East, Mumbai · 400083
Project type
Residential / Group Housing
Registered on
1 Sep 2025
Completion date at registration
December 2029
Latest completion date
April 2030
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of Puneet Allure, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MH/EE/(B.P.)GM/MHADA-9/1635/20240%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • MH/EE/(B.P.)GM/MHADA-9/1635/2024: covers plinth

Latest CC order on MahaRERA: dated 07/03/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Puneet Allure every month.

Puneet Allure: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Puneet Edifice (a group of 3 linked companies) has 9 projects on MahaRERA since 2019, this one included. Of the 9 GharKundli has checked: 5 still being built, 1 past the promised date (typically 6 months late); 4 lapsed. 7 complaints on MahaRERA across 3 projects.

Read Google reviews of Puneet Allure →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Puneet Allure: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Puneet Allure

What is the possession date of Puneet Allure?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Puneet Allure in Vikhroli East, Mumbai is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Puneet Allure?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Puneet Allure's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Puneet Allure?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Puneet Allure in Vikhroli East, Mumbai is PR1180002500687.

Is Puneet Allure registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Puneet Allure is registered as PR1180002500687 and its status is "Registered and active".

What is the construction status of Puneet Allure?

According to GharKundli's check of MahaRERA records (updated October 2026), Puneet Allure's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MH/EE/(B.P.)GM/MHADA-9/1635/2024 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Puneet Allure have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Puneet Allure safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Puneet Allure is registered on MahaRERA as PR1180002500687, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Puneet Allure's possession date changes?

The latest dates are on Puneet Allure's MahaRERA page (PR1180002500687). GharKundli's Kundli Watch sends a free WhatsApp update on Puneet Allure every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of Puneet Allure?

According to GharKundli's check of MahaRERA records (updated October 2026), Puneet Allure stands on 661 sq m of land (about 0.2 acres).

What is the track record of Puneet Allure's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Puneet Edifice (a group of 3 linked companies) has 9 projects on MahaRERA since 2019, this one included. Of the 9 GharKundli has checked: 5 still being built, 1 past the promised date (typically 6 months late); 4 lapsed. 7 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Puneet Allure?

Google Maps has reviews of Puneet Allure written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Puneet Allure?

Puneet Allure by PUNEET EDIFICE PVT LTD is in Vikhroli East, Mumbai (pincode 400083), near kanamwar Nagar, Tagore Nagar, Hariyali, Vikhroli, Maharashtra, and is registered on MahaRERA as PR1180002500687, per GharKundli's check of MahaRERA records.

When was Puneet Allure registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Puneet Allure was registered on MahaRERA on 1 September 2025. GharKundli did not find a title report on the land on file there.

Are there court cases on Puneet Allure?

No court cases are listed for Puneet Allure on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Puneet Allure?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PUNEET EDIFICE PVT LTD, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2030 in Mumbai Suburban →

Other projects in Vikhroli East

All 176 projects in Vikhroli East (400083) →

Other projects by PUNEET EDIFICE PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.