Skip to content
GharKundli

Axiom Vrindavan

by AXIOM REFAB CONSTRUCTION (INDIA) PVT LTD · Mulund West, Mumbai 400080Also near Bhandup West, Nahur, Chembur West

What’s in the report? →

Possession date of Axiom Vrindavan (MahaRERA P51800080260): 31 July 2030. It has 64 homes (2 BHK and 3 BHK, 542–820 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800080260, and currently active. Its completion date is now July 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800080260, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Axiom Vrindavan?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Axiom Vrindavan has moved

  1. 31 March 2030

    Completion date given when the project was registered

  2. 31 July 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Axiom Vrindavan’s extension records on MahaRERA (P51800080260), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Axiom Vrindavan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800080260
Status
Registered and active
Builder
AXIOM REFAB CONSTRUCTION (INDIA) PVT LTD
Location
Mulund West, Mumbai · 400080
Project type
Residential / Group Housing
Registered on
15 May 2025
Completion date at registration
March 2030
Latest completion date
July 2030
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
64
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Axiom Vrindavan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AXIOM VRINDAVAN100%4%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • AXIOM VRINDAVAN: covers PLINTH

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Axiom Vrindavan every 1–2 months.

Axiom Vrindavan: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK542 – 66056
3 BHK8208
Shops238 – 4983
Office Space716 – 1,1532

The builder’s record and reviews

Axiom Refab Construction has 7 projects on MahaRERA since 2021, this one included. Of the 7 GharKundli has checked: 2 finished, all within the promised date; 5 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of Axiom Vrindavan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Axiom Vrindavan: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Axiom Vrindavan

What is the possession date of Axiom Vrindavan?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Axiom Vrindavan in Mulund West, Mumbai is 31 July 2030, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Axiom Vrindavan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Axiom Vrindavan's builder has filed on MahaRERA, the official one, is 31 July 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Axiom Vrindavan?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Axiom Vrindavan in Mulund West, Mumbai is P51800080260.

Is Axiom Vrindavan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Axiom Vrindavan is registered as P51800080260 and its status is "Registered and active".

What is the current construction status of Axiom Vrindavan? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Axiom Vrindavan's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AXIOM VRINDAVAN is 4% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Axiom Vrindavan have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Axiom Vrindavan safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Axiom Vrindavan is registered on MahaRERA as P51800080260, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Axiom Vrindavan?

Axiom Vrindavan is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Axiom Vrindavan are 542 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Axiom Vrindavan?

For a flat in Axiom Vrindavan (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Axiom Vrindavan received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Axiom Vrindavan is still under construction, with 31 July 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Axiom Vrindavan uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Axiom Vrindavan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Axiom Vrindavan's possession date changes?

The latest dates are on Axiom Vrindavan's MahaRERA page (P51800080260). GharKundli's Kundli Watch sends a free WhatsApp update on Axiom Vrindavan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Axiom Vrindavan have?

According to GharKundli's check of MahaRERA records (updated October 2026), Axiom Vrindavan has one building filed: AXIOM VRINDAVAN with 29 floors and 69 units.

What are the flat sizes (carpet area) in Axiom Vrindavan?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Axiom Vrindavan: 2 BHK: 542 to 660 sq ft carpet (56 homes); 3 BHK: 820 sq ft carpet (8 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Axiom Vrindavan?

According to GharKundli's check of MahaRERA records (updated October 2026), Axiom Vrindavan stands on 841 sq m of land (about 0.2 acres), with 4,524 sq m of sanctioned built-up area.

What is the track record of Axiom Vrindavan's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Axiom Refab Construction has 7 projects on MahaRERA since 2021, this one included. Of the 7 GharKundli has checked: 2 finished, all within the promised date; 5 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Axiom Vrindavan?

Google Maps has reviews of Axiom Vrindavan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Axiom Vrindavan?

Axiom Vrindavan by AXIOM REFAB CONSTRUCTION (INDIA) PVT LTD is in Mulund West, Mumbai, pincode 400080 (near Bhandup West, Nahur, Chembur West), Maharashtra, and is registered on MahaRERA as P51800080260, per GharKundli's check of MahaRERA records. Its boundaries filed there include GOSHALA ROAD, INTERNAL LAYOUT ROAD. Its land is filed as 569/8. GharKundli lists all 303 MahaRERA projects in Mulund West (400080).

How many flats are in Axiom Vrindavan, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Axiom Vrindavan has 64 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Axiom Vrindavan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Axiom Vrindavan was registered on MahaRERA on 15 May 2025. GharKundli did not find a title report on the land on file there.

Does Axiom Vrindavan have any legal issues or court cases?

No court cases are listed for Axiom Vrindavan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Axiom Vrindavan?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AXIOM REFAB CONSTRUCTION (INDIA) PVT LTD, which has 5 other projects registered on MahaRERA.

All projects with possession due in 2030 in Mumbai Suburban →

Other projects in Mulund West (400080)

All 303 projects in Mulund West (400080) →

Other projects by AXIOM REFAB CONSTRUCTION (INDIA) PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.